Touchstone Exploration advances Cascadura development with Cas-4ST2X and Cas-5 wells

Touchstone Exploration

Touchstone Exploration Inc. (LON:TXP) provides an operational update on its Ortoire block activities, including drilling results from the Cascadura-4 development well.

Cas-4ST2X Well Results

Operations at Cascadura-4ST2 resumed on August 16, 2025, utilizing Star Valley Drilling Rig #205, and the well reached a total depth of 5,896 feet on September 22, 2025. The well, now designated Cascadura-4ST2X, was originally programmed to evaluate the Herrera Gr7bc sands to a depth of approximately 6,100 feet. However, after encountering gas-charged sands in the lower portion of the well, circulation was lost, leading the Company to conclude drilling operations earlier than planned.

During the pull-out, the drill string became stuck and, despite extensive recovery efforts, could not be freed. The Company has elected to complete the well for production using a combination of casing and the drill string, enabling access to the gas-charged intervals identified while drilling. Although open-hole logs could not be acquired, offset well data and real-time drilling information confirm that the well intersected Herrera Gr7bc sands consistent with the Company’s geological model.

The primary objective of the well was the Herrera Gr7bc sands, which are widespread across the Cascadura structure. Cascadura-4ST2X represents the third well drilled into the “A” block of Cascadura to encounter sands within the targeted reservoir.

Cascadura Development

Completion operations on the Cascadura-5 well will immediately commence. All tie-in equipment is on location and the well will be tested directly through the Cascadura natural gas facility following completion. Cas-4ST2X will undergo final completion and tie-in once equipment and a service rig are on site.

Following completion of Pad B operations, the drilling rig will move to the Central block location identified as Carapal Ridge-3 (“CR-3”), where site construction is approximately 60 percent complete. The location is expected to be drill-ready by the end of October.

In parallel, the Company has secured a compressor for the Cascadura facility to further enhance natural gas processing. The project is currently expected to be completed in the second quarter of 2025.

Paul R. Baay, President and Chief Executive Officer, commented:

With drilling complete on Pad B at Cascadura, we are moving rapidly into the completion and tie-in phase.

While Cas-4ST2X presented challenges due to re-entering a previous wellbore, the systems implemented on the Cas-5 well have proven effective. We remain confident in our ability to drive repeatable cost and efficiency gains at Cascadura and across our Central block program.

Production update

Production volumes averaged 5,152 boe/d in August 2025, compared with 5,300 boe/d in July and 5,088 boe/d in June. August volumes comprised 21.7 MMcf/d of net natural gas production (3,623 boe/d) and 1,529 bbls/d of net crude oil and liquids production.

Strategic Divestiture

Touchstone Exploration has entered into a sale and purchase agreement to dispose of its non-core Fyzabad oil property to a third-party Trinidad-based company. Fyzabad averaged 37 bbls/d of net production in August 2025 and had limited scalability within the Company’s portfolio.

Transaction consideration consists of three turnkey drilling wells to be drilled across Touchstone’s WD-8 and WD-4 blocks. Under the agreement, the purchaser will drill the wells while Touchstone supplies certain ancillary drilling and completion equipment.

Two wells are currently scheduled for drilling before year-end 2025, with the third well planned for the first quarter of 2026. Closing of the Fyzabad disposition is expected in the fourth quarter of 2025, subject to customary regulatory approvals.

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Touchstone Exploration advances Cascadura development with Cas-4ST2X and Cas-5 wells

Touchstone Exploration has provided an operational update on its Ortoire block, confirming gas-bearing sands at the Cascadura-4ST2X well and the start of completion work on Cascadura-5.

Touchstone Exploration Q2 2025 Performance Update

Touchstone Exploration Inc. recorded average production of 4,399 boe/d in Q2 2025, supported by its acquisition of Shell Trinidad Central Block Limited.

Touchstone Exploration Q2 production up at Central Block

Touchstone Exploration reports that following its 16 May 2025 acquisition of Shell Trinidad Central Block Ltd it delivered quarter-over-quarter production growth at the Central Block licence in Trinidad and Tobago.

Touchstone Exploration completes Cascadura 5 well, confirms hydrocarbon sands

Touchstone has drilled the Cascadura-5 well to 7 020 ft, encountering approximately 620 ft of Herrera Gr7bc sands with continuous hydrocarbon indicators, and will mobilise to Cascadura-4 once funding is secured.

Touchstone Exploration awaits £10.3m private placement settlement

Touchstone Exploration Inc. updates on its £15.375 million private placement, detailing progress and outstanding funds expected by June 20, 2025.

Touchstone Exploration completes $28.4m Trinidad acquisition

Touchstone Exploration Inc. has successfully acquired Shell Trinidad Central Block Limited, enhancing its production capabilities and expanding its asset portfolio in Trinidad.

Search

Search