Firering Strategic Minerals reports first quicklime sales in Zambia

Firering Strategic Minerals plc (LON:FRG), an emerging producer of quicklime and explorer of critical minerals, has announced that its Zambian quicklime operation, Limeco Resources Limited, has recorded its first sales of high-purity quicklime. In parallel, upgrade work on the next three of the site’s eight kilns (Kilns 2-4) is now underway, marking the next phase of operational ramp-up.

Highlights

·    First quicklime sales secured to local and regional customers.

·    Optimisation of Kiln 1 is ongoing with high-quality quicklime being produced.

·    Work has commenced on modifying and commissioning Kiln 2, followed by Kiln 3 and then Kiln 4.

·    Sales from aggregates and other ancillary products and services continue to provide a stable revenue base as kiln commissioning progresses.

·    Advancing discussions with a leading Zambian bank to secure funding to increase interest in Limeco to 45% and repay Bridge Loan.

Yuval Cohen, Chief Executive Officer of Firering Strategic Minerals, commented: “We are delighted to report Limeco’s first sales of quicklime have been secured, which is a major milestone in our journey towards establishing the operation as a leading regional supplier of this essential industrial product. While its optimisation continues to progress carefully and steadily, Kiln 1 is currently producing commercial quality quicklime at around 50 tonnes per day and serving as a robust operational model as we move into the commissioning of Kilns 2-4.

“The ramp-up at Limeco is well timed, aligning with the Zambian government’s drive to increase copper output, evidenced by a 30% year-on-year rise in Q1 2025. By producing high-purity quicklime locally, Limeco reduces reliance on imports, cuts transport costs and emissions, and delivers a more cost-effective, reliable, and sustainable solution that supports Zambia’s industrial growth and decarbonisation goals.”

Details

Limeco operates a large-scale limestone project approximately 22km west of Lusaka, Zambia. The site is strategically located to service the rapidly growing copper production industry in the Central African Copperbelt, as well as broader regional markets.

The optimisation of the first of eight kilns is ongoing with current daily quicklime production standing at around 50 tonnes; steady-state output is targeted at 80 to 100 tonnes per day.  The kiln is producing quicklime of excellent quality, with purity levels of 85-90%, well above the 80% industry benchmark for metallurgical applications. This high product quality has generated strong early interest, resulting in sales secured with local and regional customers. Due to commercial sensitivities, spot pricing and customer information will be disclosed only as required under regulatory obligations.

While the optimisation of Kiln 1 has taken slightly longer than initially anticipated due to intermittent blockages, a common occurrence in global kiln operations, Limeco has now gained better insights in managing the various operating parameters, feed, gas and air flows, discharge regime, which will assist in streamlining operations. This process will be replicated in a modular fashion across the remaining seven kilns. Limeco has commenced modifications to Kiln 2, followed by Kilns 3 and 4.

In parallel, Limeco continues to generate cash flow from aggregate sales and other ancillary revenue streams, providing a strong operational foundation as the kiln commissioning progresses.

Stabilising production at Kiln 1 and generating revenue were the final key milestones required to progress discussions with a leading Zambian bank in relation to the previously agreed non-binding term sheet (see RNS dated 15 November 2024). With these milestones now achieved, discussions are advancing with the objective of securing funding that would enable Firering to increase its interest in Limeco to 45% and repay the outstanding Bridge Loan.

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Firering reports interim results as Limeco quicklime output reaches 55 tpd

Firering Strategic Minerals has released its interim results for the six months to 30 June 2025, highlighting progress at its Limeco project in Zambia. Kiln 1 is now producing around 55 tonnes per day of quicklime, with refurbishment of Kiln 2 on track for commissioning in Q4 2025.

Firering boosts Limeco output with kiln upgrade and sales growth

Firering Strategic Minerals has increased production at its Limeco quicklime plant in Zambia, with Kiln 1 now operating steadily at 45-50 tonnes per day following a successful upgrade. Refurbishment of Kiln 2 is in progress, with commissioning expected soon, and further improvements planned for additional kilns to enhance efficiency.

Firering Strategic Minerals regains control of Atex and Alliance projects

Firering has confirmed that Ricca Resources has withdrawn from its earn-in agreement, relinquishing all interests in the Atex and Alliance Lithium-Tantalum Projects in Côte d'Ivoire. Firering now holds 90% of Atex and 51% of Alliance, retains a 10.6% stake in Ricca, and is seeking repayment of funds advanced under the agreement.

Firering Strategic Minerals increases stake in Limeco to 26.9%

Firering Strategic Minerals has exercised the first tranche of its option to acquire an additional 6.4% stake in Limeco Resources, raising its total shareholding to 26.9%. The move reflects Firering’s confidence in Limeco’s quicklime project and long-term market potential.

Firering Strategic Minerals to raise £1.01m to increase Limeco stake

Firering Strategic Minerals to raise £1.01 million through a placing and subscription of 67.3 million new shares at 1.5p each. The funds will support the exercise of the first two tranches of its option to increase its stake in Limeco Resources to 30.7% and help ramp up quicklime production.

Firering Strategic Minerals raises £1.01 million to advance Limeco quicklime project

Firering Strategic Minerals plc has raised £1.01 million via a placing and subscription at 1.5 pence per share to fund the first two tranches of its Limeco option, increasing its stake to 26.9 per cent by 31 July 2025.