Firering Strategic Minerals commences first quicklime production at Limeco

Firering Strategic Minerals

Firering Strategic Minerals plc (LON:FRG), an emerging quicklime production and critical mineral exploration company, has announced the firing of its first gasifier and Kiln 1 at its Limeco quicklime project on 10 and 12 February 2025 respectively, marking the commencement of quicklime production at Limeco.

Yuval Cohen, Chief Executive of Firering Strategic Minerals, commented: “Last week’s achievements of firing the gasifier and Kiln 1, were significant milestones. The gasifier has been running successfully since 10 February and Kiln 1 will be refired later this week at which point the first quicklime will be produced and announced within days. This will be followed by an estimated 30-day optimisation period. This is a key step towards achieving full-scale operations across all eight kilns by the end of 2025.  Once at steady-state production (100 tonnes of quicklime per kiln per day) Limeco will produce over 200,000 tonnes annually, establishing itself as one of Zambia’s largest quicklime producers and an important supplier to the growing copper industry in the Central African Copperbelt.”

Details

Following the successful commissioning of the gasifier and Kiln 1, phased production is now underway at the Limeco project, with a target of 600-800 tonnes of quicklime per day by the end of 2025. A key development in this process has been the conversion of the fuel source for the eight lime kilns from Heavy Fuel Oil to gasification. This successful change will improve operational efficiency and significantly reduce plant operating costs.

Having commenced mechanical commissioning of Kiln 1 in December 2024 and the first gasifier in January 2025, firing both the gasifier and Kiln 1 last week is a major achievement for Limeco. The gasifier has been successfully and consistently running since 10 February, enabling the Company to move forward to refiring the kiln following commissioning adjustments, with crushed limestone (-90mm to +60mm), at the end of this week.  Over several days, the temperature inside the kiln will gradually rise to approximately 1,000°C. Once this temperature is reached, the limestone will undergo a thermal decomposition process, known as calcination, for 7 to 9 hours, producing high-quality calcium oxide (CaO), or quicklime.  Following the delivery of this first quicklime production, we expect to have a period of approximately 30 days to optimise production quantity and quality.

The first kiln, like the remaining seven kilns, is expected to produce up to 100 tonnes of quicklime per day, operated continuously on a 24/7 basis, with only brief pauses for scheduled maintenance. This efficient process ensures a steady supply of quicklime, maximising energy usage while minimising waste.

A group of men in orange jumpsuits standing on a metal platform AI-generated content may be incorrect.

Figure 1: Successful firing of the gasifier (10 February 2025).

A group of people standing next to a large white machine AI-generated content may be incorrect.

Figure 2: Successful firing of burners of Kiln 1 (12 February 2025).

A large pipes in a factory AI-generated content may be incorrect.
Figure 3: View of gasifier and gas ducting connecting gasifier to lime plant.

A metal stairs leading up to a building AI-generated content may be incorrect.
Figure 4: View of gasifier.

A metal ladder next to a building AI-generated content may be incorrect.
Figure 5: View of gasifier with lime plant in the background. 

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Firering Strategic Minerals regains control of Atex and Alliance projects

Firering has confirmed that Ricca Resources has withdrawn from its earn-in agreement, relinquishing all interests in the Atex and Alliance Lithium-Tantalum Projects in Côte d'Ivoire. Firering now holds 90% of Atex and 51% of Alliance, retains a 10.6% stake in Ricca, and is seeking repayment of funds advanced under the agreement.

Firering Strategic Minerals increases stake in Limeco to 26.9%

Firering Strategic Minerals has exercised the first tranche of its option to acquire an additional 6.4% stake in Limeco Resources, raising its total shareholding to 26.9%. The move reflects Firering’s confidence in Limeco’s quicklime project and long-term market potential.

Firering Strategic Minerals to raise £1.01m to increase Limeco stake

Firering Strategic Minerals to raise £1.01 million through a placing and subscription of 67.3 million new shares at 1.5p each. The funds will support the exercise of the first two tranches of its option to increase its stake in Limeco Resources to 30.7% and help ramp up quicklime production.

Firering Strategic Minerals raises £1.01 million to advance Limeco quicklime project

Firering Strategic Minerals plc has raised £1.01 million via a placing and subscription at 1.5 pence per share to fund the first two tranches of its Limeco option, increasing its stake to 26.9 per cent by 31 July 2025.

Firering Strategic Minerals begins sales and expands Limeco stake

Firering Strategic Minerals plc has reported a pivotal year in 2024, securing a 20.5% stake in Zambia’s Limeco quicklime project and recording its first commercial sales in June 2025.

Firering Strategic Minerals reports first quicklime sales in Zambia

Firering Strategic Minerals plc has achieved a key milestone with its Zambian subsidiary, Limeco Resources, securing its first high-purity quicklime sales.

Search

Search