KEFI Gold and Copper Nears Transformational Milestone with Tulu Kapi – Edison Investment Research

KEFI Gold and Copper

KEFI Gold and Copper (LON:KEFI) flagship Tulu Kapi gold project in Ethiopia is now on the cusp of major progress, with final financing arrangements entering the home stretch. This momentum, detailed in a 17 July 2025 note by Edison Investment Research, reflects not only project-contractual finalisation but also meaningful groundwork activity and community engagement – placing KEFI on track for first gold by late FY27.

With infrastructure elements such as access roads, construction camps, and water supply facilities already built, and community compensation payments underway, KEFI now appears to be past the final obstacles to full-scale construction.

Edison analyst Lord Ashbourne captures the sense of impending transition, noting:
“With contractual finalisation imminent, KEFI’s shares are at a key inflection point, with the company now targeting first gold in late FY27.”

Advancing the $320 Million Financing Package

In recent months, KEFI has made visible strides in derisking and readying Tulu Kapi. Importantly, the company has:

  • Appointed BCM as its preferred mining contractor
  • Raised £7.6 million through a supported equity placement
  • Completed major early works like road access, security camps, and logistics coordination
  • Triggered community compensation payments, a vital social milestone

These updates cap a multi-year effort to shore up KEFI’s funding base. The US$320 million project financing mix includes:

  • US$240 million in senior secured debt from project finance banks
  • US$50–60 million in equity and preference shares from Ethiopian and specialist African investors
  • US$20 million equity contribution by the Ethiopian government at project level

Field activities are accelerating, supported by the now-ratified Ethiopian Parliamentary approval for both co-lending banks, the final regulatory hurdle. Upcoming months will focus on wrapping definitive agreements, issuing contractor notices, and initiating the drawdown process.

Full-Year Financial Snapshot

While KEFI remains pre-revenue as typical for development-stage miners, Edison estimates annualised free cash flow of £99.4 million from 2029 to 2034. Despite a wider pre-tax loss expectation of £14.6 million in FY2025, the group is expected to reach profitability by FY2026 and begin paying dividends from FY30.

Edison maintains a conservative yet upward-sloping valuation, based on Tulu Kapi’s robust project economics:

  • NPV5 of US$690 million at US$2,400/oz gold price, with KEFI’s 80% share worth approx. £412 million
  • Additional contributions from Saudi projects Hawiah and Jibal Qutman
  • Total risk-adjusted equity valuation: 1.41p/share, rising to 5.46p/share at current gold prices
  • Potential 66.7% IRR to investors buying shares at the current level of 0.54p

Ashbourne’s valuation summary underlines KEFI’s leverage to the gold price and approaching production:
“At current metals prices, our valuation increases to 5.46p now (plus a further 0.75p/share for the underground mine) and to 7.33p in FY29, implying an IRR of 66.7% to buyers of the shares at their current price in sterling terms over the next 12 years.”

Tulu Kapi – A High-Grade, High-Impact Asset

The Tulu Kapi mine is expected to yield around 160,000oz of gold annually in its first full year, with room for increased output when potential underground resources are brought to bear. Over the life of the open-pit mine, average cash cost is forecast at US$953/oz.

Community engagement also appears strong, with over 360 households (or approximately 1,300 people) supported via a government-led Resettlement Action Plan. KEFI has allocated US$24.7 million towards land compensation and long-term livelihood development, all coordinated in conjunction with the Oromia Regional Government.

Upcoming Milestones and Valuation Sensitivities

Key events expected in H2 2025 include:

  • Completion and signing of definitive project-financing agreements
  • Drawdown of equity and initial debt tranches
  • Launch of core civil works post-wet-season in Q4 2025
  • Steady construction ramp-up toward commissioning in late 2026

The company’s valuation is highly sensitive to gold prices. Edison notes that at US$3,300/oz, KEFI’s equity value rises to 6.21p/share (including underground mine), up from its risk-adjusted base of 1.41p.

On a Final Note

KEFI Gold and Copper is entering a critical phase in its development journey. Field mobilisation, community compensation, and updated backer commitments underscore real traction after years of structuring and negotiation. Backed by a US$320 million financing package and robust government support, the Tulu Kapi gold project may soon deliver Ethiopia’s next large-scale gold operation. While investor attention will now naturally focus on execution discipline over the next 18–24 months, KEFI’s valuation metrics suggest significant upside potential. As Edison’s note highlights, the company’s fortunes will ultimately hinge on successful deployment rather than technical feasibility — a position far stronger than in years past.

Share on:
Find more news, interviews, share price & company profile here for:

    Latest Company News

    Copper hits record high as supply constraints meet rising demand

    Copper has hit a record high as tight supply, rising industrial demand and US tariff concerns increase competition for available metal.

    KEFI moves Tulu Kapi closer to construction while advancing underground expansion

    KEFI is moving Tulu Kapi towards construction while preparing an underground mine that could add production using the same processing infrastructure.

    KEFI strengthens Board with Danny Callow appointment

    Danny Callow joins KEFI as an independent Non-Executive Director, bringing extensive African mine development experience as the company refines its Board and governance structure ahead of planned Tulu Kapi production in 2028.

    KEFI Gold & Copper advances second Tulu Kapi mine plan after positive PEA

    KEFI Gold & Copper has outlined an updated underground mine plan for Tulu Kapi, alongside revised production and capital estimates.

    Gold sets up for a fresh test of higher levels

    Gold is building a stronger technical and macroeconomic setup as dollar weakness, US debt concerns and upcoming Federal Reserve signals put higher price levels in focus.

    KEFI moves Tulu Kapi into construction phase ahead of 2028 production

    KEFI is advancing resettlement, procurement, financing and construction preparations at Tulu Kapi as the Ethiopian gold project targets commissioning in late 2027 and full production in mid-2028.