Drax signs 250MW battery storage tolling agreement with Fidra Energy

Drax Group

Drax Group plc (LON:DRX) has announced that it has signed a tolling agreement with West Burton C Limited, a company owned by Fidra Energy(1), for 250MW (500MWh) of new BESS capacity.

Highlights

·    Tolling agreement for 250MW 2-hour duration BESS at West Burton, England

·    No upfront capital cost – construction, maintenance and availability risk sits with Fidra

·    10-year tolling agreement with annual payments indexed to UK CPI

·    Contract provides Drax with full operational control and dispatch rights

·    Protected grid connection, targeting a Commercial Operation Date (COD) in 2028

·    Expected returns significantly ahead of Drax’s Weighted Average Cost of Capital(2)

·    Strong strategic fit

·    Aligned with Drax FlexGen strategy, adding short duration and fast response capability

·    Complements Drax investments in physical ownership of BESS and asset optimisation

·    Closely aligned with UK energy objectives of energy security and decarbonisation

Drax Group Chief Executive Officer, Will Gardiner, said: “Flexible Generation technologies like battery storage will support a secure, affordable and clean energy system for British homes and businesses. Our first BESS tolling agreement is an important step in our ambition for a gigawatt scale pipeline of battery storage opportunities, alongside our recent acquisitions of Flexitricity and three battery storage developments.

“We are working to create opportunities for growth and value creation in our FlexGen portfolio that are aligned to the UK’s energy needs, and are underpinned by strong cash generation, disciplined capital allocation and attractive returns for shareholders.”

Under the agreement Fidra will retain responsibility for construction, maintenance and availability of the asset during the contract period. In return Drax will pay a fixed annual tolling fee over the agreed term of 10 years from the COD, in return for full operational control and dispatch rights, retaining all revenues (excluding Capacity Market revenues).

Drax sees the agreement as a capital light opportunity to provide additional BESS capacity for the Group’s FlexGen portfolio, alongside physical ownership of BESS assets(3).

The agreement is subject to Fidra taking a final investment decision on the project by Q3 2026 and commercial operations by H2 2029.

Strategic fit – aligned with UK energy needs and Drax FlexGen business

Drax is developing a GW scale pipeline of BESS opportunities comprised of (1) physical assets and (2) the capabilities to optimise third-party assets with the provision of route to market, floor and tolling structures.

In October 2025, Drax signed an agreement with Apatura Limited to acquire three BESS projects, which when fully commissioned will provide capacity totalling 260MW(3). In January 2026 Drax announced the acquisition of Flexitricity, providing an optimisation platform for the development of the Group’s FlexGen business, including BESS(4).

Notes:

(1)   Battery Energy Storage | Flexible Battery Electricity | Fidra Energy

(2)   The cash flow that Drax expects to generate over the life of the contract when compared to the present value of the annual toll payments, is expected to deliver a return significantly above Drax’s WACC.

(3)   Acquisition of 260MW 2-hour BESS portfolio – 07:00:11 30 Oct 2025 – DRX News article | London Stock Exchange

(4)   Acquisition of Asset Optimisation Platform – 07:00:06 21 Jan 2026 – DRX News article | London Stock Exchange

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Latest Company News

Drax signs 250MW battery storage tolling agreement with Fidra Energy

Drax has entered into a 10-year tolling agreement with Fidra Energy for a 250MW (500MWh) battery energy storage system at West Burton in England.

Drax strengthens flexibility ambitions with Flexitricity acquisition

Drax’s planned acquisition of Flexitricity boosts its positioning in the UK flexibility and storage market.

Drax expands FlexGen platform with Flexitricity acquisition

Drax has signed an agreement to acquire Flexitricity, an Edinburgh-based provider of optimisation and route-to-market services for flexible energy assets.

Drax secures biomass supply agreement for US aviation fuel project

Drax signs deal to supply biomass for new US plant aiming to produce carbon-negative aviation fuel.

Drax deepens community ties in the US south with fundraising drive

Drax boosts US community ties with record local fundraising for child and family services.

Drax builds local links through seasonal initiative at Cruachan Visitor Centre

Drax hosted a fundraising event at its Cruachan Visitor Centre, supporting Oban RNLI and reinforcing community ties near a key energy site.

Search

Search