Oriole Resources plc (LON:ORR) Chief Executive Officer Martin Rosser caught up with DirectorsTalk to discuss the new ultra-fine grinding (UFG) processing method at the Bibemi gold project, the US$13.7 million reduction in initial project capital expenditure, potential improvements to project economics and the company’s development plans across its African portfolio.
Q1: Martin, today’s announcement highlights a significant reduction in the potential capital cost of developing Bibemi. Can you just explain for us in simple terms what you’ve achieved with the alternative processing method and why this is such an important development for Oriole?
A1: Well, this is a major technical success, without doubt. We’ve now demonstrated that we’ve got two viable technical processing methods for the unusual mineralogy that we have at Bibemi, but the ultra-fine grinding flowsheet is clearly the preferred new and improved option.
As it’s simpler, it uses more conventional equipment. Whilst pressure oxidation is fine, it’s more complicated, so this UFG flowsheet will be easier to operate in a remote location.
We’ve demonstrated very good recoveries and performance with the new method, and so we’re absolutely delighted.
Q2: Now, the new study indicates a US$13.7 million capital cost saving, reducing the estimated initial project capital expenditure to US$46.7 million, whilst maintaining the targeted annual production of 10,000 ounces of gold. How significant is this in terms of the potential economics, operational simplicity and the ability to finance the project?
A2: Well, it’s extremely significant. As you’ve just highlighted there, there’s a substantially lower capital expenditure, 38% lower for the plant capital cost, and it has a processing cost per ounce of gold recovered compared to the pressure oxidation flowsheet. What that translates through to is great potential for improved economics.
Improved economics clearly will lead to a better project, and a better project will improve the financing exercise. Indeed, by adopting a process that’s more straightforward, it will be easier for potential investors, when it comes to debt and equity financing, to consider the opportunity and hopefully arrange that finance.
So again, lots of positives.
Q3: You’ve identified further opportunities to improve gold recoveries and reduce operating costs. How much scope is there for further optimisation and what are the next steps in completing the updated preliminary economic assessment?
A3: Well, we see that there’s good scope for some improvements. We have plans afoot to determine what we need to do next. We don’t think that the test work to determine what improvements there may be is going to take particularly long.
It means that we can only get better in terms of the economics that we’ve reported today, potentially, obviously based on success. So, that will be something for us to look at in due course.
Separately, and critically and most importantly, we’re going to finalise and publish the preliminary economic assessment as soon as possible. We’ve got all the information we need.
We just have to do a few other bits and pieces to feed back into the study, and we’re beginning to be doing all of that in parallel, and I emphasise in parallel, with the ongoing exploitation licence application process that we are underway with in Cameroon.
Q4: How does today’s announcement strengthen your position in the ongoing discussions with Cameroon authorities regarding the exploitation licence? What are the key milestones investors should look out for as you seek to move the project towards development?
A4: Well, it greatly enhances and strengthens our position with the government because it demonstrates our technical expertise and capability. We’re emphatically the leading company in the sector for exploration, success and discovery, therefore, project work.
Of course, with this new development, especially finding processing method solutions, we’re moving this project forwards to what will be the country’s first hard rock gold mine once the exploitation licence is granted. That’s a critical milestone, not just for Oriole Resources, but for the government.
So this just, in our opinion, will reinforce our strong case and motivate the government to expedite this as much as it can.
Q5: Just putting Bibemi into the wider Oriole context. You now have a 1.66 million-ounce gold resource at MBE, a potential route to gold production at Bibemi, and the opportunity to generate in Wapouzé. How do these projects complement each other, and how do you see Oriole evolve over the next 12 to 18 months?
A5: Well, they complement each other very well because we have got significant progress towards now two projects which have got very near, Bibemi and Wapouzé. We’ve got our town as being advanced towards also an exploitation licence application in a few years’ time.
So, what we’re going to be doing, like we’ve done for the last few years, we’re going to keep advancing our projects, we’re going to keep delivering results. Optimistically, of course, we continue to think that we’re going to have great results through our exploration efforts, and thereby we’re going to add fundamental value.
So, if I can just run through the milestones that are coming up, starting with MBE, we’re going to commence our next work programme once we finalise that with our partner BCM, and we’re already considering conceptual mine development scenarios.
At Bibemi, as you’ve already heard, we’re looking forward to getting the exploitation licence granted as quickly as possible. In parallel, we’re going to update the PEA based on this very exciting metallurgical test work new flowsheet. We’re going to, post-exploitation licence, complete the remaining studies to support mine development regarding the Eastern Central Licence Package licences. We’ve got lots of good things happening there with lots of work to report upon soon.
At Wapouzé, we’ve already submitted an exploitation licence application. We’ve got more studies to do, and we’re looking to do a deal with a potential third-party investor or industrial partner to move that forward. As listeners, I’m sure, will be aware, it’s got great potential to be able to support a significant new cement manufacturing works.
Finally, changing country to Senegal. We’ve got a very exciting project in Senegal. We’ve got an exploration programme under the operatorship of our partner Managem. That will be generating significant news flow over the months to come.
So, in summary, we’ve got lots going on. We don’t rest on our laurels. We’re going to keep pushing hard, keep delivering results and adding value and we’re very excited as to what the future has.