Jubilee Platinum PLC (LON: JLP) has today announced the commissioning of fine chrome operation has now commenced.

Highlights

At PlatCro

· PlatCro’s pre-classification and dewatering circuit commences production of PGM rich material for refining at Northam’s Eland Platinum plant

· Production at PlatCro will be ramped up, targeting the production of 60 000 tonnes per month of PGM rich material, more than doubling Jubilee’s current PGM processing rate

At DCM

· Jubilee’s state of the art DCM fine chrome plant commenced commissioning

· The DCM fine chrome plant will be ramped up to 25 000 tonnes per month of additional capacity over the next 4 weeks targeting the production of 8 000 tonnes per month of fine chrome concentrate

Jubilee Platinum PLC CEO, Leon Coetzer, said:

“I am extremely pleased at yet another leading performance by the Jubilee team delivering the PlatCro pre-processing circuit and the DCM fine chrome plant on-time and in budget. Both projects involve leading edge processes as we continuously strive to deliver industry leading solutions to the benefit of all our stakeholders.

We have recently announced our acquisition of the PlatCro chrome beneficiation operation which we intend to integrate with our current PlatCro PGM project, forming a fully integrated operation to further streamline costs and optimise metal earnings. The addition of the PlatCro pre-processing plant to produce PGM rich material for further refining at the Eland Platinum plant, is the first of a number of processing improvements targeted for the integrated PlatCro operation.

I am particularly pleased with the implementation of our industry first DCM fine chrome plant. Our ability to target the recovery of the fine chrome element of existing mine waste material opens tremendous opportunities to Jubilee for further growth in the chrome industry. We will target to roll out this solution at our existing operations at Hernic and PlatCro, as well as the wider chrome industry.”

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Jubilee Metals seeks flexibility to fund Molefe region development

Jubilee has called a General Meeting for 15 June 2026 to seek authority to allot shares and dis-apply pre-emption rights up to 7.5% of its issued share capital, supporting its Zambia copper strategy and Molefe region development.

Jubilee Metals secures US$1.5m convertible loan for Molefe copper development

Jubilee has secured a US$1.5 million unsecured convertible loan note to accelerate development of the greater Molefe region in Zambia, with discussions continuing over a potential further US$10 million investment.

Jubilee Metals reports higher copper production as Zambia ramp-up continues

Jubilee increased nine-month saleable copper production by 28.7% to 2,177 tonnes, with Roan output more than doubling and Molefe Mine expansion progressing ahead of further guidance.

Jubilee Metals targets higher copper production at Molefe Mine in Zambia

Following Phase 1 drilling and trenching results, Jubilee Metals plans to expand Molefe Mine by linking two open pits, increasing ore supply to the Sable refinery and advancing further drilling on the project’s eastern extension.

Jubilee reports stronger H1 FY2026 copper production and improved EBITDA

Jubilee’s unaudited interim results for the six months to 31 December 2025 show copper production up 8.7% to 1,543 tonnes, revenue up 70.5% to US$14.1 million and EBITDA from continuing operations improving to US$2.0 million, as the group advances its integrated copper strategy in Zambia.

Jubilee Metals reports strong Molefe drilling results and eastern copper oxide extension

Phase 1 infill drilling at the Molefe copper mine confirmed near-surface oxide mineralisation and grades consistent with the expansion mine plan, while identifying a new mineralised zone extending about 250 metres to the east. Jubilee said Phase 2 drilling is under way to define the extension and support a future formal resource estimate.

Search

Search