Criterium Energy says SE-MGH gas output is running ahead of expectations after first sales

CEQ

Criterium Energy has reported that early gas production at its SE-MGH field in Indonesia is running ahead of expectations, less than three weeks after first sales gas was achieved.

The TSXV-listed upstream energy company released unaudited financial results for the third quarter ended 30 September 2026 and said production at SE-MGH averaged 7.4 million cubic feet per day during the first two weeks, supported by stable wellhead pressures. Around 150 barrels of condensate have also been produced to date, averaging 12-13 barrels per day.

Overall company production exceeded 1,850 barrels of oil equivalent per day. Oil output in the third quarter averaged 573 barrels per day. Including the reported average gas production of 7.4 MMcf/d, pro forma output totalled about 1,890 boe/d.

Revenue and cash flow improve

The company also pointed to stronger cash generation and improved financial performance. Cash flow from operations rose 42% year on year in the first nine months of 2026. In the third quarter, Criterium narrowed its net loss by 42% and increased net revenue by 5% compared with the same period a year earlier, supported by higher realised oil prices.

For October 2026, Criterium realised an oil price of US$120 per barrel, which it said represented a premium to Indonesian and dated Brent benchmarks. Condensate from SE-MGH is blended with the company’s existing oil production and sold under the same contracts.

Under its gas sales agreement, Criterium receives a fixed price of US$7.00 per MMBtu on a take-or-pay basis. Based on a measured gas heating value of 1,117 Btu/scf during early production, the company said this is equivalent to approximately US$7.82 per Mcf. At current production levels, it expects gross monthly revenue from gas sales of about US$1.7 million.

Balance sheet and operations

Maintenance work was carried out at the PLT and MGH oil fields to address natural decline and production falling below expected levels. The work was completed after gas production started at SE-MGH and did not interrupt oil production.

Criterium said cash on hand was relatively flat at C$1.9 million at 30 September 2026, compared with C$2.0 million at 31 December 2025. Cash generated from operations during the quarter was used for maintenance at MGH and PLT, and for testing and preparations for N-MGH development. Nominal repayments to lenders were made in the quarter, with sustained payments expected to resume once gas production at SE-MGH stabilises.

Management continues to work with the Indonesian Tax Office and lenders on longer-term solutions to reduce overall leverage. President and chief executive Matthew Klukas said the company’s focus will now be on the next phase of gas development and strengthening the balance sheet.

Next projects in the pipeline

Following first gas at SE-MGH, Criterium is advancing the next phase of low-cost gas developments, including N-MGH, Macan Gedang and Cerah.

At N-MGH, which has 5 Bcf of 2P reserves, the company has started front-end engineering design and surveying work after successful well tests of MGH-20 in the first quarter of 2026 and MGH-32 in the third quarter of 2026. The planned development involves a new pipeline linking the N-MGH wells to the Central Mengoepeh Oil Field processing facilities before continuing to SE-MGH and downstream processing and sales facilities. Criterium is currently producing oil from MGH-20 and said gas rates and pressures remain supportive of further development. It expects future production from N-MGH of 2-3 MMcf/d, plus incremental oil volumes.

At Macan Gedang, which has 13 Bcf of 2C resource, the Macan Gedang-1 well tested at rates of up to 5 MMcf/d. The company has discussed a fast-track development mechanism, known as Put on Production, with Indonesian regulator SKK MIGAS. A new production well would be drilled and connected by pipeline to the same processing facilities used by SE-MGH.

At Cerah, which has 34 Bcf of 2U resource, Criterium has completed work to re-establish access roads and the well site ahead of drilling Cerah-2, a twin of Cerah-1. Cerah-1 encountered gas shows in the Gumai formation but was not tested. Drilling at both Macan Gedang and Cerah is scheduled for 2027, with preparations for longer-lead items set to begin in the fourth quarter of 2026.

Share on:

Latest Company News

Criterium Energy says SE-MGH gas output is running ahead of expectations after first sales

Criterium Energy has reported stronger-than-expected early gas production at SE-MGH, alongside higher cash flow and plans for more gas...

Criterium Energy lifts Indonesian gas output as SE-MGH start-up exceeds early expectations

Criterium Energy’s SE-MGH field in South Sumatra is producing above expectations, with first sales gas achieved on 10 November....

Criterium Energy starts gas output from SE-MGH field as Indonesia project reaches first production

Criterium Energy has brought first gas onstream from its Southeast Mengoepeh field in South Sumatra and will now focus...