Ampeak Energy has completed the delivery and installation of all batteries and key equipment at its Afon Wysg 1 battery storage project in Newport, South Wales.
The 240MWh project, located at Uskmouth Sustainable Energy Park, is expected to be energised later in November 2026, with full commercial operation targeted for the first quarter of 2027.
The installation includes 55 battery units supplied by e-STORAGE, part of Canadian Solar, alongside 36 inverters, 18 twin skids and the main grid transformer. Principal contractor Jones Bros Civil Engineering UK completed the installation, with the equipment delivered over 22 days.
Work has also been completed on the site’s new substation and high-voltage cabling for connection to the national grid. Around two-thirds of the existing power station export cable has been reused, while materials from previous demolition work have been recycled as part of the construction.
Ampeak is also progressing plans to expand the project from 240MWh to 480MWh. Foundations have already been poured and space has been left between the battery units to accommodate the additional capacity. The company aims to secure financial close for the expansion shortly after the initial project enters commercial operation.
The next stage for Afon Wysg 1 will involve energisation, followed by charging and discharging tests to confirm the system is ready for commercial operation.