Tirupati Graphite Madagascan projects complete, aiming for 8% of global flake graphite demand

Tirupati Graphite

Tirupati Graphite plc (LON:TGR, TGRHF.OTCQX), the specialist graphite and graphene company developing sustainable new age materials, has provided an update in continuation to its announcement released on 22 September 2022 on the ongoing developments and operations of the Sahamamy and Vatomina projects in Madagascar.

Vatomina operations and development

·    The Vatomina preconcentrate plant continues to operate uninterrupted following its reorganisation and the Company is pleased to advise that:

o Both the preconcentrate and final concentrate plants continue to operate over the name plate ore feed capacity of 600 tons per day completely synchronised with smooth and constant operation;

o The construction and installation of the second preconcentrate plant at Vatomina is now complete, with trial runs and integration to the existing operations in process;

o With reduction in ore movement activities, the current heavy earthmoving mining machinery (‘HEMM’) fleet has completed the development of other infrastructure and nascent mining areas, which meet the ore feed requirements of the second preconcentrate plant; and

o Strengthening of internal roads and other infrastructure developments at Vatomina are now complete and well prepared to mitigate the risks from adverse weather conditions in the future.

·    The Company does not foresee any challenges in stabilising Vatomina operations at above 1,200 tons ore feed per day with effect from December 2022; stabilising operations at 12,000 tpa output as planned.

Sahamamy operations and development

·    The operations and development of Sahamamy has continued at full pace and the Company is pleased to advise that:

o The new road connecting Sahamamy project to National Highway 2 and Vatomina project has been strengthened throughout the nearly 40 kilometres of road, with the last few kilometres currently under completion;

o The existing 3,000 tpa plant at Sahamamy remained in operation and shall be decommissioned in December following the stabilisation of the second preconcentrate operations in Vatomina;

o Extensive mine development has been executed in the nascent Sahasoa deposits of the Sahamamy project and is ready to provide the required 1,200 tons per day of ore for the new plants;

o Construction and installation of both pre-concentrate plants in Sahamamy are now complete with tests and trial runs initiated;

o Construction and installations at the main processing plant is substantially complete at Sahamamy;

o We remain on target to stabilise operations of the 18,000 tpa plant by end of the current quarter;

o The first power generation from the 100Kw hydro power plant (‘HPP’) has been achieved during November with integration and commercial use underway with related cost savings expected to commence from December;

o To progress the next HPP of 400 Kw, related studies and application for required approvals have been initiated.

Shishir Poddar, Tirupati Graphite Executive Chairman, said:

“We have come a long way in a short time and have effectively brought under control the impacts of the adverse conditions experienced in Madagascar earlier this year. Our innovative and cost-effective solutions have started to bear fruit. Market conditions for graphite are very positive, and this is the ideal time for us to be increasing production of this critical material.

“With the turnaround of the Madagascan projects now complete, we are again progressing towards our aim of providing approximately 8% of global flake graphite demand.”

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Latest Company News

Graphene power storage offers a clear materials opportunity

Graphene-based power storage offers investors a direct materials angle on faster charging, safer systems and longer product life.

Total Graphite publishes GM notice

Total Graphite plc has distributed its Circular to shareholders and Notice of General Meeting ahead of the GM scheduled for 5 June 2026 in London. The documents, including voting and proxy information, are available on the company’s website.

Total Graphite targets higher-value graphite sales

Total Graphite is using a new trading line to build customer access for higher-value graphite products before scaling its own mine-to-market supply strategy.

Total Graphite reviews US Anode PFS to advance integrated battery supply chain

Total Graphite is updating its US-based anode processing feasibility study to align with current market conditions and support a vertically integrated graphite-to-battery supply strategy alongside its Montepuez project.

Total Graphite updates Mozambique development strategy

Planned study updates will reassess costs, pricing, and phased development options while supporting financing discussions and long-term downstream graphite ambitions.

Total Graphite launches value-added trading business

Total Graphite reports early success in its new trading division, generating $91,000 from April transactions and building a pipeline of 900 MT of value-added graphite products through November 2026.

Search