KEFI Minerals plc Escalate preparatory field activities for Tulu Kapi Gold Project

KEFI Minerals

KEFI Minerals plc (LON:KEFI), the gold and copper exploration and development company with projects in the Kingdom of Saudi Arabia and the Federal Democratic Republic of Ethiopia, has today reported the escalation of preparatory field activities in relation to the Company’s Tulu Kapi Gold Project in Ethiopia since announcing on 8 October 2018 that local, zonal and regional authorities had confirmed their intention to expedite community resettlement.

The authorities have undertaken the necessary preparatory steps to carry out the planned community resettlement in Q1 2019. The addition field activities in the past week include the following surveys and inspections:

· Completion of a 14km road route survey by the Ethiopian Roads Authority, for a new road required for the Project production phase;

· Completion of a 47 km route survey for electricity transmission lines from the regional main line to the site for the Tulu Kapi sub-station, carried out by the Ethiopian Electricity Power Corporation;

· Siting of the last geotechnical drilling to enable the final design of foundations for the processing plant and associated infrastructure, set out by Lycopodium with independent geotechnical consultants Knight Piesold;

· Reconfirmation of compensation calculations, carried out by the local government (Wareda);

· An inspection of new host lands, being carried out by the West Walega Zonal Administration; and

· Follow-up base line environmental surveys completed by independent consultant Golder Associates.

KEFI Minerals said that it is pleased to report that the field and community work has intensified now that the 2018 wet season has passed. These developments are progressing in parallel with work on government administrative tasks, construction planning and financing arrangements. All parties are focused on construction start-up in early 2019 and first production in H2 2020. Further updates will be provided as matters progress.

Share on:
Find more news, interviews, share price & company profile here for:

Latest Company News

KEFI finalises funding and begins full construction at Tulu Kapi gold project

KEFI has launched full construction of its Tulu Kapi gold mine, with financing secured and production targeted for 2026.

KEFI sets Tulu Kapi on a new development path

KEFI Gold and Copper secures US$340m in project funding plus US$30m in streaming finance to advance its flagship Tulu Kapi mine towards full production by 2027.

KEFI confirms full launch of Tulu Kapi Gold Project

KEFI says contracting and field mobilisation are underway at its Tulu Kapi Gold Project in Ethiopia, with a US$340m funding package assembled and commissioning targeted for late 2027 ahead of full production in 2028.

Gold prices break through $4400 as investors position ahead of rate cuts

Gold crosses $4400 for the first time as investors reposition ahead of expected rate cuts and weaker currencies.

KEFI Tulu Kapi Gold Project update on US$30m funding

KEFI has confirmed it has signed a term sheet for US$30 million in equity-ranking gold stream funding for its Tulu Kapi Gold Project in Ethiopia.

Gold is holding firm as the Fed signals a pause

Gold is holding firm above $4,300 as the Fed signals an extended pause and investors reassess portfolio risk.

Search

Search