KEFI Gold and Copper provides an operational update

KEFI Gold and Copper

KEFI Gold and Copper plc (LON:KEFI), the gold and copper exploration and development company with projects in the Federal Democratic Republic of Ethiopia and the Kingdom of Saudi Arabia, has today provided an operational update.

Ethiopia

Today is election day in Ethiopia. These are widely regarded as the most important elections in the country’s history.  The electioneering atmosphere in the lead-up around the country has been one of vibrant, but peaceful campaigning, reflecting very positively on the reforms over recent years.  Ethiopia remains amongst the highest growth countries in Africa and the world, whilst it continues to push its agenda of liberal and democratic reform.

Tulu Kapi Project Finance

The Tulu Kapi Gold Project (the “Project” or “Tulu Kapi”) remains on track with previous guidance and KEFI, through its subsidiary Tulu Kapi Gold Mines Share Company (“TKGM”), has presented its Project finance syndicate and submitted its Project finance plan to the Ethiopian central bank (“National Bank of Ethiopia”, or “NBE”) for permission that it may proceed as outlined.  This follows a long, thorough and rigorous due diligence process by the Senior Lenders.

Whilst the NBE conducts its review, the other outstanding administrative details are being progressed with the various Ethiopian Government agencies including, the Ministry of Mines and Petroleum (“MOMP”), Ministry of Finance, Ethiopian Roads Authority and Ethiopian Electricity Power Corporation.  These are normal compliance procedures to enable KEFI/TKGM and its syndicate of financiers and contractors to proceed to financial closing, which includes, inter alia, execution of detailed documentation, subscription of the asset-level equity funds and triggering full development, with debt funds to be disbursed later this year in compliance with the Senior Lenders specified conditions.

These procedural matters include requests for finalising confirmations of registration of historic investment, establishment of correspondent bank account arrangements, confirmation of construction schedules for road and electricity, and various other administrative matters already agreed in principle.

Starting full development of the Project is the highest priority for KEFI and the Ethiopian Government. All key stakeholders are pushing hard to finalise preparations and the Company has undertaken to the MOMP that, upon timely receipt of these confirmations, KEFI will push to financial closing by the end of July 2021, or as near as possible thereto given the local document registration procedures and the COVID-affected limitations of syndicate parties’ physical locations.

Recent Tulu Kapi Project Activities

KEFI continues to oversee the physical preparations for full development to be triggered at financial closing, such as:

•    Clearing of new host lands for community members to be resettled;
•    Overseeing the early works programme of detailed engineering and procurement, by principal construction contractor Lycopodium;
•    Supporting the planning and procurement programmes of mining services contractor Corica;
•    Overseeing the ‘new access road’ and ‘electricity connection’ works contracts; under which surveys and procurement has been completed;
•    Triggering compensation procedures for the first resettlers at the Tulu Kapi electrical substation site; and
•    Recruitment of further key personnel for the next stage of the Project.  

Saudi Arabia

Hawiah Gold Project

KEFI’s operations in Saudi Arabia are conducted through its 34% owned joint-venture company, Gold & Minerals Ltd (“G&M”), where KEFI is the operating partner.

G&M are working to finish the Phase 4 drilling programme in Q3 2021 with the goal of reporting an expanded and upgraded Mineral Resource.  With Ramadan having ended, drilling since late May 2021 has been 24/7 with three rigs on site.

The Preliminary Feasibility Study for the potential start of development of the Hawiah deposit in 2023 continues, and other recent activities have included the following:

•    Completion of the Environmental and Social Baseline Study;
•    Metallurgical testing progressing with reasonable recoveries so far being indicated for all principal metals, copper, gold, zinc and silver; and
•    Completion of the exploration camp construction.

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Share on:
Find more news, interviews, share price & company profile here for:

Latest Company News

Gold is holding firm as the Fed signals a pause

Gold is holding firm above $4,300 as the Fed signals an extended pause and investors reassess portfolio risk.

KEFI Gold and Copper advances financing for Tulu Kapi as full funding package nears completion

KEFI Gold and Copper has reported further progress on financing for the Tulu Kapi Gold Project, confirming debt documentation for US$240 million is ready for execution and detailing steps to secure the remaining equity-risk capital.

Gold setting the stage for 2026

Gold’s recent rebound and widespread institutional optimism hint at a potential re‑entry moment for bullion as a strategic portfolio anchor heading into 2026.

Deutsche Bank sees gold staying higher for longer

Deutsche Bank raises its 2026 gold forecast as central banks and institutions drive a more structural shift in demand.

KEFI moves first in Ethiopia as mining sector opens to global capital

KEFI is now building Ethiopia’s first internationally backed gold mine, with capital secured and construction underway.

KEFI Gold and Copper plans full Tulu Kapi project development by late 2025

KEFI says full development of the Tulu Kapi Gold Project is expected to begin by the end of 2025, with a US$340 million budget finalised and lender approval secured for the US$240 million debt component.

Search

Search