KEFI Gold advances Tulu Kapi development towards 2028 production target

KEFI

KEFI Gold and Copper is progressing development of its Tulu Kapi gold project in Ethiopia, with major engineering and construction contracts now in place and work restarting following a temporary suspension in September. The company remains focused on achieving its first gold pour in early 2028, followed by full production by mid-2028.

A significant development came with the award of an engineering, procurement and labour hire contract to Lycopodium Limited. The appointment provides an important element of the project’s construction framework and supports the timetable for bringing the mine into production.

Development activity resumed in October following a temporary suspension caused by a safety and security incident on 4 September 2026. The restart is being implemented in phases, with support from project stakeholders and lenders. Initial activities include power connections and access road improvements, followed by community resettlement housing, land replacement, security infrastructure, bulk earthworks and permanent accommodation.

The phased approach allows construction preparations to progress while addressing the operational and community requirements needed for a sustainable development. Maintaining local stakeholder support and security will remain important as activity increases towards the main construction programme.

KEFI has already secured substantial project financing. A $240m senior debt facility has been signed, alongside completion of the required equity risk capital arrangements. This provides the financial framework for the development and represents an important step in reducing the funding uncertainty that has historically affected the project.

The company also awarded a mining services contract worth more than $400m to BCM Group in June 2026. Together with the Lycopodium appointment, this establishes important relationships with experienced contractors responsible for delivering key elements of the development.

Tulu Kapi is designated an Ethiopian Strategic Project, reflecting its importance to the country’s ambitions to expand its mining industry, increase export revenues and strengthen the contribution of mining to gross domestic product. The project is expected to provide employment and wider economic benefits through construction, mining operations and associated infrastructure development.

KEFI’s immediate priority is maintaining construction momentum and delivering the remaining development milestones. The combination of secured financing, major contractor appointments and the phased resumption of work provides a clearer route towards production.

KEFI Gold and Copper plc (LON:KEFI) is an exploration and development company focused on gold and copper deposits in the highly prospective Arabian-Nubian Shield. The Company operates in Ethiopia and Saudi Arabia with projects including Tulu Kapi project, Jibal Qutman EL and Hawiah.

Share on:
Find more news, interviews, share price & company profile here for:

KEFI approves US$87 million Jibal Qutman gold project development in Saudi Arabia

KEFI Gold and Copper reports that its Saudi Arabian joint venture, GMCO, has approved the US$87 million first stage of the Jibal Qutman Gold Project, subject to outstanding procedural requirements, with development targeted to begin in Q4 2026.

KEFI restarts Tulu Kapi gold project development in Ethiopia

KEFI Gold and Copper (AIM: KEFI) has recommenced development at its Tulu Kapi Gold Project in Ethiopia following the lifting of a suspension imposed after the Genji Incident in September 2026. Work will resume in phases, with electricity infrastructure, access roads, community resettlement and mine construction among the initial priorities.

KEFI reports £87m net assets as Tulu Kapi development advances

KEFI Gold and Copper increased net assets to £87m at 30 June 2026 after completing its £35.6m equity raise, while Tulu Kapi development progressed following completion of its US$400m-plus funding package.

KEFI strengthens Board with Danny Callow appointment

Danny Callow joins KEFI as an independent Non-Executive Director, bringing extensive African mine development experience as the company refines its Board and governance structure ahead of planned Tulu Kapi production in 2028.

KEFI Gold & Copper advances second Tulu Kapi mine plan after positive PEA

KEFI Gold & Copper has outlined an updated underground mine plan for Tulu Kapi, alongside revised production and capital estimates.

KEFI advances Tulu Kapi resettlement and equipment procurement

KEFI Gold & Copper reports progress on Tulu Kapi resettlement, procurement and construction, alongside updates on Saudi and exploration plans.