# Valeura Energy accelerates Wassana redevelopment, targets first oil in Q2 2027

- Link: https://www.directorstalkinterviews.com/valeura-energy-accelerates-wassana-redevelopment-targets-first-oil-in-q2-2027/4121261530
- Published: 2026-09-01T07:42:52+01:00
- Author: Amilia Stone

**[Valeura Energy Inc](https://www.directorstalkinterviews.com/company/valeura-energy-inc/vle.to).**(
[TSX:VLE](https://www.directorstalkinterviews.com/company/valeura-energy-inc/vle.to),
OTCQX:VLERF) has announced that it intends to accelerate its Wassana field redevelopment
project on block G10/48 (100% operated interest) in the offshore Gulf of Thailand.

> **Dr. Sean Guest, President and CEO commented:**
> _“Work on our new-build central processing platform (“CPP”) is proceeding on budget
> and remains ahead of schedule, with facility construction (also known  as mechanical
> completion) in the yard expected to be complete by 01 October 2026.   We are now
> taking the opportunity to install the facility earlier than originally planned,
> leading to the potential for first oil from the new development at approximately
> the beginning of Q2 2027._
> _As Valeura’s first organic greenfield development in Thailand, and the largest
> capital venture ever undertaken by our Company, I am very pleased that this project
> is exceeding our expectations.”_

**Project Acceleration**

Valeura has finalised all commercial arrangements and contractual amendments required
to start installation of the Wassana CPP in October 2026, approximately two months
earlier than originally envisaged.  Separately, the Company has provided notification
to its drilling rig contractor to start its charter of the _Shelf Enterprise_ drilling
rig on 01 November 2026, to initially drill Nong Yao wells through the Nong Yao 
A facility’s additional well slots and thereafter to support earlier development
drilling on the Wassana field.

**Guidance**

While costs for the Wassana redevelopment are on budget, the Company anticipates
that accelerating the project, including the corresponding drilling activity, will
result in additional 2026 spending, mainly reflecting a shift from its 2027 budget
into 2026.  As a result, Valeura’s new full year 2026 Adjusted capex^((1)) (including
exploration spend) guidance is US$220 – 235 million (previously US$195 – 215 million).
Given the anticipated production plateau rate of approximately 7,500 bbls/d from
the new CPP, the Company anticipates that a two-month acceleration in start-up will
result in approximately 430,000 bbls in additional oil production in 2027, versus
the original project plan.

_(1) Non-IFRS financial measure or non-IFRS ratio – see “Non-IFRS Financial Measures
and Ratios” section_

**Wassana Redevelopment Background**

In 2025, Valeura took a final investment decision to redevelop its Wassana field
by deploying a new-build CPP with the objective of commercialising more oil volumes
than would be possible with the existing production facility, the mobile offshore
production unit (“MOPU”) _Ingenium_, which is due for decommissioning at approximately
the end of 2027.  The redevelopment project has resulted in an increase in the total
anticipated recoverable oil volumes and an extension in the anticipated end of economic
life of the field.  In addition, the CPP has been designed to facilitate the tie-
in of additional satellite production facilities, which may be built in the future
to develop additional accumulations of oil both to the north and south of the Wassana
field.  Recent mapping of the area south of the Wassana field has identified significant
additional oil volumes and the Company is currently reviewing exploration drilling
options to fully assess this satellite potential.