has provided an update on the construction of the Cascadura facility and Royston-
1X production testing. Touchstone has an 80 percent operating working interest in
the Cascadura field and the Royston-1X well, which is located on the Ortoire block
onshore in the Republic of Trinidad and Tobago. Heritage Petroleum Company Limited
holds the remaining 20 percent working interest.

**Cascadura**

The Cascadura-1ST1 and Cascadura Deep-1 downhole safety plugs were removed on July
8 and July 9, 2023, respectively. Both wells are currently shut in, with wellhead
pressures at approximately 4,100 pounds per square inch. It is anticipated that 
the Cascadura natural gas and liquids facility will operate between approximately
600 to 750 pounds per square inch.

On July 20, 2023 we completed the initial operational preparedness inspection of
the facility with the Ministry of Energy and Energy Industries (“MEEI”) which involved
a comprehensive evaluation of the facility’s infrastructure, safety protocols, and
operational procedures. Following the inspection, minor modifications to optimize
the facility’s performance and operational protocols were completed and the facility
was mechanically complete on July 30, 2023. Pressure testing of the facility with
inert nitrogen gas commenced on July 28, 2023, and is now 70% complete.

As we continue to pressure test the facility, we will finalize the electrical and
instrumentation connections required to link the Cascadura facility to the National
Gas Company of Trinidad and Tobago pipeline tie-in point. We are scheduling the 
final MEEI inspection this week prior to the introduction of initial natural gas
into the system.

**Royston**

Production testing at Royston-1X is ongoing and the Company will update the market
when testing has concluded.

> **Paul Baay, Touchstone President and Chief Executive Officer, commented:**
> “_Touchstone is working diligently to complete the commissioning of the facility
> and we are eager to commence first production. We continually strive to meet or
> exceed all industry regulations and guidelines and our adherence to the highest
> health and safety standards will continue to guide us through the completion of
> the facility._“

**Touchstone Exploration Inc.**

Touchstone Exploration Inc. is a Calgary, Alberta based company engaged in the business
of acquiring interests in petroleum and natural gas rights and the exploration, 
development, production and sale of petroleum and natural gas. Touchstone is currently
active in onshore properties located in the Republic of Trinidad and Tobago. The
Company’s common shares are traded on the Toronto Stock Exchange and the AIM market
of the London Stock Exchange under the symbol “TXP”.

Share on: