# Touchstone Exploration updates on Environmental Impact Assessment

- Link: https://www.directorstalkinterviews.com/touchstone-exploration-updates-on-environmental-impact-assessment/4121071442
- Published: 2022-07-06T07:10:05+01:00
- Author: Giles

**[Touchstone Exploration](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l)
Inc.** (TSX, [LON:TXP](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l))
has provided a further update on the status of the Cascadura Environmental Impact
Assessment (“EIA”) in support of an application for a Certificate of Environmental
Clearance, which must be approved by the Trinidad and Tobago Environmental Management
Authority (“EMA”) to conduct development operations within the Cascadura area in
the Company’s Ortoire block. Touchstone has an 80 percent operating working interest
in Ortoire block, with Heritage Petroleum Company Limited holding the remaining 
20 percent working interest.

Further to the Company’s announcement on June 27, 2022, and in accordance with the
EMA’s regulated review process, Touchstone continues to engage with the EMA and 
respond to its queries to support the Cascadura area EIA application.

The Company received an initial EIA Review and Assessment Report (“RAR”) from the
EMA on May 5, 2022 and responded to the requests raised on May 15, 2022. Following
receipt of a second RAR on June 24, 2022, Touchstone has submitted a partial response
and will be meeting with the EMA to clarify the remaining aspects to ensure that
the queries are addressed by the Company. Touchstone will provide further feedback
to the EMA as appropriate following this meeting. The EMA has noted that a determination
will be made within thirty working days of receiving a complete response to the 
second RAR.

The EIA application was initially submitted on December 23, 2021 and pursuant to
applicable legislation was to be determined by the EMA within 80 working days, unless
extended while the EMA seeks further information or clarifications. The latest RAR
represents the second extended date from the EMA beyond the original 80 working 
days review period.

As noted in the Company’s announcement on June 27, 2022, the forecasted onstream
date of the Cascadura facility will be established by the timing of receipt of the
approved EIA application, and the Company will update stakeholders as appropriate.

**Touchstone Exploration Inc.**

Touchstone Exploration Inc. is a Calgary, Alberta based company engaged in the business
of acquiring interests in petroleum and natural gas rights and the exploration, 
development, production and sale of petroleum and natural gas. Touchstone is currently
active in onshore properties located in the Republic of Trinidad and Tobago. The
Company’s common shares are traded on the Toronto Stock Exchange and the AIM market
of the London Stock Exchange under the symbol “TXP”.

Share on: