# Touchstone Exploration updates on drilling operations and amended bank loan

- Link: https://www.directorstalkinterviews.com/touchstone-exploration-updates-on-drilling-operations-and-amended-bank-loan/4121145762
- Published: 2024-03-04T07:05:27+00:00
- Author: Amilia Stone

**[Touchstone Exploration](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l)
Inc** ([LON:TXP](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l))
has provided updates on its bank debt and drilling operations.

**Bank Debt**

Touchstone’s wholly owned Trinidadian subsidiary, Touchstone Exploration (Trinidad)
Ltd., has entered into a binding term sheet with our existing Trinidad-based lender
providing for an increase in borrowing capacity of $13 million. The parties are 
currently documenting an amended and restated bank loan agreement and related security
registrations, following which the additional credit capacity will become effective.

The principal changes included in the Amended Bank Loan are as follows:

·      a new $10 million five-year non-revolving term loan facility, with no principal
repayment in the first year and sixteen equal and consecutive quarterly payments
thereafter; and

·      an increase in our current revolving loan facility borrowing capacity from
$7 million to $10 million, which will mature two years from the execution date and
may be renewed at the option of the parties thereafter.

Following execution of the Amended Bank Loan, Touchstone’s facilities will consist
of its unchanged existing seven-year term loan facility, the new five-year $10 million
term loan facility, and the increased $10 million revolving loan facility.

The existing seven-year non-revolving term loan facility has a current principal
balance of $21 million, with fourteen equal and consecutive quarterly principal 
payments of $1.5 million outstanding through to the June 15, 2027 maturity date.
We have $7 million drawn on our revolving loan facility, resulting in an aggregate
$28 million in bank debt principal currently outstanding.

We intend to use the additional Amended Bank Loan facility borrowing capacity to
finance our 2024 capital program as presented in our December 19, 2023 news release
entitled “_Touchstone Announces 2024 Capital Budget, Preliminary 2024 Guidance and
an Operational Update_“.

**Drilling Operations**

Touchstone Exploration has commenced drilling the Cascadura-3 development well and
the CO-374 development well. Cascadura-3 was spud on March 1, 2024 from our Cascadura
C surface location on the Ortoire block in which we have an 80 percent working interest.
The well is targeting gas-charged sands in the Herrera formation northeast of the
recently drilled Cascadura-2 well and is expected to be drilled to an anticipated
total depth of 7,000 feet using Star Valley Rig #205. CO-374 was spud on February
28, 2024 on our CO-1 block, in which we have a 100 percent working interest. The
well is targeting crude oil-charged sands in the Cruse and Forest formations and
is expected to be drilled to a total depth of 6,600 feet using PCSL Rig #8.

The Cascadura-2 well has been successfully cased after we encountered wellbore instability
issues due to high gas pressures which resulted in the need to sidetrack a portion
of the well. Operations are proceeding on the road and pipeline right-of-way which
will tie-in the Cascadura development wells to our Cascadura natural gas facility.
This project includes the preparation of the Cascadura B surface location, which
has been approved for the drilling of up to four additional development wells.

Share on: