# Touchstone Exploration Coho gas facility and pipeline to begin commissioning operations

- Link: https://www.directorstalkinterviews.com/touchstone-exploration-coho-gas-facility-and-pipeline-to-begin-commissioning-operations/4121075747
- Published: 2022-08-03T07:21:29+01:00
- Author: Giles

**[Touchstone Exploration](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l)
Inc.** (TSX, [LON:TXP](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l))
has announced that the Company has summitted a notice to residents in the community
that the Coho gas facility and pipeline will commence pre-commissioning and commissioning
operations. Pursuant to the Coho Certification of Environmental Clearance, residential
notification is required to be made a minimum of five business days prior to the
commencement of operations. The Coho area is located in the Ortoire block, where
Touchstone has an 80 percent operating working interest and Heritage Petroleum Company
Limited holds the remaining 20 percent working interest.

The pre-commissioning of the gas facility and pipeline consists of testing all electronics,
alarms, and operating systems in the facility, testing of the flare and emergency
shutdown systems, as well as purging air from the system using inert nitrogen gas.
Subsequent to these operations, system commissioning operations will commence, which
entails the introduction of natural gas from the Coho-1 well into the facility and
pipeline in a step rate manner, officially bringing the system onstream to the Central
block natural gas facility.

Coho-1 will commence production following completion of the commissioning and pipeline
handover process, with the expectation that production will increase over time to
10 MMcf/d (1,667 boe/d) gross, 8 MMcf/d (1,333 boe/d) net. Touchstone will provide
further information once production is optimized through the system.

> **Paul Baay, Touchstone Exploration** **President and Chief Executive Officer,
> commented:**
> _“The completion of the Coho facility and pipeline will be a significant milestone
> for Touchstone, as it will represent our first natural gas production and is expected
> to double our current production on a boe basis. Throughout this process we have
> encountered challenges that have provided us valuable knowledge to streamline 
> the construction of the Cascadura facility._ _During the pre-commissioning and
> commissioning process, we will need to balance the system with the well, pipeline
> and Central block facility. We will keep all stakeholders informed of our progress,_
> _and I would personally like to thank our shareholders for their continued patience
> as we proceed to full commercial production.”_

Share on: