# Touchstone Exploration Cascadura Deep-1 data confirms substantial liquids rich gas discovery

- Link: https://www.directorstalkinterviews.com/touchstone-exploration-cascadura-deep-1-data-confirms-substantial-liquids-rich-gas-discovery/412992602
- Published: 2021-05-25T07:09:42+01:00
- Author: Giles

[Touchstone Exploration](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l)
Inc. (TSX, [LON:TXP](https://www.directorstalkinterviews.com/company/touchstone-exploration-inc/txp.l))
has provided an operational update, highlighted by the recovery of pressure gauges
from the Cascadura Deep-1 well on the Company’s Ortoire onshore exploration block
in Trinidad (Touchstone 80 percent working interest operator, Heritage Petroleum
Company Limited 20 percent working interest).

As previously announced, the Cascadura Deep-1 well was completed over a 199-foot-
thick interval in Sheet Four of the overthrust Herrera Formation. Following production
testing operations, the well was shut in for a pressure buildup test on April 11,
2021, and the pressure gauges were recovered on May 17, 2021.

**Cascadura Deep-1 Testing Highlights**

·      Buildup test data showed no depletion with a final bottomhole pressure of
4,746 psi, confirming a substantial liquids rich gas discovery.

·      Analysis of buildup data showed the test was unbounded with a minimum radius
of investigation of 1,500 feet, confirming the significant size and reserves potential
of the pool.

·      While the well test data indicated that the formation was damaged, we are
confident that the well will require no stimulation and that flow rates will be 
consistent with those during testing (average flow back rate of 22.9 MMcf/d of natural
gas and 449 bbls/d of NGLs).

·      Natural gas produced during the production test was approximately 94 percent
methane with no hydrogen sulfide and NGLs consisted of 57 degree API condensate 
with no associated hydrogen sulfide.

·      There remains approximately 560 feet of potential pay above the completed
zone which can be evaluated in future development.

**Operational Highlights**

·      The COVID-19 state of emergency in Trinidad currently has not had a significant
impact on the Company’s day-to-day operations, although related restrictions are
causing delays to construction and field work.

·      The design for the main production facility at Cascadura has been completed
with an initial production capacity of 90 MMcf/d (expandable to 200 MMcf/d).

·      Requested to complete an Environmental Impact Assessment (“EIA”) on the Cascadura
development project that will enable us to undertake a pre-approved multi-year program
including drilling, completions, facilities, gathering lines and the main sales 
infrastructure without the time intensive application process that would have previously
accompanied each individual workstream.

·      Royston location preparation has been delayed due to COVID-19 restrictions
impacting construction, with the well anticipated to spud in June 2021.

·      Royston seismic program continues with 149 of 370 shot holes drilled and 
data acquisition anticipated to commence mid June 2021.

·      Coho surface facility is nearing completion and awaiting pipeline installation
and tie-in.

·      Chinook-1 testing continues with the planned completion of the Cruse sands
currently awaiting regulatory approval.

> **Paul Baay, President and Chief Executive Officer, commented:**
> “I am pleased to report that the downhole gauges recovered from Cascadura Deep-
> 1 have provided excellent data, and the information has increased our confidence
> in the substantial size of the pool’s reserves and its potential deliverability.
> The data is consistent with the previous testing performed at Cascadura-1ST1, 
> and we are encouraged by the lack of any boundary limits observed on the reservoir.
> The team continues to move all of our projects forward under the COVID-19 restrictions
> that were recently enacted in Trinidad. We continue to have a comprehensive COVID-
> 19 protocol in place in collaboration with our industry partners, and we are committed
> to the safety and well being of our employees, contractors and the residents of
> the communities we operate in. For the most part, our routine operations remain
> uninterrupted, and we will recommence the affected operations as soon as we can
> safely do so.
> I remain confident that we will spud Royston-1 in June despite recent construction
> delays due to COVID-19 emergency health measures. The drilling of Royston-1 will
> complete the first phase of our exploration program at Ortoire. The second phase
> is expected to include the Steelhead and Guabine prospects targeting the Herrera
> and Karamat Formations, as well as our Cretaceous prospect at Kraken. The phase
> two exploration program is anticipated to be performed in parallel with development
> programs at our confirmed Ortoire discoveries. Our future capital projects are
> anticipated to commence following the start of production from Coho and Cascadura,
> as these discoveries are expected to provide the funding for our future development
> and exploration programs.”

**COVID-19 Update**

A state of emergency was declared in Trinidad and Tobago on May 15, 2021 with a 
curfew between the hours of 9:00 p.m. to 5:00 a.m. in an effort to combat the rising
number of COVID-19 cases and deaths. The state of emergency was an enhancement to
other restrictions that were already in place including limitations on non-essential
businesses and services. Our operations have been granted essential service status
but some of our suppliers have not, which has resulted in partial delays to our 
current exploration activities. The state of emergency has not materially affected
our base production operations but has impacted the preparation of the Royston-1
well access road and the shipping of the third-party rig to Trinidad.

Regulations that were due to expire on May 23, 2021 have been extended to July 4,
2021. This is separate from the current state of emergency, which will be debated
in Parliament and will continue until necessary for up to three months. However,
we will continue to manage our operations in accordance with domestic regulations
and only proceed when we have access to all the required services available for 
safe and cost-effective operations.

**Cascadura Deep-1 Testing**

The pressure recorders were recovered from the Cascadura Deep-1 well on May 17, 
2021 and provided 44 days of data that included initial completion pressure, isochronal
flow and shut-in buildup data. During the buildup period, the Company observed bottomhole
pressures returning to pre-test levels, with a final shut-in pressure of approximately
4,746 psi (Cascadura-1ST1 test one (lower): 4,762 psi, test two (upper): 4,715 psi).
The buildup data suggested that the formation was damaged to some extent during 
drilling, with an estimated skin of between +4 and +7 (Cascadura-1ST1 test one (
lower): +0.1, test two (upper): -1.1). Based on flowback observations, the Company
believes that the well will continue to clean up once on production. No boundaries
were observed during testing, with a radius of investigation of over 1,500 feet,
confirming previous results observed at Cascadura-1ST1.

Gas analysis at Cascadura Deep-1 displayed a methane content of 93.7 percent (Coho
98.6 percent, Cascadura-1ST1 test one (lower) 93.3 percent) while NGL analysis indicated
57 degree API condensate (Cascadura-1ST1: 53 degree API condensate). No hydrogen
sulfide was observed in any samples, and no produced water was recorded during testing.

> **James Shipka, Chief Operating Officer, commented:**
> “The data gathered from Cascadura Deep-1 reinforced our interpretation of the 
> Cascadura structure and is extremely encouraging for the production potential 
> of the well. This test completed 199 feet of a total of 1,007 feet of reservoir
> observed in the overthrust Herrera section, and there remains nearly 560 feet 
> of high-quality sand above the existing zone in the Sheet Three section for future
> development. Given the nature of the Herrera sands, the existing completion should
> efficiently drain the gas and associated liquids trapped in Sheet Four. Flowback
> testing suggested that the formation had been damaged during drilling, and the
> buildup data quantified the magnitude of the damage. We believe that the well 
> will clean up during production and that no stimulation is required at this time.
> We are now focused on bringing both Cascadura wells onto production as well as
> completing our comprehensive field development plan to efficiently exploit the
> potential of the Cascadura structure.”

**Cascadura EIA and Main Production Facility**

The Company has been advised by the Trinidad Environmental Management Authority 
that an EIA is necessary for the Cascadura development project. While this will 
require considerable upfront work, once completed it will allow us to roll out a
multi-year program including drilling, completions, facilities, gathering lines 
and the main sales infrastructure. The Company is expecting to receive the requirements
for the EIA on May 28, 2021. While this will initially delay the project, it will
bring predictable and clear timelines for Cascadura operations moving forward. The
Company will provide further information on anticipated timing of the EIA as it 
becomes available.

We have completed the design for the Cascadura main production facility and will
be soliciting bids for the required components and construction of the surface facilities.
The design contemplates an initial production capacity of 90 MMcf/d (expandable 
to 200 MMcf/d as development progresses) with the ability to recover and sell all
free liquids from current and expected future wells.

**Royston**

Touchstone is currently waiting on availability of the necessary soil stabilization
materials to complete construction of the Royston-1 access road and surface location.
Access to these materials is dependant on our suppliers being able to comply with
the current COVID-19 restrictions. The drilling rig is in the final stages of pre-
spud preparation and will be available to move immediately upon the completion of
the access road. All drilling personnel are on the ground in Trinidad and have cleared
the required quarantine protocols.

Independent of the drilling of Royston-1, we are currently in the process of acquiring
2D seismic data with 149 shot holes drilled to date out of a total of 370. Weather
has been favorable thus far, and we are targeting to shoot and record data commencing
the second week of June 2021. This data will provide information on possible development
drilling at Royston, along with optimizing the location for the future Kraken well
to test the Cretaceous Formation.

**Coho **** **

The Coho facility construction at the Coho-1 well is nearly completed and we expect
to commence testing in the next three to four weeks. The Company is currently awaiting
final direction from the National Gas Company of Trinidad and Tobago regarding the
preferred delivery point for Coho gas volumes. Once this has been provided, the 
Company will begin pipeline construction which is anticipated to take 60 days subject
to weather conditions.

**Chinook**

The testing of the Herrera zones at Chinook-1 has been completed, and the Company
will move up-hole to test the Lower Cruse Formation which indicated gas while drilling.
The Cruse Formation appears to be aerially extensive with hydrocarbons having been
observed and produced throughout the Ortoire block and the surrounding area. Gas
shows were encountered at the nearby Cascadura project while drilling, and the Company
looks forward to testing the commercial potential of these sands.

In the Herrera zones, test three of the Chinook-1 well was put to pump and, after
seven days, showed very limited to no new-fluid inflow with only load fluid and 
minimal oil being recovered. The well was shut in for a buildup period at which 
time the well experienced a substantial surge of reservoir fluid and solids from
the formation. This inflow appears to have encapsulated the downhole assembly in
sand, and following several attempts, we believe the pump to be unretrievable. This
zone will be abandoned as we now focus on the shallow Cruse completion.

The Company has identified two additional locations significantly updip from the
original Chinook well to evaluate the economics of the Chinook structure in the 
Herrera Formation. Given the limited inflow observed during testing and the skin
damage reflected by the Cascadura Deep-1 testing, the Company is confident that 
the Herrera section of the Chinook-1 well was damaged while drilling. We are evaluating
alternative drilling designs to limit possible reservoir damage in any future wells
at Chinook.

**Touchstone Exploration Inc.**

Touchstone Exploration Inc. is a Calgary, Alberta based company engaged in the business
of acquiring interests in petroleum and natural gas rights and the exploration, 
development, production and sale of petroleum and natural gas. Touchstone is currently
active in onshore properties located in the Republic of Trinidad and Tobago. The
Company’s common shares are traded on the Toronto Stock Exchange and the AIM market
of the London Stock Exchange under the symbol “TXP”.

Share on:
