# Tirupati Graphite Madagascan projects complete, aiming for 8% of global flake graphite demand

- Link: https://www.directorstalkinterviews.com/tirupati-graphite-madagascan-projects-complete-aiming-for-8-of-global-flake-graphite-demand/4121091470
- Published: 2022-11-24T07:14:12+00:00
- Author: Giles

**[Tirupati Graphite plc](https://www.directorstalkinterviews.com/company/tirupati-graphite-plc/tgr.l)**(
[LON:TGR](https://www.directorstalkinterviews.com/company/tirupati-graphite-plc/tgr.l),
TGRHF.OTCQX), the specialist graphite and graphene company developing sustainable
new age materials, has provided an update in continuation to its announcement released
on 22 September 2022 on the ongoing developments and operations of the Sahamamy 
and Vatomina projects in Madagascar.

_**Vatomina operations and development**_

·    The Vatomina preconcentrate plant continues to operate uninterrupted following
its reorganisation and the Company is pleased to advise that:

o Both the preconcentrate and final concentrate plants continue to operate over 
the name plate ore feed capacity of 600 tons per day completely synchronised with
smooth and constant operation;

o The construction and installation of the second preconcentrate plant at Vatomina
is now complete, with trial runs and integration to the existing operations in process;

o With reduction in ore movement activities, the current heavy earthmoving mining
machinery (‘HEMM’) fleet has completed the development of other infrastructure and
nascent mining areas, which meet the ore feed requirements of the second preconcentrate
plant; and

o Strengthening of internal roads and other infrastructure developments at Vatomina
are now complete and well prepared to mitigate the risks from adverse weather conditions
in the future.

·    The Company does not foresee any challenges in stabilising Vatomina operations
at above 1,200 tons ore feed per day with effect from December 2022; stabilising
operations at 12,000 tpa output as planned.

_**Sahamamy operations and development**_

·    The operations and development of Sahamamy has continued at full pace and the
Company is pleased to advise that:

o The new road connecting Sahamamy project to National Highway 2 and Vatomina project
has been strengthened throughout the nearly 40 kilometres of road, with the last
few kilometres currently under completion;

o The existing 3,000 tpa plant at Sahamamy remained in operation and shall be decommissioned
in December following the stabilisation of the second preconcentrate operations 
in Vatomina;

o Extensive mine development has been executed in the nascent Sahasoa deposits of
the Sahamamy project and is ready to provide the required 1,200 tons per day of 
ore for the new plants;

o Construction and installation of both pre-concentrate plants in Sahamamy are now
complete with tests and trial runs initiated;

o Construction and installations at the main processing plant is substantially complete
at Sahamamy;

o We remain on target to stabilise operations of the 18,000 tpa plant by end of 
the current quarter;

o The first power generation from the 100Kw hydro power plant (‘HPP’) has been achieved
during November with integration and commercial use underway with related cost savings
expected to commence from December;

o To progress the next HPP of 400 Kw, related studies and application for required
approvals have been initiated.

> **Shishir Poddar, Tirupati Graphite** **Executive Chairman, said:**
> _“We have come a long way in a short time and have effectively brought under control
> the impacts of the adverse conditions experienced in Madagascar earlier this year.
> Our innovative and cost-effective solutions have started to bear fruit. Market
> conditions for graphite are very positive, and this is the ideal time for us to
> be increasing production of this critical material._
> _“With the turnaround of the Madagascan projects now complete, we are again progressing
> towards our aim of providing approximately 8% of global flake graphite demand.”_