# Tirupati Graphite Completion of Commissioning & Start of Sellable Production from Vatomina Plant

- Link: https://www.directorstalkinterviews.com/tirupati-graphite-completion-of-commissioning-start-of-sellable-production-from-vatomina-plant/4121020857
- Published: 2021-09-06T07:17:56+01:00
- Author: Giles

**[Tirupati Graphite plc](https://www.directorstalkinterviews.com/company/tirupati-graphite-plc/tgr.l)**(
[LON:TGR](https://www.directorstalkinterviews.com/company/tirupati-graphite-plc/tgr.l)),
the fully integrated, revenue generating, specialist graphite producer and graphene
and advanced materials developer, has advised that it has completed the installation
and commissioning of its first 9,000 tpa flake graphite module at its Vatomina Project
in Madagascar. 

**Highlights**

·    Completed the installation and commissioning of first 9,000 tpa flake graphite
module at Vatomina, which brings the total production capacity in Madagascar to 
12,000 tpa on the path to reaching total production capacity of 84,000 tpa by 2024.

·    Equipment testing, dry and wet commissioning trials completed successfully 
allowing initiation of ore feed and start of sellable production at start-up ore
feed rate of 15 tonnes per hour (“tph”), being 50% of the plant rated capacity; 
ore feed rate being progressively increased up to full rated plant capacity.

·    Stockpiling of finished products commenced with first shipment to fulfil pre-
orders received by the Company from customers in Europe, USA and Asia expected within
2 weeks generating first revenues from Vatomina.

·    Other ongoing activities across the two Madagascan projects include:

o  Progressing with Stage II exploration and drilling programmes initiated in February
2021;

o  Extension of internal infrastructure and roads, including a road connecting the
two projects;

o  Redevelopment of the Sahamamy hydropower plant to a 100-kilo watt capacity; and

o  Initiation of activities for the development and advancement of construction 
of the second 18,000 tpa module at Sahamamy.

> **Shishir Poddar, CEO of Tirupati Graphite, said, Shishir Poddar, CEO of Tirupati
> Graphite, said, **_“We are delighted to have completed the commissioning of the
> first of four modules at Vatomina, which marks the latest in a series of investments
> to increase production of high-quality graphite from our projects in Madagascar
> to support world demand and continue the expansion of our production capacity 
> up to 84,000 tpa by 2024. This is a commendable achievement for the Company given
> the procurement and logistics challenges that were faced by the team whose tireless
> efforts enabled us to successfully execute our plans to upscale the plant capacity
> to 9,000 tpa and get into production. This is an important milestone as it now
> brings both our Madagascan projects into operation and advances us on our journey
> of becoming a material global supplier of sought-after Madagascan flake graphite._
> _“We recently announced 12-month trading results from our 3,000 tpa Sahamamy plant,
> which further demonstrated the low-cost advantage we possess in our operations.
> With 12,000 tpa of production capacity (i.e., 4x increase from current) now operational,
> we expect the unit cost of production to be improved, which will lead to an enhancement
> on the c.57% gross operating margins that was achieved at Sahamamy, as the production
> output at Vatomina ramps up to the full rated capacity of 9,000 tpa.  The start
> of production at Vatomina provides us with additional revenues and operational
> margins, which will be used to partially fund our development funding costs going
> forward._
> _“Our recent announcement regarding the impending acquisition of a portfolio of
> advanced stage graphite assets in Mozambique will, if completed, boost our mineral
> resource base by over 152 million tonnes @ 8.5% TGC, complementing_ _our existing
> mix of predominantly jumbo and large flake graphite products from our Madagascan
> projects. We continue to rework the development plans for these projects and look
> forward to updating the market as we progress to secure the approvals for completion
> of the acquisition.” _

**Details**

The Company remains focused on strengthening its primary mining and processing in
Madagascar where it operates two high-quality flake graphite projects, Sahamamy 
and Vatomina, which are being developed using a modular approach that provides the
flexibility to respond to evolving graphite market conditions. 

Having commenced production at Sahamamy in March 2019, Tirupati has now completed
the installation and commissioning of its first 9,000 tpa flake graphite module 
at Vatomina, which brings the total production capacity in Madagascar up to 12,000
tpa.  Notably, both projects offer a favourable larger flake size distribution, 
which is priced at a considerable premium to smaller size flakes and is being sold
to customers globally. As previously announced in the Company’s trading results (
refer RNS dated 24 August 2021), the ‘_Average Selling price per MT of Production’_
achieved was US$801/£605. Under the Company’s medium-term development plan (‘MTDP’),
total capacity in Madagascar is planned to increase to 84,000 tpa by 2024. 

The plant’s design, construction and installations were undertaken by the Company
using its demonstrated capabilities and experience with the development, construction,
implementation, and operations of the 3,000 tpa module at Sahamamy. Major activities
included, but were not limited to:

o  Construction of circa 22,000 square feet (“ft^(2)“) of covered buildings including
the main plant building, engineering centre, stores, office building and residential
accommodation buildings and associated facilities;

o  Design of the raw material crushing and feed system tailor made for the saprolitic
ore type from the projects, which were manufactured at the engineering centre by
the Company at the plant site;

o  Two Self Attrition Graphite Extractors (‘SAGE’) units installed in a series, 
SAGE is a proprietary equipment designed and manufactured by the Company’s founders
that removes sand from the graphite ore at the first stage or the process and is
being successfully used at Sahamamy;

o  A set of milling and flotation equipment which are the key processing circuit
components in the process plant to enrich the flake graphite up to 96% purity;

o  Installing dewatering, drying, screening, blending and magnetic separator systems
for finishing of flake graphite products that are tailor-made to customer requirements;

o  Installing an electrical system that included 61 electrical motors of ratings
ranging from 1 Horsepower (‘hp’) to 50 hp for a total >530 hp; 12 electrical control
and supply panels; 3 diesel generator sets with combined capacity of c.900 Kilo 
Volt Amperes; and over 3 circuit kilometres of flexible copper cabling;

o  Installing a set of input water, process and tailing pumps integrated with c.
3 kilometres of water and tailings line piping.

o  Set up of a Quality Control Laboratory with capacity to test >75 graphite ore,
process and finished product samples per day and perform microscopic studies of 
ore and finished products which is planned to be strengthened further with X-ray
fluorescence spectroscopy and similar equipment to meet advanced testing requirements
of the Company’s high-tech customers.

o  Two mining pits have been opened and supplying ore to the ROM pad and feedstock
to the process plant (see RNS dated 21 April 2021).

The commissioning and start of production processes included a series of dry trial
runs for each plant equipment followed by the entire processing plant.  Wet runs
were then executed equipment wise and for the entire process plant, after which 
feed of ore and start of sellable production was initiated at start-up ore feed 
rate of 15 tph, being 50% of the plant’s rated capacity. All equipment testing, 
dry and wet commissioning trials were completed successfully with no material defects
requiring rectification. The ore feed rate is being progressively increased up to
the plants rated capacity as production output ramps up to full plant capacity over
the coming 4 to 6 weeks.

The capacity of the first module at Vatomina was upscaled to 9,000 tpa in February
2021 (see RNS dated 8 February 2021), in response to increased demand. Additional
work to upscale the capacity included:

o  Increasing the planned constructed area from c.15,000 ft^(2) to 22,000 ft^(2);

o  Modification of the previously received flotation equipment to upsize capacity;

o  Addition of a larger primary mill, two higher capacity SAGE units used for sand
separation, one flotation cell, a larger crushing system and additional finishing
equipment;

o  Increasing the mining equipment fleet size;

o  Increasing the previously planned capacity of ancillary facilities including 
power generation and distribution system and water management system.

A number of other development activities continued alongside at the Company’s two
Madagascan projects, which include, but are not limited to:

o  Progressing with Stage II exploration and drilling programmes initiated in February
2021 (see RNS dated 10 February 2021);

o  Construction of additional and strengthening of existing internal infrastructure
and roads, including a road connecting the two projects (see RNS dated 21 April 
2021);

o  Redevelopment of the Sahamamy hydropower plant to a 100-kilo watt capacity (see
RNS dated 8 March 2021);

o  Initiation of activities for the development and advancement of construction 
of the second 18,000 tpa module at Sahamamy (see RNS dated 29 June 2021).