# Tirupati Graphite commercial flake production commenced at Sahamamy Project

- Link: https://www.directorstalkinterviews.com/tirupati-graphite-commences-production-from-new-facilities-at-its-sahamamy-project/4121106837
- Published: 2023-02-20T07:11:41+00:00
- Author: Amilia Stone

**[Tirupati Graphite plc](https://www.directorstalkinterviews.com/company/tirupati-graphite-plc/tgr.l)**(
[LON:TGR](https://www.directorstalkinterviews.com/company/tirupati-graphite-plc/tgr.l)),
the specialist graphite and graphene company developing sustainable new age materials,
has announced that it has commenced production from the newly built 18,000 tons 
per annum flake graphite production facilities at its Sahamamy project in Madagascar.
The Company has thus reached a globally significant 30,000 tpa flake graphite capacity
and is progressing towards a steady state >80% production in the near term.

The Company also provides an update on the ongoing developments and operations at
both of its flake graphite projects in Madagascar, and other corporate activities.

_Sahamamy Project, Madagascar_

·   Construction, installation & commissioning of new facilities with a name plate
capacity to produce 18,000 tons of flake graphite per annum has been completed and
commercial production has commenced.

·    The new facilities created include:

o new mining equipment fleet with a capacity to mine c.450,000 metric tons per annum(‘
tpa’) run of mine graphite ore;

o two pre-concentrate plants each with 600 metric tons per day (‘tpd’) ore processing
capacity aggregating to c.400,000 tpa ore processing capacity;

o a final concentrate plant with capacity to produce 18,000 tons flake graphite 
per annum matching the preconcentrate capacity;

o c.3 kilometre long slurry pumping system for transport of preconcentrate product
from the preconcentrate units set up at the Sahasoa deposits to the final concentrate
unit; and

o ancillary facilities including but not limited to stores, office, laboratory and
residential facilities, processing plant water and tailing management facilities
etc.

·   The head grade feed to the preconcentrate plant was in the target range of 4–
5% and the target product grade of >95% has been achieved.

·   The mining and processing operations are fully commissioned and the Company 
will now ramp-up production and commercial sales.

·    There have been no significant challenges in the commissioning of the new facilities
and the operations are expected to reach the minimum stable output of 80% of name
plate capacity by March 2023.

·    The startup of these new facilities was delayed by three months owing to shipping
delays and weather-related interruptions caused by cyclone Cheneso.

_Vatomina Project, Madagascar_

·  The second preconcentrate unit has been seamlessly operating since the Company
reported its commissioning and integration with the existing operations on 29 December
2022.

·    Progress has been made in improving the average head grade at Vatomina by using
the extension deposits of the currently operating pits.

·    The Company is engaged to take steps to reach the name plate capacity of 12,000
tpa production by improving the head grade to an average of >3.5% from the current
2.5% range.

_Cyclone Cheneso_

·   In the final months of 2022, the Company worked on strengthening its infrastructure
before the onset of rainy season which ensured that there was minimal damage from
the recent severe weather.

·   In mid-January 2023, cyclone Cheneso hit Madagascar including the areas where
the Company’s projects are located.

·    As a precaution, Tirupati temporarily scaled back operations at both its projects
for a period of ten days to ensure safety of its personnel and assets.

·    There were no injuries to the Company’s personal and no damage to its property,
plant and equipment.

·  The infrastructure built by the Company across both its projects and the road
connecting the two sustained no significant damage.

·    Operations were scaled up to normal as water levels receded.

·    The Company remains well prepared to mitigate the effects of any further adverse
weather conditions.

_Suni Resources SA_

·   The acquisition of Suni Resources SA from Battery Minerals Limited continues
to progress to completion.

·   The Mining License for Balama Central Project was issued to Suni Resources SA
following the submission of a Bank Guarantee, and is valid until 23 July 2046.

·   The payment of Capital Gains Tax has been facilitated by the Company and all
regulatory conditions to completion have now been satisfied.

·   The Company and Battery Minerals Limited are actively working and fully committed
to completing the remaining procedural documentation and procedures to allow completion
in the coming weeks.

_Guidance of production_

·    In September 2022, the Company provided production guidance for the period 
October 2022 to March 2023 based on the assumption that the commissioning of the
Sahamamy project would occur in November 2022.

  ·   The start-up of the Sahamamy project was in effect delayed by three months
owing to shipping delays and the recent cyclone which has led to a three-month deferral
in guidance. As such, the new guidance is as follows:

| Period | Vatomina (tons) | Sahamamy (tons) | Total (tons) | 
| January to March 2023 | 1,700 – 1,900 | 800 – 1,000 | 2,500 – 2,900 | 
| April to June 2023 | 2,600 – 2,800 | 3,500 – 3,700 | 6,100 – 6,500 |

> **Shishir Poddar, Tirupati Graphite Executive Chairman, said:**
> _“The start of production at the new 18,000 tpa Sahamamy project is a significant
> milestone for us. This takes our production capacity to 30,000 tons of high-quality
> flake graphite cementing our position as a leader in the space. I want to thank
> the team on the ground for their efforts and particularly given the severe weather
> difficulties faced._
> _“The outlook for global graphite demand is overwhelmingly positive. As a key 
> component in EV batteries, the continued growth of the electric vehicle industry,
> with sales exceeding 10 million in 2022, will drive the demand and price of graphite
> for the foreseeable future. Security of supply is critical to the growth of the
> EV industry. While we will remain focussed on bringing our projects to name plate
> capacity production in the immediate term, we will continue to grow to the 84,000
> tpa production from our Madagascar projects and engage for furthering the development
> of the assets we are acquiring in Mozambique to seize opportunities the energy
> transition and green economy brings to us.”_