# Taylor Wimpey Returning to construction in a safe and managed way

- Link: https://www.directorstalkinterviews.com/taylor-wimpey-returning-to-construction-in-a-safe-and-managed-way/412814887
- Published: 2020-04-23T07:37:40+01:00
- Author: Amilia Stone

**[Taylor Wimpey plc](https://www.directorstalkinterviews.com/ftse-company/taylor-wimpey-plc/tw.l)**(
LON:TW) today released an update on our response to COVID-19 and our current trading
to coincide with the Annual General Meeting.

Further to our update on 24 March, which announced the orderly closure of sites,
show homes and sales centres, today we set out an update on trading, our strong 
cash position, and our planning and practical steps for a phased return to construction
in May, subject to the latest Government guidance and medical advice.

> **Pete Redfern, Chief Executive, commented:**
> “Our first priority is always the health and safety of our customers, employees,
> subcontractors and suppliers. We took an early decision at the end of March to
> close our sites while we assessed in detail how to build homes without compromising
> on health and safety or quality. We are now confident that we have clear plans
> and processes in place so we can safely start back on site in a phased way beginning
> on 4 May. 
> In the period while our sites have been closed, trading has inevitably been impacted.
> However, we are still seeing continued demand for our homes and our sales teams
> have been selling homes remotely, and digitally, week to week. Cancellations represent
> less than 1% of our current order book. We have a strong balance sheet and have
> managed the business conservatively and are as well positioned as we can be in
> the very difficult circumstances.  
> The past few weeks have been unlike anything we have seen before, presenting huge
> challenges for businesses and individuals, and we support the measures put in 
> place by the Government to reduce the spread of the virus and safeguard the NHS
> and public health. I would like to thank each and every one of our people for 
> their outstanding efforts and commitment, and the way in which they have come 
> together, working extremely hard not only to support the business and its performance,
> but to provide invaluable help to their local communities.”

**Overview**

·    Remobilisation to start on 4 May with a phased process based on detailed new
site operating protocols developed in compliance with strict social distancing requirements,
on the majority of our sites in England and Wales

·    Sales centres, show homes and regional offices to remain closed while we monitor
latest guidance around social distancing. We will continue to provide service to
customers and sell remotely and digitally

·    Order book has continued to increase and as at week ending 19 April 2020, the
total value stood at approximately £2,677 million (2019 week 16: £2,399 million)

·    Strong balance sheet and gross cash position of c.£836 million as at 22 April
2020  

**Return to construction in a safe and managed way**

Today we are setting out our strategy for a phased return to site construction and
operating, with strict social distancing protocols. This is based on current Government
and medical guidelines and will allow us to operate a sensible and well managed,
slow but steady return to activity. Our own site management teams will use the week
commencing 4 May to prepare sites for a new method of operating with the first subcontractors
returning on the week commencing 11 May.

On 24 March we announced the orderly closing of our sites, show homes and sales 
centres to protect the health and safety of our customers, employees and subcontractors
across the UK. While construction was deemed a permitted activity by the UK Government,
we believed that it was essential to be confident that we could modify our working
practices to adhere to strict social distancing guidance and this required time 
and careful planning. We received strong support for this early decision from all
stakeholder groups, particularly our customers, employees and subcontractors.

**Revised protocols and guidelines**

Since then, we have worked closely with our partners, reviewing guidance issued 
by the Construction Leadership Council (CLC) and taken advice from the Health and
Safety Executive, to assess each and every aspect of our site activities and address
the changes that need to be made to fully comply with the restrictions imposed by
social distancing requirements.

We are now confident that we have a clear set of detailed protocols and revised 
guidelines which we can operate safely, and on a sustainable basis for as long as
is necessary. These protocols include a fully revised set of working practices and
additional precautionary measures including modified site operational practices,
revised Risk Assessments, inductions, and changes to site format, including bespoke
PPE for two person tasks which we have designed in-house.

In addition, we have created the Taylor Wimpey COVID-19 Code of Conduct setting 
out our commitment to deliver a safe working environment for our employees and subcontractors
working on site, while stating our very clear expectations of behaviours of all 
those visiting our sites to work. We will be regularly monitoring and enforcing 
these behaviours on our sites and will require all staff, subcontractors and suppliers
to sign up to this Code of Conduct in advance of starting on site. This has been
based on the CLC guidance document which we have positively adapted and enhanced
for a housebuilding setting. We welcome the news that, going forward, the Health
and Safety Executive will be monitoring safe processes in response to COVID-19 on
site.

**Phased remobilisation**

From the week commencing 4 May 2020 we will start the process of remobilisation 
of construction, with the support of our site management team, in a controlled and
managed way, on the majority of our sites in England and Wales. This decision is
based on current Government guidance and medical advice and, if this was to tighten
further, we would conduct a further review. At this stage we do not expect to start
work in Scotland, until a return to construction receives the Scottish Government’s
support. In order to ensure that the correct behaviours are embedded, we have planned
a managed and gradual site start, and as a result, we do not expect to deliver meaningful
build progress until mid-May. We will assess build output on each site based on 
meeting the new social distancing protocols. The phased nature of our remobilisation
is key to making the necessary adjustments to site safety and to properly train 
our employees, suppliers and subcontractors in the new requirements and ways of 
working. We will also make our new working practices available to others if requested
free of charge, which we believe will be useful for smaller housebuilders with limited
resources.

**Sales centres, show homes and customer support**

We do not plan to reopen sales centres, show homes or regional offices at this time.
It is likely that the decision to reopen sales centres will be closely linked to
a general relaxation of conditions for non-essential retail, and will not happen
until we feel able to assure the safety of our employees, subcontractors and customers.

We continue to perform urgent and critical customer care tasks and are looking to
increase the number of these that we can complete under current restrictions, particularly
focusing on emergency and outdoor items. This will always be subject to the ability
to carry out the work safely and our customers being happy that the arrangements
are right for them.  

**Learnings from Spanish business**

Spain is now moving into the early stages of relaxation of the lockdown rules and
our small Spanish business will help to provide us with an early understanding of
the potential issues that may arise as we carefully recommence activities there.

**Positive net sales and trading**

Total Group completions (including joint ventures) in the 16 weeks to 19 April 2020
were 2,271 (2019 week 16: 2,644), reflecting the impact of our site closures. While
our sales centres and show homes have remained closed, throughout the period of 
the lockdown we have continued to sell homes, support existing customers and progress
purchases on a remote basis. Whilst new homes sales have been at lower levels, we
are encouraged by the continued demand for our homes, at a time when customers have
been unable to visit our sites or show homes. Since closing our sites and sales 
offices, cancellations have represented only 0.8% of the total order book and new
sales have exceeded the number of cancellations, meaning that we have grown our 
order book during shutdown by more than 200 units. These sales are at prices comparable
to those achieved in the first quarter of 2020, and do not contain any bulk sales.

As part of the orderly closedown of sites after 24 March, where it was deemed safe
to do so, and being mindful of customers individual circumstances, we offered customers
whose homes were build complete and had passed our Home Quality Inspection process
the option to complete their move in the days that followed, which a number chose
to do.

As a result of our new digital reservation process, our order book has continued
to increase and at week ending 19 April 2020, its total value stood at approximately
£2,677 million (2019 week 16: £2,399 million). This represents 10,880 homes (2019
week 16: 10,291 homes), excluding legal completions to date, of which well over 
half are exchanged (including affordable).  

**Strong balance sheet and cash position**

As previously announced, we have fully drawn down our £550 million Revolving Credit
Facility and as at 22 April, we had cash balances of c.£836 million. This strong
liquidity position means that our focus is very much on future opportunities rather
than solely short term cash generation.

As previously announced, in light of the uncertainty caused by the pandemic, the
Board took the decision to cancel the 2019 final dividend of 3.80 pence per share(
c.£125 million) that was due to be paid on 15 May and the planned 2020 special dividend
payment of 10.99 pence per share (c.£360 million) that was due to be paid on 10 
July.

Her Majesty’s Treasury has confirmed that we are eligible in principle, subject 
to documentation, as an issuer of the Covid Corporate Financing Facility (CCFF).

**Engaged and motivated employees**

We are very proud of how our employees have responded during this crisis, going 
above and beyond both for Taylor Wimpey and in the interests of their customers 
and wider communities. To support the long term [sustainability](https://www.directorstalkinterviews.com/sustainability-green-stocks-news)
of the business, we have taken the decision to utilise the Government’s Coronavirus
Job Retention Scheme. The decision to furlough employees has been based solely on
the level of work they could meaningfully do while sites were closed, and all of
our employees remain important to the future of Taylor Wimpey. To support our furloughed
employees through this challenging time, we have ensured every employee remains 
on their full base pay and, mindful of the importance of their mental wellbeing,
we are encouraging regular contact with their teams to ensure they are up to date,
feel connected and ready to return to work. We are also making resources available
to all employees to enable them to learn new skills and access online training. 

We have also started internal masterclasses, which give our employees the opportunity
to expand their knowledge sets in areas outside of their direct expertise and which
also include sessions focusing on best in class production topics, which have been
very popular.

Our significant investment in IT and flexible working over the last three years,
has meant that we have been able to switch our operations to remote working very
quickly and successfully and we continue to communicate and engage on a daily basis
with all of our employees. As we plan remobilisation, we believe that this is a 
significant competitive advantage.

As we manage the phased return to work, we are conscious that each of our employees
has different personal circumstances and we are committed to supporting them as 
effectively as possible. We will not be asking those who are vulnerable, shielding
the vulnerable or our apprentices to return to site at this stage. We will not ask
any employee or subcontractor to work in an environment where they do not feel safe.

Many of our employees have stepped forward to volunteer for the NHS and support 
local communities and charities. This includes our employees and partners coming
together to raise £66k for the NHS, Crisis and Childline through the Taylor Wimpey
Isolation Challenge. Our teams across the business have eagerly played their part
in supporting our key workers and communities. On closure, our site teams distributed
much needed PPE to local NHS and care homes.

We have also been running an in-house manufacturing project with employees which
is supplying GP surgeries and care homes with reusable 3D printed face visors. This
project has so far serviced 32 locations and we can currently add approximately 
four new care homes a day. From this, we have created a wider project to support
care homes, procuring and delivering basic PPE to c. 50 care homes across the country
with urgent PPE needs, including 75,000 masks, 75,000 aprons and 38,000 pairs of
gloves.

**Strong relationships with suppliers and subcontractors**

Our relationships with suppliers and subcontractors are very important to us and
their support and loyalty will be key to ensuring we start back on sites in the 
right and most sustainable way. We have remained in constant dialogue with subcontractors
and suppliers throughout this crisis and have committed to them that we will pay
them promptly, we will be open and clear with our communication and provide targeted
help and support to the most financially vulnerable. Our newly created £5 million
subcontractor scheme, “Pay it Forward”, was established to help up to 2,750 vulnerable
individuals working for our subcontractors and has received excellent feedback, 
making a real difference where it is most needed.

**Quality landbank**

We maintain an active dialogue with land vendors, however, due to the increased 
uncertainty, we took the decision last month to put discretionary land spend on 
hold.  We have now started to look for future land opportunities on a selective 
basis. At the end of March 2020, our short term landbank stood at c.78k plots (2019
equivalent period: c.79k plots). Our strategic land pipeline stood at c.137k potential
plots as at the end of March 2020 (2019 equivalent period: c.128k plots). During
the shutdown our land team secured the UK’s first significant remote planning permission
for a joint venture of around 750 homes with Waltham Forest Borough Council in East
London.

**Outlook**

Whilst at this stage it is too early to resume guidance, we are encouraged by the
resilience and confidence in our order book. We have continued to sell remotely 
during the shutdown period which demonstrates the strong underlying demand for our
homes.

We are a cautiously run business and have come into this crisis with a strong balance
sheet and net cash position.

Taylor Wimpey has continued to engage with our key stakeholders, including our employees,
suppliers and subcontractors and these strong relationships leave us well positioned
as we plan for the resumption of operations.