# SSE remains on course to deliver record investment in 2022/23SSE

- Link: https://www.directorstalkinterviews.com/sse-remains-on-course-to-deliver-record-investment-in-202223sse/4121098784
- Published: 2023-01-20T07:16:16+00:00
- Author: Amilia Stone

**[SSE plc](https://www.directorstalkinterviews.com/ftse-company/sse-plc/sse.l)**(
LON:SSE) has announced its Q3 trading statement.

·    **2022/23 adjusted earnings per share expectations updated to more than 150
pence.**

·    **Update reflects the strength of the Group’s diverse business mix, which continues
to create value, alongside the increased certainty from strong operational performance
and supportive market conditions.**

·    **SSE remains on course to deliver record investment in excess of £2.5bn this
year, backed by its strong balance sheet and credit ratings, with clear visibility
of further investment opportunities that support the transition to net zero.**

This Trading Statement updates SSE’s financial outlook, outlines operational performance
for the third quarter ending 31 December 2022 and highlights recent strategic progress
made in the delivery of the Group’s Net Zero Acceleration Programme.

**FINANCIAL OUTLOOK
SSE is updating its current expectations for full-year 2022/
23 adjusted earnings per share to more than 150 pence from the previous guidance
of at least 120 pence. This update reflects the strength and stability of its balanced
mix of regulated and market-facing businesses with continuing good availability 
and supportive market conditions leading to flexible generation plant and gas storage
optimisation significantly offsetting lower than planned renewables output and hedge
buy-back costs. It also reflects a narrower range of probable financial outcomes
with the decrease in risk from recent falls in forward power and gas prices and 
further clarity over the Electricity Generator Levy both reducing uncertainty in
the financial outlook as the year has progressed.

With market volatility expected to continue in the near term, uncertainties such
as plant availability, weather conditions, and the extent to which market conditions
lead to further optimisation of flexible generation plant, will determine the final
full-year outturn. SSE will provide an update on performance for the final months
of the year in its Notification of Closed Period statement.

In line with the Group’s five-year dividend plan, announced as part of its NZAP 
in November 2021, SSE intends to recommend a full-year dividend of 85.7p per share
plus RPI for 2022/23 followed by a rebase to 60p in 2023/24 to support the Group’s
significant investment and growth plans. The dividend is then expected to increase
by at least 5% per annum in 2024/25 and 2025/26.

SSE remains on course to deliver record investment in 2022/23, with capital expenditure(
including acquisitions) still expected to be in excess of £2.5bn. Investment opportunities
associated with net zero continue to accelerate, not least in SSE’s regulated networks
businesses. December’s Accelerated Strategic Transmission Investment (ASTI) framework
announcement clears the way for SSEN Transmission to build the assets required to
support 50GW of offshore wind by 2030 and work continues on agreeing a final settlement
for SSEN Distribution to implement its £3.6bn RIIO-ED2 business plan following Ofgem’s
recent final determination, which saw baseline allowances for SSEN Distribution 
increasing by £300m from draft determinations, representing a 21% increase in allowed
expenditure compared to an equivalent period in RIIO-ED1.

The Group’s balance sheet continues to strengthen and, following the completion 
of a minority stake sale of SSEN Transmission in November 2022, the net debt to 
EBITDA ratio is anticipated to be well below the target 4.5 times for this financial
year. At 18 January 2023, c.23% of available liquidity had been utilised on cash
collateral for forward commodity contracts.

> **Gregor Alexander, Finance Director, said:**
> _“Our fully funded £12.5bn Net Zero Acceleration Programme is progressing at pace
> as we build the renewables, networks and flexible energy assets needed for a cleaner,
> more secure energy system._
> _“SSE is performing well in a shifting and volatile energy landscape, underlining
> the strength of our balanced business mix and the quality of our assets, and we
> are well placed to deliver a strong financial performance for the full year._
> _“We are responding to the cost of living and energy crises by investing record
> amounts and remain committed to investing additional profit we make into critical
> low-carbon electricity infrastructure. By doing so, we are creating lasting value
> for SSE’s stakeholders, and society as a whole.”_

**Q3** **PERFORMANCE & OPERATIONAL UPDATE**

**SSE Renewables**  

Output of electricity from renewable sources in which SSE has an ownership interest
across the UK and Ireland was 0.76TWh, or around 10%, below plan in the nine months
to 31 December 2022 but 0.94TWh higher than the equivalent period last year. The
third quarter has continued to see periods of unseasonably calm and dry weather 
with delays to the Seagreen project also contributing to the shortfall against plan.

Construction on Seagreen continues, alongside Dogger Bank and Viking, with Seagreen
still expected to be completed in summer 2023 assuming normal weather and planned
vessel availability.

| ** ** | **Actual output for 9 months to 31 December 2022** | **% of planned output** | **Planned output for 9 months to 31 December 2022** | **Actual output for 9 months to 31 December 2021** | 
| Onshore wind generation output – GWh inc. constrained off output | 3,458 | 96% | 3,586 | 2,791 | 
| Offshore wind generation output – GWh inc. constrained off output | 1,328 | 78% | 1,692 | 1,099 | 
| Conventional hydro generation output – GWh | 2,074 | 88% | 2,345 | 2,030 | 
| **Total renewables output (excl. pumped storage) – GWh** | **6,860** | **90%** | **7,623** | **5,920** | 
| Pumped storage generation output – GWh | 205 | – | – | 156 | 
| **Total renewables output – GWh** | **7,065** | **–** | **–** | **6,076** |

1.    Output based on equity share and in the nine months to 31 December 2022 includes
341GWh of onshore and 97GWh of offshore compensated constrained off generation. 
The same period in 2021 included 268GWh of onshore, and 118GWh offshore, compensated
constrained off generation.

2.     Planned output is consistent with the 11.4TWh outlook for 2022/23 as stated
in May 2022, which included 0.9TWh of planned output from Seagreen during the period.

**SSE ThermalFlexible thermal generation continues to play a key part in the transition
to net zero, creating value by optimising output and forward trading to reflect 
market conditions and providing the fast response services required in an increasingly
intermittent renewables-led system. Strong availability across the existing fleet
during the last quarter, combined with market conditions, has meant output of electricity
from SSE’s gas-fired generation plant for the nine months to 31 December 2022 was
27% higher than the same period last year as SSE’s fleet helped ensure security 
of supply for customers.

Meanwhile, commissioning of Keadby 2 CCGT is due to recommence on 22 January with
the performance validation period continuing to be expected to complete on 11 February
2023.

| ** ** | **9 months to****31 December 2022** | **9 months to****31 December 2021** | 
| Gas-fired generation output (GB) – GWh | 13,232 | 8,670 | 
| Gas-fired generation output (ROI) – GWh | 1,018 | 2,517 | 
| **Total gas-fired generation output – GWh** | **14,250** | **11,187** |

1.    Output includes 311GWh of oil-fired generation in the nine months to 31 December
2022 and 642GWh of oil-fired generation in the same period in 2021, primarily older
Irish plant.

2.     In September 2021 SSE’s offtake agreement for 100% of output from its Seabank
CCGT JV expired, with output following that date only recognised to the extent of
its 50% equity share.

3.    Output in GB includes 1,012GWh of output from the Triton Power portfolio from
acquisition on 1 September 2022. The output primarily relates to the Saltend CCGT.

4.    Output in Ireland in the nine months to 31 December 2022 was impacted by unavailability
at Great Island CCGT, which returned to service in July 2022, and Tarbert oil-fired
plant.

5.     Output in GB excludes 649GWh of commissioning output in 2022 from Keadby 
2 CCGT, with the plant’s performance validation period expected to complete on 11
February 2023.

**NOTIFICATION OF CLOSED PERIOD**

SSE expects to issue a Notification of Closed Period statement on 30 March 2023 
ahead of publication of its Preliminary Full-year Results for 2022/23 on 24 May 
2023.

Share on: