# SSE Plc Q3 Trading Update: EPS Guidance Maintained

- Link: https://www.directorstalkinterviews.com/sse-plc-q3-trading-update-eps-guidance-maintained/4121238175
- Published: 2026-02-04T07:31:46+00:00
- Author: Amilia Stone

**[SSE plc](https://www.directorstalkinterviews.com/ftse-company/sse-plc/sse.l)**(
LON:SSE) has announced it Q3 Trading Statement

This Trading Statement updates on strategic progress and operational performance
for the nine-month period ending 31 December 2025 and provides guidance for 2025/
26 full-year earnings.

 * **Strong networks performance with a two-thirds increase in investment compared
   to this point last year.**
 * **Renewables output slightly higher, reflecting capacity additions against mixed
   weather conditions.**
 * **Momentum behind the £33bn Transformation for Growth plan with three quarters
   of key transmission consents received and the fifth major transmission project
   in construction.**
 * **2025/26 full-year adjusted Earnings Per Share expected to be between 144 – 
   152 pence.**

## Trading update

SSE expects that 2025/26 adjusted Earnings Per Share will be between 144 – 152 pence,
reflecting strong operational performance against mixed weather conditions. Previously
reported Business Unit operating profit expectations remain unchanged.

The regulated networks businesses have delivered a 64% increase in investment compared
to the first nine months of last year as strategic delivery accelerates. Around 
£1.8bn was invested^(1) in networks as construction gathers pace on the major ASTI
and LOTI projects in Transmission, while Distribution continues to progress investment
through its baseline plan and Uncertainty Mechanisms.

Generation output from SSE Renewables over the first nine months was 7% higher than
the same period in prior year, reflecting the ongoing increase in capacity from 
its construction programme against mixed weather conditions.

Guidance remains subject to factors such as weather, market conditions and plant
availability over the remainder of the year. An update on actual performance will
be provided in SSE’s Notification of Closed Period statement on 2 April 2026.

_^(1)_ _adjusted investment is net of SSEN Transmission 25% minority interest._

## Strategic progress

Momentum continues behind delivery of SSE’s five-year, £33bn Transformation for 
Growth investment plan, with a number of projects of critical national importance
reaching delivery, planning and policy milestones including:

 * Five transmission planning decisions have been secured since November. SSEN Transmission
   now has 25 of the 34, or three quarters of the major consents required to fulfil
   its licence condition to deliver the 11 major projects that reinforce the grid
   in the north of Scotland. Securing the remaining consents will be a focus for
   the business for the remainder of this calendar year.
 * Following receipt of its final consent, the Spittal-Peterhead link became SSEN
   Transmission’s fifth major project to fully enter construction. The project comprises
   a 203km 2GW subsea High Voltage Direct Current cable and two convertor stations.
   The cables for the project, and cabling for the planned Western Isles link, have
   been secured through the awarding of a €2bn contract, SSEN Transmission’s biggest
   ever, to NKT.
 * SSE welcomed improvements to baseline total expenditure within the RIIO-T3 Final
   Determination. The Group also noted updates to Ofgem’s proposed financial parameters
   and incentive regime, and it continues to assess the overall investability of
   the package ahead of the deadline for accepting the price control, on 3 March.
 * SSEN Transmission has signed a £1bn, 12-year Bank Facility backed by an £800m
   financial guarantee from the UK Government’s National Wealth Fund in addition
   to a £500m, 19-year Bank Facility guaranteed by the Swedish Export Credit Agency(
   EKN). These facilities provide an important source of longer-dated funding diversification
   as investment gathers pace.
 * Berwick Bank B offshore wind farm will now progress towards Final Investment 
   Decision after securing a 20-year contract for 1.4GW in last month’s CfD Allocation
   Round 7. This opens a valuable route to market for a world-class project at a
   competitive strike price for consumers of £89.49/MWh.
 * Turbine installation is nearing completion on Dogger Bank A, with the 95th and
   final turbine set to be installed in the next available weather window. Installation
   will then immediately commence on the second phase, Dogger Bank B. Commissioning
   work continues on Dogger Bank A and is expected to be complete later this calendar
   year.

> **Barry O’Regan, Chief Financial Officer, said:**
> _‘__Since announcing our £33bn investment programme to unlock the enormous growth
> opportunity presented by the transformation of electricity networks, our focus
> has been on accelerating investment and delivering the plan that will create compounding,
> long-term earnings and value for investors.’_
> _‘We are encouraged by recent steps from government and regulators – from positive
> signals on the upcoming transmission price control to the success of AR7 and updated
> ambitions for offshore wind – which highlight the value of SSE’s integrated business
> model and will ultimately help deliver a cleaner, secure and more affordable energy
> system.’_

## Operational performance

| **Regulated Networks Investment – £m** | **Q3 YtD FY26** | **Q3 YtD FY25** | 
| SSEN Transmission (net of Minority Interest) | 1,207 | 632 | 
| SSEN Distribution | 581 | 458 | 
| **SSE Networks adjusted investment** | **1,788** | **1,090** |

| **Generation Output –** **GWh** | **Q3 YtD FY26** | **Q3 YtD FY25** | 
| Onshore wind output | 4,514 | 4,154 | 
| Offshore wind output | 3,185 | 2,819 | 
| Hydro, pumped storage and battery gross output | 2,177 | 2,280 | 
| **Total renewable output** | **9,876** | **9,253** | 
| ** ** | ** ** | ** ** | 
| **Total flexible thermal output** | **10,605** | **12,488** |

Renewable output based on equity share and includes compensated constrained-off 
generation.

Thermal output is based on equity share except Marchwood where 100% of volumes are
included due to the contractual arrangement.