# Solo Oil Plc Update on Horse Hill, Weald Basin, UK

- Link: https://www.directorstalkinterviews.com/solo-oil-plc-update-horse-hill-weald-basin-uk/412742434
- Published: 2017-12-19T07:24:11+00:00
- Author: Giles Arbor

**Solo Oil plc** (LON:SOLO), the natural resources investment company focused on
acquiring and developing a diverse global non-operated portfolio of strategic oil
and gas assets, today notes that Horse Hill Development Limited (“HHDL”), the operator
of the Horse Hill oil discovery in the Weald Basin where Solo holds a 6.5% working
interest, has released an update on the plans for further development.

HHDL’s release, as set out by UK Oil and Gas Investments plc, is as follows:

**Highlights:**

· 150-day production flow-test and new drilling programme set to commence in late
winter 2017/18

· Programme aims to confirm commerciality of Portland and Kimmeridge oil discoveries
and gear-up for first permanent oil production targeted for early 2019.

· Drilling of HH-2 appraisal well as future producer to directly follow flow testing
programme

· Permanent production consent application underway, submission to SCC expected 
in spring 2018

· Swift and successful eviction of protesters completed at Horse Hill site on 02
December

**UK Oil & Gas Investments PLC** (LON:UKOG) announces that it has been advised by
Horse Hill Developments Ltd (“HHDL”), the operator of the Horse Hill-1 (“HH-1”) 
oil discovery, in which the Company holds a 32.435% interest, that key contracts
and the requisite funding commitments from all participants are in place to undertake
the production flow testing and drilling campaign approved by Surrey County Council(“
SCC”) in October 2017. The 2018 programme is planned to commence directly upon the
discharge of SCC’s pre-commencement planning conditions, expected by the end of 
winter 2017/18. Environment Agency approval for the full programme was granted in
September 2017.

**Horse Hill Oil Discovery**

The HH-1 Portland sandstone and Kimmeridge Limestone oil discoveries lie within 
onshore Weald Basin licences PEDL137 and PEDL246 covering an area of 55 square miles(
143 km2) north of Gatwick Airport. As previously reported on 21 March 2016, HH-1
flow tested at a significant commercial aggregate stable dry oil rate of 1,688 barrels
of oil per day (“bopd”) from the Portland, Kimmeridge Limestone 3 (“KL3”) and Kimmeridge
Limestone 4 (“KL4”) reservoir horizons.

**2018 Horse Hill Flow Test Programme**

Following a short period of civil works to upgrade site facilities, a 150-day production
testing programme focused upon the Portland, KL3 and KL4 reservoirs will commence.
As commercially viable initial flow rates were established by the 2016 flow tests,
the 2018 testing programme’s goal is to confirm that HH-1’s reservoirs are each 
connected to a commercially viable oil volume, thus enabling a declaration of commerciality
to be made.

The Portland, KL3 and KL4 flow tests, each planned for around 30-40 days duration,
will consist of a sequence of stabilised steady state flow and shut in periods to
establish the oil in place (“OIP”) directly connected to the well. A short maximum
flow-rate test will also be included for each reservoir. If time permits, a further
short-term test of a deeper untested Kimmeridge reservoir may be undertaken.

Testing will commence with the Portland reservoir, which in the Company’s opinion,
given the 323 bopd stable pumped rate achieved in 2016 and the 32 million barrels
most likely OIP calculated by Xodus in 2017, is a strong candidate for commercial
viability. Subject to a successful test, a Portland commercial declaration is expected
to be made by mid-2018. A Kimmeridge commerciality declaration would follow programme
completion and analysis of reservoir engineering data.

**2018 Horse Hill Drilling Programme**

Subject to a successful testing outcome in the Kimmeridge and Portland, the HH-2
well is planned as a future Portland producer, with an expected spud towards the
end of summer 2018. Drilling plans include optionality to deepen HH-2 into the Kimmeridge
to gather core and image log data, together with a possible northwards deviation
to access the adjacent oil bearing Collendean Farm fault block’s significant Portland
OIP.

The HH-1z Kimmeridge side-track spud is now planned for 2019 following construction
of a Kimmeridge reservoir model utilising HH-1 Kimmeridge production data, reservoir
data from the Company’s 100% owned Broadford Bridge-1 & 1z Kimmeridge discovery 
and any future HH-2 Kimmeridge core.

**Production Planning Application**

To achieve its goal of stable, long-term Horse Hill oil production by spring 2019,
HHDL now plans to submit a further production planning application to SCC in late
spring 2018. This application will seek consent to produce oil initially from HH-
1 & 1z, and HH-2, together with further production wells in a second contingent 
drilling phase.

**Horse Hill Eviction**

On Saturday 2 December 2017, a 42-person team, including High Court bailiffs and
the UK’s pre-eminent specialist protester removal contractor, successfully removed
around 20 activists who had illegally occupied part of the Horse Hill site since
Thursday 30 November 2017. These activists intimidated, jostled and verbally abused
HHDL’s security staff and caused criminal damage during their illegal occupation.

An increased security presence will now remain on the site until completion of the
2018 programme.

The Company is rigorously pursuing all available legal means to seek recourse for
this and any future events that prevent or obstruct its right to conduct its lawful
business.

Solo Oil Plc investing policy is to acquire a diverse global portfolio of direct
and indirect interests in exploration, development and production oil and gas assets,
with an on-shore focus in politically stable countries.