# Sirius Minerals Plc making good progress and in line with guidance

- Link: https://www.directorstalkinterviews.com/sirius-minerals-plc-making-good-progress-and-in-line-with-guidance/412786632
- Published: 2019-07-02T07:31:42+01:00
- Author: Giles Arbor

**Q2 progress update**

 * Comprehensive US$3.8 billion funding solution for stage 2 financing requirements
   launched on 30 April 2019 and on-track to complete before the end of September
   2019
 * Successful completion of US$425 million equity offering and US$400 million convertible
   bond offering
 * Long-term, take-or-pay supply agreement signed with IFFCO, one of the largest
   co-operative societies in the world, for volumes increasing to 1 Mtpa POLY4
 * Construction advancing well, and the Company remains on target to achieve first
   polyhalite and commercial production on time and in line with its cost schedule

**Sirius Minerals Plc** (LON: SXX) provides its latest quarterly progress update.

**Chris Fraser, Managing Director and CEO of Sirius Minerals plc, commented:**

> “The successful raising of US$825 million of funding during the quarter marked
> the completion of the first part of our stage 2 financing. We are making good 
> progress with the remaining components of our stage 2 financing package, which
> we expect to complete by the end of September this year in line with guidance,
> and which will enable us to bring our multi-nutrient POLY4 product to our customers
> to meet the expanding needs of the global agriculture industry.”

**Safety**

The Project’s Lost Time Injury Frequency Rate stands at 2.35. The LTIFR is a measure
of lost time incidents per million man-hours on a twelve-month rolling average basis.

**Stage 2 financing**

On 1 May 2019, the Company announced that it had successfully raised gross proceeds
of approximately US$825 million as part of the US$3.8 billion stage 2 financing 
package announced on 30 April 2019, expected to fund the Project to the point at
which it generates positive operating cash flows. The US$825 million was raised 
through a Firm Placing and Placing and Open Offer of ordinary shares for US$425 
million (£327 million) and through an offering of guaranteed convertible bonds due
2027 for new gross proceeds of US$400 million.

The Company placed US$106.6 million in aggregate principal amount of the New Convertible
Bonds with holders of the Company’s outstanding US$244 million of Guaranteed Convertible
Bonds due 2023 by way of a repurchase. No new proceeds were received by the Company
in connection with the repurchase.

The net proceeds of the New Convertible Bonds have been placed in an escrow account
and will be released to the Company upon the issuance of US$500 million senior secured
guaranteed bonds (or another acceptable US$500 million debt financing) and entry
into the proposed US$2.5 billion revolving credit facility with [JP Morgan](https://www.directorstalkinterviews.com/company/news/funds)
Chase Bank N.A., London Branch, expected to occur no later than the end of September
2019. The net proceeds received pursuant to the Firm Placing and Placing and Open
Offer provide the Company with sufficient cash to progress the Project in line with
key milestones to the end of September 2019.

The Company is making good progress on all workstreams connected with the proposed
US$500 million issuance of Initial Bonds and entry into the proposed US$2.5 billion
RCF, which will together complete the Company’s stage 2 financing.

**Construction progress**

The Company remains on track to achieve first polyhalite in 2021 and in line with
its cost schedule. Construction continues to progress in line with key milestones
at each of its construction sites.

**Service and production shafts**

Service shaft works are on target to complete the construction of the foreshafts
by year end to enable commencement of excavation of the main shaft using the shaft
boring roadheader. The Company’s first SBR recently passed its Factory Acceptance
Test and is due to commence arrival at the Woodsmith Mine site in August 2019. The
SBR will then be erected on-site. Assembly of the SBR and installation into the 
foreshaft is scheduled to be completed in December 2019.

The excavation of the 35-metre diameter service shaft foreshaft to 45 metres was
completed in the first quarter of 2019, enabling commencement of the excavation 
of the inner-main shaft, which will be excavated to a total depth of approximately
120 metres. The main shaft has now been excavated to approximately 85 metres below
ground level, using conventional excavation techniques.

The service shaft temporary winder building foundations have been completed. Erection
of the temporary and permanent winder buildings, which will house the service shaft
hoists, and installation of the temporary and permanent winders is in progress and
on schedule.

Production shaft works are on target to complete the construction of the foreshaft
and excavation of the main shaft to 120 metres by year end. The 32-metre diameter
production shaft foreshaft, which will be excavated to a depth of 45 metres from
surface, has been excavated to approximately 9 metres below ground level at quarter
end.

The production shaft differs from the service shaft in that it already has diaphragm
walls installed to a depth of 120 metres in the inner-main shaft. Once the larger
diameter foreshaft has been excavated to a depth of 45 metres and the floor installed,
the inner-main shafts will be excavated to a depth of 120 metres using conventional
methods inside the existing diaphragm walls. This is expected to be completed in
December 2019. The SBR for the production shaft is due to commence arriving on-site
in October 2019. The SBR for the production shaft is currently erected in Germany
and will be undertaking various cutting optimisation tests prior to being dismantled
and shipped to the Woodsmith Mine.

The application of considerable learnings from the service shaft excavation has 
meant that the production shaft excavations are progressing at a faster-than-expected
rate and excavation is on track to meet 2019 targets.

Construction of the production shaft permanent winder building foundations is underway
and is progressing ahead of schedule.

**Mineral Transport System**

**MTS Drive 1 – Wilton to Lockwood Beck**

The tunnel boring machine being used to construct Drive 1 of the mineral transport
system completed its advance to the bottom of the MTS launch portal during the quarter
and has successfully commenced mechanical tunnelling. At quarter end, the TBM has
advanced approximately 210 metres into the MTS tunnel, which is ahead of schedule.
The TBM is progressing on target to advance the MTS tunnel excavation to 3km by 
year end.

**MTS Drive 2 – Lockwood Beck towards Woodsmith Mine**

The Lockwood Beck MTS shaft pre-sink is well underway and had reached a depth of
approximately 37 metres below ground level at quarter end. The pre-sink will continue
to approximately 47 metres to enable installation of the Galloway (the multi-level
working platform that will be suspended near the shaft bottom during sinking and
raised and lowered as required to allow conventional drill and blast sinking to 
continue to the final depth of the shaft). Drill and blast operations are expected
to commence during the year.

The Lockwood Beck shaft is scheduled to reach its target depth of 360 metres in 
the first quarter of 2020. Once complete, shaft bottom works will be undertaken 
prior to the shaft being handed over from DMC to STRABAG to begin construction of
the launch cavern for the Drive 2 TBM at the 360-metre level.

**MTS Drive 3 – Woodsmith Mine towards Lockwood Beck**

The first approximately 115 metres of the MTS shaft excavation has been completed
during the quarter using a Herrenknecht vertical sinking machine. The VSM has been
removed from the shaft and preparation for the installation of the drill and blast
Galloway is underway.

Civil works for the MTS winder building is complete and building erection is about
to commence. The drill and blast Galloway is on site and under construction and 
delivery of steelwork has commenced.

**Materials Handling Facility**

Granulation trials for the materials handling facility test plant, including yield
and efficiency optimisation, have been successfully completed during the quarter
at the Company’s R&D facility in Teesside. The test plant has now been decommissioned
in preparation for conversion to a full R&D demonstration plant to be commissioned
during the year.

**Port Handling Facility**

Procurement of the overland conveyor that will transport our POLY4 product from 
the MHF to the port, was completed during the quarter. The cost of the contract 
is in line with the Company’s existing cost estimates. Site clearance continues 
at the Redcar Bulk Terminal site and good progress is being made.

**Sales and marketing**

During the quarter the Company signed a take-or-pay supply agreement with Indian
Farmers Fertilisers Cooperative Limited for the supply of POLY4 in India. Volumes
under the agreement will increase to one million tonnes per annum in year eight,
with an option to increase this to 1.25 Mtpa. The IFFCO agreement takes the Company’s
total peak aggregate volumes under contract to 11.7 Mtpa.

IFFCO is one of the largest co-operative societies in the world with access to over
55 million Indian farmers. The agreement provides access to one of the top three
fertilizer markets in the world with a total nutrient consumption of approximately
30 Mtpa.

During the quarter the Company initiated 29 new agronomy trials with a total of 
48 trials initiated in 2019 to date. The total number of trials established by the
Company now stands at 430 on 48 crops in 30 different countries. The Company has
continued to establish a significant number of on-farm demonstrations with a number
of its offtake partners’ key and sizeable customers. The programme of on-farm demonstrations
is expected to show to future end-users of POLY4 the benefits of incorporating POLY4
into their fertilizer programmes.

**Investor webcast**

Sirius Mineral’s Chief Executive Officer, Chris Fraser will host a webcast for investors
and analysts at 9.30am today.

The webcast can be listened to live by clicking on the link below. A replay will
be available on the Company’s website in due course.