# Rio Tinto Update on Tropical Cyclone Veronica

- Link: https://www.directorstalkinterviews.com/rio-tinto-update-on-tropical-cyclone-veronica/412770944
- Published: 2019-04-01T07:45:03+01:00
- Author: Charlotte Edwards

**Rio Tinto** ([LON:RIO](https://www.directorstalkinterviews.com/ftse-company/rio-tinto-plc/rio.l)),
iron ore operations in the Pilbara, Western Australia, are progressively resuming
following the passing of Tropical Cyclone Veronica. However, initial inspections
uncovered some damage to the Cape Lambert A port facility. As a result, Rio Tinto
has declared force majeure on certain contracts and is working with its customers
to minimise any disruption in supply.

The impact of the disruption to production caused by the cyclone and repairing the
damage sustained at the port facilities, combined with the damage caused by the 
fire at Cape Lambert A in January, will result in a loss of approximately 14 million
tonnes of production in 2019. As a result Rio Tinto’s Pilbara shipments in 2019 
are expected to be at the lower end of the 338 and 350 million tonnes (100 per cent
basis) guidance provided.

Safety remains our top priority as we ramp up operations, and undertake the necessary
remediation work, following the passing of the cyclone.