# Rio Tinto PLC Update on Oyu Tolgoi underground project

- Link: https://www.directorstalkinterviews.com/rio-tinto-plc-update-on-oyu-tolgoi-underground-project/412787889
- Published: 2019-07-16T07:20:27+01:00
- Author: Amilia Stone

**[Rio Tinto plc](https://www.directorstalkinterviews.com/ftse-company/rio-tinto-plc/rio.l)**(
[LON:RIO](https://www.directorstalkinterviews.com/ftse-company/rio-tinto-plc/rio.l))
has today provided an update on the schedule and cost of the Oyu Tolgoi underground
project in Mongolia.

The Project continued to progress in 2019 towards its path to become one of the 
largest copper mines in the world.

Since February, key below ground infrastructure such as the control room facility
and the jaw crusher system are now complete and construction of shafts 3 and 4 is
progressing well. The commissioning of shaft 2 remains on track for October 2019.

As previously advised, enhanced geotechnical information and data modelling suggests
that there may be some stability risks identified with the approved mine design 
and so a number of other mine design options are also under consideration to complete
the Project. Studies to date indicate that these options may result in some of the
critical underground infrastructure, such as the mid-access drive and the ore handling
system, being relocated or removed. Options relating to the sequence of crossing
the panel boundaries during mining operations are also being analysed. 

These options are being evaluated to determine the final design of the first panel
of mining, “Panel 0”, and this work is anticipated to continue until early 2020.
Given the further technical work which is needed, the Definitive Estimate, which
will include the final estimate of cost and schedule for the remaining underground
project, is now expected to be delivered in the second half of 2020, reflecting 
the preferred mine design approach.

All options under consideration present a pathway to sustainable first production,
and have different cost and schedule implications. To date, these have been defined
to a level of accuracy associated with a Conceptual Study or Order of Magnitude 
Study, and, therefore, significantly more work is required to complete the final
assessment.

Preliminary information now suggests that, depending on which mine design options
are adopted, first sustainable production could be achieved between May 2022 and
June 2023, a delay of 16 to 30 months compared to the original feasibility study
guidance in 2016. This range includes contingency of up to eight months reflecting
the unexpected and challenging geotechnical issues, complexities in the construction
of shaft 2 and the detailed work still required to reach a more precise estimate.

Preliminary estimates for development capital spend for the Project, depending on
the outcome of the work described above, is now $6.5 billion to $7.2 billion, an
increase of $1.2 billion to $1.9 billion from the $5.3 billion previously disclosed
^([1]).

These preliminary ranges incorporate a range of productivity assumptions and remain
subject to change prior to completion of the Definitive Estimate.

The company will continue to focus on minimising the impact to project schedule 
and cost, as it works through the detailed analysis and testing of each mine design
option. Although further work is necessary to reach definitive conclusions, Rio 
Tinto is reviewing the carrying value of its investment in the Project and will 
announce if any changes are required, in the half year results on 1 August 2019.

> **Stephen McIntosh, Group executive, Growth & Innovation said** “We have made 
> significant progress on a number of key elements in the construction of the underground
> project during 2019. However, the ground conditions are more challenging than 
> expected and we are having to review our mine plan and consider a number of options.
> Delays are not unusual for such a large and complex project but we are very focused
> as a team on finding the right pathway to deliver this high value project.”

> **Arnaud Soirat, chief executive, Copper & Diamonds said **“Oyu Tolgoi is a world-
> class ore body and a world-class business that is already producing copper, employing
> around 16,000 people and benefitting Mongolia through taxes, royalties and significant
> procurement. We are working with TRQ and the Government of Mongolia to complete
> the underground, which will unlock the most valuable part of the mine for the 
> benefit of all stakeholders.”