# Rainbow Rare Earths Ltd To rapidly increase scale of mining operations

- Link: https://www.directorstalkinterviews.com/rainbow-rare-earths-ltd-to-rapidly-increase-scale-of-mining-operations/412766016
- Published: 2019-01-31T07:21:09+00:00
- Author: Giles Arbor

**Rainbow Rare Earths Ltd** (LON: RBW), the rare earth element mining company, has
today announced an operations update from its Gakara Project in Burundi for the 
three months to 31 December 2018.

**Results for Q2 2018-19 (Three Months to 31 December 2018)**

 

  |

 |

Q2 2018-19

(31 Dec 2018)

  |

Q1 2018-19

(30 Sep 2018)

  |

FY 2017-18

(30 June 2018)

  |  
 |

Concentrate sold (tonnes)

  |

300

  |

350

  |

475

  |  
 |

Concentrate exported (tonnes)

  |

275

  |

275^(1)

  |

575

  |  
 |

Grade TREO per tonne concentrate

  |

56%

  |

59%

  |

58%

  |  
 |

 |

 |

 |

 |  
 |

 |

US$/t

  |

US$/t

  |

US$/t

  |  
 |

Gross sales price

  |

1,884

  |

2,147

  |

2,263

  |  
 |

Marketing and handling

  |

(94)

  |

(167)

  |

(175)

  |  
 |

Net sales price

  |

1,791

  |

1,980

  |

2,088

  |  
 |

Transportation and royalty

  |

(387)

  |

(261)

  |

(381)

  |  
 |

Production cost

  |

(2,827)

  |

(2,852)

  |

(2,430)

  |  
 |

 |

 |

 |

 |  
 |

LTIFR

  |

0.00

  |

0.00

  |

0.00

  |

1 Q1 exports previously reported at 350t, however have been restated as 275t to 
reflect a more consistent recognition of sales timing going forward

> **Martin Eales, CEO of Rainbow Rare Earths, said: **
> “Production in the quarter was broadly flat compared to the prior period, however
> we have now put in place a plan to rapidly increase our scale of mining operations
> by opening two further areas before the end of 2019 which is expected to transform
> our overall production profile and financial performance to take us to breakeven
> and beyond.
> “We have learned a huge amount about our mining operation from the first full 
> year of production and, given the natural fluctuations within the veins in each
> mining area, it makes sense to further de-risk our project and improve production
> consistency by adding additional mining faces. This will put us in a strong position
> to take advantage of the extremely strong current demand for our mineral concentrate,
> allowing us to capitalise on our status as one of only two listed commercial REE
> producers outside of China. I look forward to providing further updates on our
> expansion plans over the coming months as we progress towards profitability.”

**Production update for quarter to 31 December 2018**

Production for the three months to 31 December 2018 from the Gakara mine measured
in terms of exported concentrate remained in line with the (adjusted) previous quarter
at 275 tonnes. 300 tonnes of concentrate were sold in the quarter (Q1 2018-19: 350
tonnes), while average grade decreased slightly from 59% to 56% TREO.

The Company’s partnership with thyssenkrupp Materials Trading (‘TK’) for the sale
of concentrate is working extremely well and the demand for Rainbow’s concentrate
product is significantly higher than the current production.

**Sales price and Production costs**

Gross sales price per tonne achieved in the quarter was approximately 9% below Q1
2018-19 at US$1,884/t compared to US$2,147/t, with the difference principally caused
by the effects of a decrease in market prices for rare earths in the period (the
Company’s indicative basket price decreased from US$11.91/kg to US$11.33/kg during
the quarter) as well as a reduction in average TREO grade from 59% to 56%.

TK’s marketing and handling costs fell to US$94/t from US$168/t in the previous 
quarter as a result of some lower handling costs at the destination port.

Transportation costs from the mine site to the port of Mombasa increased from US
$261/t in Q1 to US$387/t, which included some standing charges as a result of the
temporary exportation embargo imposed by the Government of Burundi on all mineral
companies during October, as well as some true-up costs from previous quarter which
proved higher than initial estimates

Production costs of US$2,827/t were slightly lower than Q1 costs (US$2,851/t), but
remain significantly higher than expected due to modest levels of ore produced in
the quarter from Gasagwe and Murambi (see below) and high costs for rented mining
equipment (which the Company is now proposing to purchase outright, subject to financing).

**Mining at Gasagwe and Murambi**

Final permitting for Murambi, the Company’s newest mining area, was received in 
early December, which was later than planned and therefore delayed the creation 
of a haul road and waste dump until the New Year resulting in an impact on the rate
of extraction from the site. The current quarter is expected to provide significantly
more ore tonnes from this area as Murambi reaches full scale operation. In addition,
the concentrate yield from Murambi ore has improved as more tonnes have been processed
and suggests that this deposit will approach similar yield levels to Gasagwe.

As explained in the previous quarter, production from the Gasagwe pit has delivered
at lower rates than had been initially anticipated due to variations in vein structure
and consequently the Company has adjusted its production planning to incorporate
recent experience and better reflect the likely output of each mining area on an
average quarterly basis.

**Production Expansion**

Whilst the Company has achieved notable successes so far in developing the Gakara
Project and demonstrating that it can consistently produce and sell rare earth concentrate,
the revised production expectations for Gasagwe and Murambi demonstrate that the
Company needs to be operating additional mining areas in order to de-risk the fluctuations
and uncertainty caused by operating at a limited scale and to deliver profitability.
The Company is swiftly moving to develop mining operations at the Kiyenzi and Gomvyi
Centre areas, as previously announced, and expects both areas to be in operation
in the latter half of calendar 2019 with a further new mining area planned to be
in operation in early 2020, to replace Gasagwe which, as originally planned, is 
expected to reach the end of its life in late 2019.

Cash flow breakeven on a monthly basis is therefore anticipated in the second half
of calendar 2019 as production from the planned new sites commences.

**Financing**

The funding agreement with Lind Partners of up to US$7.75 million as announced on
28 January 2019 provides Rainbow with confidence over a base level of funding over
the next two years but also maximum flexibility during the forthcoming period of
increased development where mining production may vary from month to month before
it is anticipated to reach a more stable and cash generative level.

In addition, Rainbow is working with its bankers and suppliers of new fleet and 
equipment to take advantage of credit facilities in the most efficient manner.

**Exploration and maiden JORC Resource**

On 17 December 2018, Rainbow announced its maiden JORC Resource of over 1.2 million
tonnes covering just a small fraction of the Gakara Project. Three areas (Gasagwe,
Murambi South and Gomvyi Centre) are very high grade vein stockwork deposits totalling
12,491 tonnes of Total Mineral Resource at an average TREO grade of 55% representing
at least two years’ planned plant feedstock. Additionally, Kiyenzi was found to 
have nearly 1.2 million tonnes of Mineral Resource at an average grade of 2.2% TREO
using a 1% cut off.

These extremely positive maiden results demonstrate the huge potential of the Gakara
Project, whether through a continuation of the low volume/high grade production 
or through eventual large scale development of lower grade material.

**Outlook**

From a standing start, Rainbow has learned a great deal about mining its high grade
vein stockwork deposits during its first full year of production in calendar 2018.
Initial targets proved to be challenging due to variability in vein deposition at
differing depths. The opening of multiple mining areas during 2019 will serve to
mitigate some of the normal production fluctuations from each site.

The Company anticipates that both Kiyenzi and Gomvyi Centre will start contributing
ore tonnes in the second half of calendar 2019 (H1 19-20 financial year) and take
the Company to at least breakeven production. Concentrate production for the next
six months is dependent on tonnages from the existing pits, Gasagwe and Murambi.