**Rainbow Rare Earths Ltd** (LON:RBW), the Rare Earth Element mining company, has
today announced an update from its maiden drilling campaign at its Gakara Project
in Burundi. Gakara is one of the highest grade rare earth element mining projects
globally, with an estimated in situ vein grade of 47-67% Total Rare Earth Oxide (‘
TREO’), and the Company is targeting to ramp up production to an annualised rate
of 5,000 tonnes per year (approximately 400 tonnes per month) by the end of calendar
year 2018.

**Highlights**

· Laboratory results from the Kiyenzi drill cores have confirmed initial field analysis
of the presence of multiple intersections of high grade REE

· Test highlights include 6.5m @ 7.1% TREO (including 44cm @ 35.3% TREO) and 1m @
27.8% TREO (including 50cm at 30.34% TREO)

· Mineralisation at Kiyenzi is contained within a breccia pipe structure, in which
REE minerals are interspersed with non REE-containing rocks. This implies lower 
average grades per tonne, but much wider mineralised zones and therefore greater
tonnages, and simpler, faster mining

· As previously announced, Rainbow will now proceed with the Phase 2 exploration
campaign with an aim of delivering a code-compliant resource by the end of 2018

> **Martin Eales, CEO of Rainbow, said:** “We were anticipating some exciting mineralisation
> at Kiyenzi following our original field testing, and these laboratory results 
> now confirm it. The thickness of the breccia deposit is likely to add many more
> tonnes to our code-compliant resource, targeted for this year, and should also
> be better suited to mechanised mining.
> “Phase 2 drilling starts within the next month at Kiyenzi and we look forward 
> to incorporating these results, as well as other areas within the Gakara project,
> into our targeted maiden resource later this year with a view of further ramping
> up our production of REE concentrate in the near-term to achieve our 6,000tpa 
> run rate target by the end of 2019.”

**Phase 1 Drilling Campaign**

Rainbow’s Phase 1 drilling campaign commenced in the first quarter of this year 
and targeted a) the current production site at Gasagwe, b) the Kiyenzi prospect,
where a high-priority gravity anomaly had been found, and c) a number of anomalies
revealed by the airborne magnetic survey flown in Q4 2017. On 30 April 2018 Rainbow
announced details of drilling at the Gasagwe mining site and the Kiyenzi target,
as well as outlining plans for the completion of Phase 1 drilling and the laboratory
testing of over 90 Kiyenzi drill core samples.

**Kiyenzi laboratory results**

As previously announced, five drill holes at Kiyenzi encountered REE mineralisation
over multiple intersections. Mineralisation was initially visually identified as
bastnaesite/monazite (the rare earth carrying minerals) and tested in the field 
with a hand held Niton XRF which indicated REE mineralisation. Over 90 core samples
have now been laboratory tested to confirm the precise nature of these intersections
and the results are extremely encouraging with selected results shown below.

  |

**Hole ID**

  |

**From (m)**

  |

**To (m)**

  |

**Width (m)\***

  |   |

**Grade – TREO%**

 

  |  
 |

GAK_DD_10

  |

7.00

  |

7.72

  |

0.72

  |   |

7.72% including 17cm at 10.98%

  |  
 |

GAK_DD_10

  |

19.00

  |

19.12

  |

0.12

  |   |

15.23%

  |  
 |

GAK_DD_11

  |

26.50

  |

33.00

  |

6.50

  |   |

7.10% including 44cm at 35.32%

  |  
 |

GAK_DD_12

  |

1.97

  |

2.20

  |

0.23

  |   |

18.25%

  |  
 |

GAK_DD_12

  |

10.40

  |

10.80

  |

0.40

  |   |

2.84%

  |  
 |

GAK_DD_12

  |

12.05

  |

12.09

  |

0.04

  |   |

5.36%

  |  
 |

GAK_DD_13

  |

2.61

  |

3.59

  |

0.98

  |   |

2.79%

  |  
 |

GAK_DD_13

  |

23.75

  |

24.75

  |

1.00

  |   |

27.81% including 50cm at 30.34%

  |

 

(All holes were drilled with a 50° dip)

Unlike the cleaner veins currently being mined at Gasagwe (typically averaging 3cm
to 15cm), the intersections revealed in the Kiyenzi drill core are ‘breccias’ that
vary in thickness and are much more heterogeneous. As anticipated in the 30 April
2018 announcement, the intersections contain lower global grades on a TREO basis
per tonne of in situ rock than a cleaner narrow vein; however, it is likely that,
considering the apparent sizeable widths of the intersections, this material will
be more amenable to mechanised extraction at greater volumes than Gasagwe and other
similar narrow vein areas within the Gakara Project.

**Completion of Phase 1**

Rainbow Rare Earths Ltd completed the Phase 1 campaign by drilling the remaining
airborne magnetic anomalies that were identified in Q4 2017. Holes were drilled 
up to 150m on the five selected targets but no further evidence of REE mineralisation
was discovered in these holes which may suggest an alternative location for the 
carbonatite source of the high grade REE veins or that it is at a depth not encountered
by the drill holes.

Some highly magnetic units were intersected at various depths in the holes which
are likely to have contributed to the magnetic anomalies suggested by the airborne
survey.

**Commencement of Phase 2 campaign**

As confirmed in April 2018, Rainbow intends to start Phase 2 of the exploration 
campaign in July 2018, which will comprise approximately 750 metres of further core
drilling at Kiyenzi. Should the mineralisation discovered to date prove sufficiently
consistent, Rainbow intends to model and report a code-compliant resource by the
end of 2018 which will additionally include further resource tonnes at Gasagwe and
the next planned mining area. The Phase 2 drilling campaign will be complemented
by further trenching and terracing at Kiyenzi, particularly of the shallow intersections,
together with mineralogical and metallurgical testing of the breccia material.