# Pensana Technical Due Diligence Report on Longonjo reported by TMC

- Link: https://www.directorstalkinterviews.com/pensana-technical-due-diligence-report-on-longonjo-reported-by-tmc/4121139447
- Published: 2024-01-24T08:31:11+00:00
- Author: Amilia Stone

**Pensana plc** ([LON:PRE](https://www.directorstalkinterviews.com/company/pensana-rare-earths-plc/pre.l))
has advised that the technical due diligence report on the Longonjo rare earth project
in Angola has been reported by The Mineral Corporation (TMC) to ABSA Capital (ABSA)
as the Mandated Lead Arranger for potential debt funding of the Project.

**A summary of TMC’s key findings:**

The Project is located approximately 320km east of the Port of Lobito and envisages
the open pit mining and processing of near surface Rare Earth Elements (REE) bearing
carbonatite ores to produce a mixed REE carbonate (MREC) concentrate which will 
then be marketed commercially.

The holder of the Mineral and Mining Rights over the Longonjo mining licence area
is the Angolan registered company Ozango Minerais S.A. (Ozango), which is 84% owned
by Portugal domiciled subsidiaries of Pensana. The balance of Ozango is held by 
the Angolan Sovereign Wealth Fund and two Angolan partners.

Longonjo will comprise an open pit mine to recover near surface REE, which will 
then be processed via concentration and downstream refining to produce a commercially
saleable Mixed Rare Earth Carbonate (MREC) concentrate for export via the Port of
Lobito to third-party offtakers for the purpose of ultimately producing Neodymium/
Praseodymium (NdPr) feed into the renewable energy and electric vehicle markets.

A nominal plant feed of 0.8Mtpa has been specified at a TREO feed grade of 4.12%
and an NdPrO feed grade of 0.9%. The stockpiling and blending strategy critical 
to achieving stable and consistent concentrator performance and product has been
identified and included in the mining and processing flowsheets. The plant design
is nominally based on a dry concentrate feed of approximately 59ktpa, to produce
a nominal MREC dry product of 19.6ktpa (15ktpa normal operating conditions).

Whilst TMC is of the opinion that ramp-up to achieve design recoveries will be challenging,
and the ongoing operational control of the processing plants will be critical to
maintaining product quality and recovery, TMC notes no fatal flaws in terms of the
revised bankable feasibility study (BFS) review and no material technical divergences
from the level of study required for bank funding approval.

TMC noted the capital estimate provided is extremely detailed and based on bills
of quantities and tendered prices with a capital base date of Q4 2023. An accuracy
assessment was also carried out, which confirms the level of accuracy complies with
that required by a BFS standard. TMC is of the opinion that sustaining capital may
be slightly understated however this does not present a material risk to the Project.

**Capital Cost Breakdown**

| Concentrator Plant | US$37 766 993 | 
| Plant Common Areas | US$14 687 930 | 
| TSF | US$7 157 201 | 
| Recovery Plant | US$75 472 541 | 
| Plant Infrastructure | US$15 568 988 | 
| Project Infrastructure | US$123 386 | 
| Mine Infrastructure | US$9 707 348 | 
| Environmental | US$4 538 590 | 
| Security | US$1 767 680 | 
| Site Infrastructure | US$7 001 150 | 
| Indirect Costs | US$22 640 254 | 
| Contingency | US$20 100 933 | 
| Total Project Capital Expenditure | US$216 532 994 |

The capital estimate was derived from the various currencies relating to the goods
and services costs in the country of origin and adjusted for the relevant exchange
rates: US$ South African Rand ZAR 18.5, European Euro EUR 0.9, Australian Dollar
AUD 1.5 and Angolan Kwanza AOA 830.

TMC notes the level of detail provided in the detailed capital estimate consisting
of in excess of 18,000 line items, the methodology undertaken to produce the capital
estimate and the basis of estimate being predominantly based on bills of quantity,
tendered rates and budget quotations.

Operating Cost Estimates have been updated based on the revised Project scope and
also brought to a consistent cost base date of Q4 2023. TMC has reviewed all of 
the operating cost centre data and concurs that the operating cost estimates as 
provided meet the accuracy levels associated with a BFS, however it is noted that
the retender for the mining contract scheduled for late 2024 will impact on overall
Project economics and in all likelihood trigger the requirement for a revision of
the mining optimisation plan.

TMC notes that the financial model as received is detailed in all modelled inputs
and results in free cash flow levels which would be likely to support a funding 
decision. TMC reiterates the sensitivity of the Project economics to the forecast
rare earth oxide prices and recommends that the imminent offtake agreements and 
pricing structures should be included in any funding agreement as Conditions Precedent.
Once these are available the Project financial model should be updated, and the 
economics revised. The Project economics are most sensitive to projected market 
dynamics and the resulting product pricing projections, which in turn present the
most material risk to Project economics.

Earthworks and civils contractors established site in November 2022. Servitude bush
clearing and pylon installations to the borehole pumps, contractors camp, main camp
and water treatment plant were in progress at the time of the site visit at the 
end of February 2023. Overall, the level of detail design of the infrastructure 
is commensurate with the requirements of the BFS and TMC is of the opinion that 
the infrastructure design is appropriate and fit for purpose to support the mining
and processing operations.

TMC is of the opinion that the level of work undertaken for the project schedule
and plan of execution is commensurate with the requirements of a BFS and the work
undertaken is comprehensive and will be the basis for a potential successful project
execution.

Extensive work has been undertaken in the areas of social and community engagement.
TMC supports the programmes and costs which have been allocated to the various social
initiatives, however notes that the Relocation Action Plan still requires careful
monitoring and management to ensure successful implementation, minimising community
grievances. Ozango’s engagements and initiatives now comply with the expectations
associated with a BFS level of study and in some instances exceed expected levels.

TMC notes that all legislative aspects of Human Resources management have been addressed
adequately, however it does recommend that remuneration levels are reviewed prior
to the commencement of recruitment, as the budgeted levels may mitigate against 
the procurement of top level individuals, particularly in the senior technical expatriate
roles. The BFS meets expected levels of detail in terms of all HR, operational readiness
and occupational health and safety aspects. It is noted that specific operational
readiness planning is only expected at the next stage of the Project.

> **_Tim George Pensana CEO commented:_**_ “We are very grateful to Russel Heins
> and the team at The Mineral Corporation team for the diligent and extremely thorough
> review of all aspects of the Longonjo project undertaken in their role as lead
> Technical Advisor to ABSA as the Mandated Lead Arranger and we are pleased with
> the positive recommendations._
> _The review was based on the re-engineered, reduced capital cost of the project
> for financing purposes following our review in__Q2__of 2023. A huge amount of 
> work has gone into the capital cost estimate which as noted by Russell and the
> team is based on very detailed estimates and we are pleased that despite the current
> inflationary and cost pressures the estimate has been confirmed around US$217 
> million, which includes US$20 million in contingency._
> _As previously announced, once the Longonjo operations are operational and fully
> commissioned it is our intention to expand production to around 40,000 tonnes 
> of MREC per annum which will require an additional capital cost of around US$100
> million which is expected to be incurred around year three of the initial operations._
> _Whilst this technical review has been underway, we have been working closely 
> with our financiers ABSA, FSDEA and others and we expect to be in a position to
> announce the financing arrangements shortly.”_