# Pensana early stage development commenced at the Saltend Chemicals Park

- Link: https://www.directorstalkinterviews.com/pensana-early-stage-development-commenced-at-the-saltend-chemicals-park/4121007197
- Published: 2021-07-05T07:06:09+01:00
- Author: Giles

**Pensana Plc** ([LON:PRE](https://www.directorstalkinterviews.com/company/pensana-rare-earths-plc/pre.l))
has announced that following the recent £15 million premium equity raise which was
strongly supported by the Company’s major shareholders, early stage development 
has commenced on the establishment of its rare earth processing hub at the Saltend
Chemicals Park in Humber, UK.

The Saltend plant would be the first major rare earth separation facility to be 
constructed in over a decade and the first to be located in a Freeport. The final
tax and customs regimes for the Humber Freeport (one of Europe’s busiest ports) 
are being finalised but are expected to take the form of an economic enterprise 
zone providing a combination of benefits, enabling the rapid development of the 
project and frictionless trade with European and international customers.

Pensana is aiming to establish Saltend as an attractive alternative to mining houses
who may otherwise be limited to selling their products to China, having designed
the facility to be easily adapted to cater for a range of rare earth feedstocks.

Importantly, for many miners around the world who are looking to access the European
and US supply chains, it is becoming increasingly clear that the planned EU and 
UK carbon border taxation will mean that it is no longer acceptable for manufacturers
to source material extracted or processed unsustainably.

**Site development under way at Saltend and Longonjo**

The Company is advancing the front end engineering designs (FEED) for the Saltend
and Longonjo projects towards conclusion in October. Ongoing continuous process 
pilot plant runs to confirm equipment selection, sizing and specifications will 
continue through to September reflecting the importance placed on confirmation of
scalability of design.

Pensana is working with Wood, the international engineering group. Wood has committed
forty experts from its Western Australian, UK and South African operations to work
on FEED for both projects.

The Saltend site is currently being prepared for construction by the pxGroup and
is scheduled to be handed over in the next few months.

Saltend project workstreams underway in conjunction with the pxGroup include:

 * Design of external bulk supplies including power, water, steam, fuel and reagents.
 * Preparation of works packages for demolition and removal of the redundant tank
   farm.
 * Arrangements with Associated British Ports (ABP) for direct port access to the
   Saltend site.
 * Redesign and relocation of fire-fighting facilities to accommodate the refinery.
 * Topographic and geotechnical surveys for FEED.
 * Submissions in respect of the operating/environmental permit following the Saltend
   planning approval.

In Angola, Pensana is working closely with contractors and government officials 
to progress the Longonjo project while strictly adhering to travel restrictions 
arising from the global pandemic. Project workstreams underway include:

 * Ongoing involvement of vendors in the preparations for procurement of long lead
   items including key kiln, acid plant and comminution equipment.
 * Procurement activities towards establishment of the construction camp.
 * Mining area bypass road as agreed by the Huambo province.
 * Arrangements with relevant authorities for the connection of high tension electrical
   power line to the mine.
 * Optimisation of the freight handling at the Port of Lobito and on the Benguela
   Railway for reagent supply and product export.

Additionally, Pensana’s management team is active in:

 * Discussions with a number of rare earth project developers with a view to providing
   them with an attractive processing alternative to the existing supply chains 
   in China.
 * Advancing the recently completed concept study into the establishment of a facility
   at Saltend to convert the NdPr oxides into metal alloy.
 * Discussions with Equinor following first phase approval to establishing a hydrogen
   based (NdPr) recycling facility at Saltend for end-of-life offshore wind turbine
   nacelles.
 * Undertaking life cycle analysis on the total carbon emissions of the final product.

These early works mark the beginning of the use of proceeds:

| _Saltend Solvent extraction (“SX”) refinery                         _ | _$4.9m_ | 
| _Longonjo site infrastructure                                               _ | _$3.4m_ | 
| _Longonjo concentrator plant                                              _ | _$5.1m_ | 
| _Longonjo Mixed Rare Earth Sulphate (“MRES”) plant_ | _$4.7m_ | 
| _General corporate expenses, exploration and deal costs_ | _$3.0m_ |

> **Paul Atherley, Chairman of Pensana, commented:** 
> “Demands for more secure and responsible supply chains, higher prices on carbon,
> and policies such as the border carbon adjustments are setting the stage for greater
> transparency and traceability in minerals and metals – enablers of the global 
> energy transition.
> The Humber is already the UK’s busiest port complex the freeport status with its
> customs and tax incentives aimed at levelling up provides the opportunity to establish
> the world’s first rare earth processing hub within an economic enterprise zone,
> with the benefits of frictionless trade with Europe and the rest of the world.
> We continue to work closely with our application for funding from the Automotive
> Transformation Fund, a long-term programme designed to enable the UK to build 
> the world’s most comprehensive and compelling electrified vehicle supply chain,
> supporting over 160,000 jobs.”