# Oriole Resources reports 32.2Mt maiden marble resource at Wapouzé

- Link: https://www.directorstalkinterviews.com/oriole-resources-reports-32-2mt-maiden-marble-resource-at-wapouze/4121265554
- Published: 2026-10-07T07:06:00+01:00
- Author: Amilia Stone

**[Oriole Resources](https://www.directorstalkinterviews.com/company/oriole-resources-plc/orr.l)
plc** (LON:ORR), the AIM quoted exploration and development company focused on Central
and West Africa, has announced the maiden Mineral Resource Estimate (MRE) for metamorphosed
limestone at its 85%-owned Wapouzé project in north-eastern Cameroon.

**Highlights**

·          Maiden JORC Inferred MRE for the Project of 32.2Mt, with weighted average
grades of 50.33wt% CaO, 1.13wt% MgO and 6.06wt% SiO₂ indicating the potential to
support a multi-decade limestone mining operation.

·          The MRE, which used a 42wt% CaO lower grade cut-off, has defined six 
separate marble domains (M1-6) across the north-eastern part of the Wapouzé licence,
covering a cumulative 2.6km strike length.

·          Four pit shells that demonstrate reasonable prospects for eventual economic
extraction (“RPEE”) have been defined:

o        Pit 1 (comprising domains M1 and M2) delivers the best quality material
and accounts for around one third of the Resource. 

o        At a potential production rate of around 400ktpa, Pit 1 alone contains 
an equivalent to 27.5 years of marble feed.

·          Outside of the MRE, an additional JORC Exploration Target has been estimated
for between 5.5 and 14.0Mt, with average grades between 48 and 53wt% CaO and between
0.8 and 1.4wt% MgO^([1])

·          A local level Environmental and Social Impact Assessment (ESIA) is currently
underway to support the submission of an Exploitation Licence Application (ELA) 
in Q4-2026.

·          The Company will now also prepare a preliminary economic assessment (
PEA) and is ultimately looking to achieve a royalty-based income that could be used
as additional funding for Oriole’s gold-focused exploration work in Cameroon.

> **Chief Executive Officer of Oriole Resources, Martin Rosser, said:** “We are 
> delighted with the Wapouzé maiden MRE as it shows that the Project has excellent
> potential for supporting a multi-decade limestone quarrying operation.  Using 
> an assumed production rate of 400ktpa of limestone, we believe that, subject to
> the preparation of a PEA, the Project has the potential for an attractive economic
> return. 
> “It is envisaged that the limestone product would be predominantly used as a key
> ingredient in making valuable cement in Cameroon and neighbouring Chad.  However,
> there are other possible uses for the limestone, including as chemical lime for
> use in gold ore processing and several chemical industry processes.  Regarding
> the latter, some of the drilling results show >54%wt CaO, which is very pure and
> could be used to make chemical grade calcium carbonate.  This material may, subject
> to testing of its brightness (or whiteness), be suitable for use in the mineral
> filler market for paint, paper, plastics etc.
> “Based on the magnitude of the maiden MRE, we are hopeful that, in parallel with
> this underwriting the submission of an Exploitation Licence Application in this
> quarter, we have significantly enhanced the prospects of attracting an industry
> expert partner for the Project.”

![89bb8447 0aec 4ca9 9358 9544877d0a27 (ORR)](https://dw6uz0omxro53.cloudfront.net/
3841576/89bb8447-0aec-4ca9-9358-9544877d0a27.png "Oriole Resources reports 32.2Mt
maiden marble resource at Wapouzé (ORR)")

**Figure 1. Wapouzé MRE contained within four RPEE pit shells over satellite imagery**

**Further Details**

The Wapouzé Project is in north-eastern Cameroon, approximately 100km NE of Garoua
and 20km north of the Company’s Bibemi gold project.  Wapouzé was initially an early-
stage gold exploration project but the Project was deemed less prospective for gold
than Bibemi.  However, the Company noted the presence of large quantities of carbonate
rock (predominantly marble) and applied for a change in commodity to marble, which
was granted in 2022.

Since the change in commodity, a number of surface exploration programmes have focused
on the potential high-grade marble (typically >50% CaO with low magnesium and silica)
material that would make it potentially suitable for use in the cement industry (
see announcement dated 21 April 2026). 

In September 2026, the Company published results from its 1,053.80m (21 holes) maiden
diamond drilling programme that confirmed substantial downhole widths of high-quality
marble, including: 53.50m at an average of 53.88wt% CaO and 0.88wt% MgO from 1.30m
depth in WPDD012; and 37.15m at an average of 53.42wt% CaO and 0.82wt% MgO from 
10.95m depth in WPDD014 (see announcement dated 24 September 2026).  The majority
of holes returned high-quality marble (>50wt% CaO and <2% MgO) over more than 50%
of their length.  

The Company today reports a maiden JORC Inferred MRE, contained with six marble 
domains (M1-6), of 32.2Mt with weighted average grades of 50.33wt% CaO, 1.13wt% 
MgO and 6.06wt% SiO₂ (Table 1).  The MRE was predominantly defined from geological
and geochemical data acquired during the maiden drilling programme, together with
results of a recently completed resistivity survey.

**Table 1. JORC Inferred Mineral Resource Estimate for the six marble domains identified
at Wapouzé**

| **Marble Domain** | **JORC Classification** | **Mass** | **Average Value** | 
| **CaO** | **Al****_(2)****O****_(3)** | **BaO** | **Cr****_(2)****O****_(3)** | **Fe****_(2)****O****_(3)** | **K****_(2)****O** | **LOI** | **MgO** | **MnO** | **Na****_(2)****O** | **P****_(2)****O****_(5)** | **SiO****_(2)** | **TiO****_(2)** | 
| **t** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | **wt%** | 
| **M1** | Inferred | 7,900,000 | 52.57 | 0.94 | 0.000 | 0.00 | 0.67 | 0.14 | 40.88 | 1.02 | 0.01 | 0.16 | 0.06 | 3.65 | 0.08 | 
| **M2** | Inferred | 3,100,000 | 52.96 | 0.85 | – | 0.00 | 0.49 | 0.10 | 41.35 | 0.85 | 0.01 | 0.23 | 0.07 | 3.20 | 0.06 | 
| **M3** | Inferred | 12,100,000 | 49.44 | 1.87 | 0.002 | 0.00 | 1.28 | 0.21 | 38.36 | 1.24 | 0.03 | 0.39 | 0.10 | 7.20 | 0.16 | 
| **M4** | Inferred | 1,400,000 | 48.78 | 1.81 | 0.002 | 0.00 | 1.26 | 0.27 | 38.24 | 1.01 | 0.04 | 0.32 | 0.09 | 8.22 | 0.15 | 
| **M5** | Inferred | 300,000 | 46.03 | 2.42 | 0.002 | 0.01 | 2.06 | 0.34 | 36.77 | 1.89 | 0.04 | 0.42 | 0.11 | 10.07 | 0.25 | 
| **M6** | Inferred | 7,300,000 | 48.74 | 1.73 | 0.003 | 0.00 | 1.34 | 0.27 | 38.99 | 1.21 | 0.04 | 0.31 | 0.12 | 7.44 | 0.17 | 
| **Total** | **Inferred** | **32,200,000** | **50.33** | **1.51** | **0.001** | **0.00** | **1.07** | **0.20** | **39.39** | **1.13** | **0.02** | **0.30** | **0.09** | **6.06** | **0.13** |

**_Notes_ _and JORC Cautionary Statement:_**

 * _Effective date of the Mineral Resource Estimate is 28 September 2026, being 
   the date the Oriole data room was shared with Forge International._
 * _Mineral Resource reported within the six interpreted marble domains (M1–M6) 
   and constrained by the RPEE pit shell. The depth of the pits typically range 
   from 50m to 150m, with a local maximum depth of approximately 180m in the largest
   pit area._
 * _The MRE was modelled over a cumulative strike length of approximately 2.9 km._
 * _Reported above a 42% CaO cut-off grade._
 * _Total reported Mineral Resource of approximately 32.2 Mt at weighted average
   grades of 50.33wt% CaO, 1.13wt% MgO and 6.06wt% SiO₂._
 * _Grade estimation was undertaken within hard-boundary geological domains to preserve
   the interpreted geological and geochemical differences between the individual
   marble formations._
 * _The reported Mineral Resource represents the portion of the block model considered
   to have reasonable prospects for eventual economic extraction under the preliminary
   open-pit optimisation assumptions._
 * _The Resource Estimate is shown on a gross (100%) basis for the Wapouzé Project.
   __ _ _Oriole currently holds an 85% net attributable beneficial interest._
 * _The Mineral Resource Estimate has been prepared by Robert Davies, EurGeol, CGeol,
   a Competent Person as defined by the 2012 Edition of the JORC Code._ _ __Mr Davies
   is a Director of Forge International Limited and has sufficient experience relevant
   to the style of mineralisation, type of deposit and activity undertaken to qualify
   as a Competent Person._ _ __Mr Davies consents to the inclusion in the announcement
   of the matters based on his information in the form and context in which it appears._
 * _All figures are rounded to reflect the relative accuracy of the estimate._ _
   __Apparent differences may occur due to rounding._
 * _Mineral Resources are not Mineral Reserves and further technical, economic and
   mining studies will be required before any potential conversion to Mineral Reserves._

The marble domains were constrained using preliminary open-pit optimisation using
a range of parameters, including a limestone selling price of US$13/t, US$0.5/t 
selling cost, US$2/t mining cost, US$3.5/t processing cost, 5% mining dilution, 
95% mining recovery, 98% processing recovery and 45 degree pit slopes.  This enabled
the definition of four open-pit RPEE pit shells (Pit 1 – 4), with Pit 1 (covering
domains M1 and M2) comprising approximately one third of the Resource, contributing
11Mt at an average grade of 52.68wt% CaO and 0.97wt% MgO. 

The cumulative strike length of marble covered by all four pits is approximately
2.6km.  At a production rate of around 400ktpa, Pit 1 alone contains roughly 27.5
years of marble feed.

![A diagram of a graph showing the size of a pit  AI-generated content may be incorrect.](
https://dw6uz0omxro53.cloudfront.net/3841576/8053cbf7-6028-41c7-acf3-62aa79cb83bc.
png "Oriole Resources reports 32.2Mt maiden marble resource at Wapouzé (ORR)")

**Figure 2. 3D Isometric view of Pit 1 (M1, M2) and Pit 2 (M3) marble domain block
models with downhole CaO (wt%) data, and two RPEE pit shells targeting the domains.
Viewing ~NE.**** **

The Mineral Resource is entirely contained within the Wapouzé licence boundary. 
A minor portion of the preliminary RPEE pit shell associated with Pit 1 extends 
beyond the licence boundary (Fig. 1); however, no Mineral Resource is reported outside
the licence area.  This is not considered material to the reported Mineral Resource
Estimate.  Future mine planning and optimisation will be constrained to the applicable
licence boundary.

Outside of the MRE, Forge has also defined a JORC Exploration Target* of between
5.50 to 14.0Mt with average CaO grades between 48 and 53wt%, and MgO grades between
0.8 and 1.4wt% (Table 2, Fig 3).  This has been defined as areas of mapped marble
occurrences outside of the MRE, where there is surface rock chip sampling and portable
XRF data but no drilling.  The Exploration Target has been projected to vertical
depths of 40m and 100m as the lower and upper bounds.

**Table 2. JORC Exploration Target\* for the material with mapped outcrop and rock
chip data that sits outside of the MRE**

| **Exploration Target** | **Tonnage (Mt)** | **CaO (%)** | **MgO (%)** | 
| Lower Case | 5.5 | 48–53 | 0.8–1.4 | 
| Upper Case | 14.0 | 48–53 | 0.8–1.4 |

*The potential quality and grade of the Exploration Target are conceptual in nature.
There has been insufficient exploration to estimate a Mineral Resource, and there
is no certainty that further exploration work will result in the determination of
a Mineral Resource.

_**Notes and JORC Cautionary Statement**_

 * _Effective date: 28 September 2026._
 * _The Exploration Target is based on mapped limestone/marble outcrop, geological
   interpretation, surface rock-chip sampling and XRF data._
 * _The tonnage range has been derived by projecting the mapped limestone/marble
   occurrences to vertical depths of 40m and 100m, representing the lower and upper
   cases respectively._
 * _Indicative grade ranges of 48–53wt% CaO and 0.8–1.4wt% MgO have been assigned
   based on the available surface sampling and observed geological/geochemical characteristics._
 * _The Exploration Target is shown on a gross (100%) basis for the Wapouzé Project.
   __ _ _Oriole currently holds an 85% net attributable beneficial interest._
 * _The Exploration Target is conceptual in nature._ _ __There has been insufficient
   exploration to estimate a Mineral Resource in these areas, and it is uncertain
   whether further exploration will result in the estimation of a Mineral Resource._
 * _The Exploration Target is not a Mineral Resource or Mineral Reserve and should
   not be considered equivalent to, or combined with, the reported Mineral Resource._
 * _Further geological mapping, systematic surface sampling and drilling will be
   required to test the interpreted continuity, thickness, depth extent and grade
   of the limestone/marble occurrences._
 * _All figures are approximate and have been rounded to reflect the conceptual 
   nature and level of geological confidence of the Exploration Target._
 * _The Exploration Target has been prepared by Robert Davies, EurGeol, CGeol, a
   Competent Person as defined by the 2012 Edition of the JORC Code. Mr Davies is
   a Director of Forge International Limited and has sufficient experience relevant
   to the style of mineralisation, type of deposit and activity undertaken to qualify
   as a Competent Person. Mr Davies consents to the inclusion in the announcement
   of the matters based on his information in the form and context in which it appears._

![The image appears to be a geological map or cross-section, showing various data
points, such as locations (E or N), depth (N), and other measurements like plunge
and azimuth, along with labels for different rock types or geological features.  
AI-generated content may be incorrect.](https://dw6uz0omxro53.cloudfront.net/3841576/
9adec23b-40bd-4640-bc07-6c690557e335.png "Oriole Resources reports 32.2Mt maiden
marble resource at Wapouzé (ORR)")

**Figure 3. 2D view of the Exploration Targets for Wapouzé and their spatial relationship
with rock-chip sampling data and the MRE pit shells**

The Company is also undertaking a local-level ESIA for Wapouzé which, once completed,
will form part of an ELA for the Project.  The ELA, which is expected to be for 
a simple quarrying operation for the extraction of the marble, is targeted for submission
in Q4-2026.

Commercially, a significant limestone deposit at Wapouzé could be highly suitable
for use within Cameroon’s cement industry, which is believed to be worth several
hundred million pounds per year, largely supported by expensive imports of required
clinker material.  The Company believes that there is a significant demand for cement(
for concrete) within Cameroon and neighbouring Chad (with its capital, N’Djamena,
approximately 250km NNE of Wapouzé).  Furthermore, Cameroon has seen substantial
foreign investment made into expanding its cement manufacturing capacity, with neighbouring
plants to Wapouzé producing cement from similar material, and the government is 
keen to see its reliance on imported clinker reduce significantly.

The Company also recognises that crushed marble products of specific characteristics
can also be used in other industrial processes outside of clinker/cement production.
For example, material with a high CaO (>54wt%) should qualify as chemical lime, 
which is a relatively valuable commodity and used in gold ore processing, but also
in many chemical industry processes. 

Oriole Resources is continuing its discussions with potential industry partners 
that could advance Wapouzé towards development and exploitation on an expedited 
basis.  The Company is ultimately looking to achieve royalty-based income from a
commercial scale quarrying operation, likely to be based upon the volume of material
extracted, which would provide valuable in-country revenue that could be used additional
funding for its gold exploration work in Cameroon.