# Oriole Resources Mbe project reaches 1.66Moz gold resource milestone

- Link: https://www.directorstalkinterviews.com/oriole-resources-mbe-project-reaches-1-66moz-gold-resource-milestone/4121257501
- Published: 2026-07-23T07:18:11+01:00
- Author: Amilia Stone

**[Oriole Resources](https://www.directorstalkinterviews.com/company/oriole-resources-plc/orr.l)
plc** (LON:ORR), the AIM quoted gold exploration and development company focused
on Central and West Africa, has published an updated JORC Mineral Resource Estimate
for the MB01-S deposit at its 50% owned Mbe orogenic gold project in Cameroon. Together
with the Mineral Resource Estimate for the neighbouring MB01-N deposit, published
on 13 April 2026, the total JORC Inferred Mineral Resource at the project is now
1.66 million oz contained gold with a mean grade of 1.02g/t.

**Highlights**

·   Following completion of the 10-hole step-out drilling programme last month, 
independent consultant Forge International Limited (“Forge”) has produced an updated
Inferred MRE for MB01-S of 40.1Mt with a mean grade of 1.01g/t for 1,300,000oz contained
gold.  This equates to an approximate 50% uplift to the maiden Inferred MRE for 
MB01-S and replaces that estimate.  Both the previous and the updated estimates 
have been reported using a US$3,200/oz gold price and a lower cut-off grade of 0.40g/
t Au.

·    The MRE now extends over a strike length of approximately 1,200m, a width of
up to 730m, a maximum vertical depth of 287m and remains open laterally and at depth.

·   Combined with the existing Inferred MRE at MB01-N (360,000oz at a mean grade
of 1.05g/t), located 700m to the northeast of MB01-S, Mbe now has a total Inferred
MRE of 1.66 million oz contained Au, with both deposits remaining open laterally
and at depth and with further potential satellite targets within the wider licence
area. 

·   Together with its partner, BCM International (“BCM”), the Company is now planning
the next work programmes and an update will be provided in due course.

·    The Company believes that the Project has multi-million-ounce potential.

> **Chief Executive Officer of Oriole Resources, Martin Rosser, said:** _“After 
> the completion of the recent step-out drilling programme, we had high hopes for
> a significant increase in the MB01-S MRE contained ounces.  The amount of 1.3Moz
> just published has comfortably exceeded that expectation with an almost 50% increase.
> Moreover, this was based on a relatively modest amount of drilling, 2,476.80m 
> in 10 holes, and the deposit is still open in all directions. _
> _“The current gross contained gold of 1.66Moz in the MRE for the Mbe project is
> a tremendous achievement and we maintain our firm opinion that the Mbe project
> licence has multi-million-ounce gold potential. _
> _“Not only is this a great outcome for Mbe but now for all of Oriole’s gold projects
> combined, the Company has an attributable MRE total contained gold amount of 1.11Moz,
> comfortably over the 1Moz major milestone._
> _“We are greatly looking forward to undertaking further_ _exploration_ _and evaluation
> at Mbe and enhancing our conceptual thinking on potential mine development.”_

![The image depicts a mineralized ore deposit map, illustrating two mining areas,
MB01-N and MB01-S, with their respective gold concentrations and estimated gold 
content. AI-generated content may be incorrect.](https://dw6uz0omxro53.cloudfront.
net/3773581/bcb42be4-d91f-4363-8d72-a118f73d0b56.jpg "Oriole Resources Mbe project
reaches 1.66Moz gold resource milestone (ORR)")

**Figure 1. Plan view of the total JORC Inferred Resource for Mbe, with pit-constrained
MREs for MB01-N and MB01-S, showing the block models and US$3,200/oz pit shells.**

**Further Details**

The updated MRE for the MB01-S deposit has been prepared by Forge, incorporating
data from the recently completed step-out drilling programme (see announcement dated
6 July 2026), is presented in Table 1 and has been reported in accordance with the
JORC Code.  The new estimate, which is based on a combination of drill hole and 
trench assay data acquired by the Company since 2024, is 40.1Mt at a grade of 1.01g/
t for 1,300,000oz contained Au, based on a 0.40g/t Au lower cut-off grade and is
constrained within an open pit shell optimised using a US$3,200/oz gold price. 

**Table 1. JORC MRE for MB01-S**

| **JORC Classification** | **Oxidation Level** | **Gross** | **Net Attributable (50%)** | 
| **Tonnage (t)** | **Grade (g/t)** | **Total Contained Gold (oz)** | **Tonnage (t)** | **Grade (g/t)** | **Total Contained Gold (oz)** | 
| **Inferred** | Oxide | 6,400,000 | 0.87 | 180,000 | 3,200,000 | 0.87 | 90,000 | 
| Fresh | 33,700,000 | 1.04 | 1,120,000 | 16,850,000 | 1.04 | 560,000 | 
| **Total** | **40,100,000** | **1.01** | **1,300,000** | **20,050,000** | **1.01** | **650,000** |

_Notes:_

·     _Effective date of the Mineral Resource is 8 July 2026, being the date the
Oriole data room was shared with Forge._

·     _The Resource has been estimated and reported by Robert Davies, EurGeol, CGeol,
a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves (JORC Code).  Mr. Davies
is a Director of Forge International and has sufficient experience relevant to the
style of mineralisation, type of deposit, and activity undertaken to qualify as 
a Competent Person.  Mr. Davies consents to the inclusion of this information in
the form and context in which it appears._

·     _The Operator of the Mbe Project is Oriole Resources._

·     _The Mineral Resource Estimate is based on total of 13,761 samples, collected
from 4,453m of trenching and 9,305m of diamond drilling from 34 holes, with gold
grades estimated using ordinary kriging within hard-boundary mineralisation wireframes,
based on length-weighted composited assay data._

·     _The Mineral Resource extends over a strike length of approximately 1,200m,
up to 730m width and to a maximum depth of 287m.  To define the blocks with reasonable
prospects of eventual economic extraction (RPEEE) as required under the JORC Code(
2012 Edition), the estimate has been constrained within a Lerchs-Grossman optimised
pit shell generated in Datamine NPVS, using a gold price of US$3,200/oz and the 
application of reasonable mining parameters as set out in the Project’s JORC Table
1._

·     _The Mineral Resource has been reported above a cut-off grade of 0.40 g/t 
Au and filtered by the pit shell constraint._

·     _The Resource Estimate is reported on both a gross, 100% basis and a net attributable
basis.  Oriole holds a 50% beneficial interest through the licence-holding company,
Oriole Cameroon SARL.  The remaining 50% interest is held by BCM International Limited
following completion of its earn-in, as announced on 20 February 2026._

·     _All figures are rounded to reflect the relative accuracy of the estimate.
Differences may occur due to rounding._

·     _The reported Mineral Resources are not Mineral Reserves and have not been
demonstrated to be economic to mine to the level needed to report an Ore Reserve.
Further exploration, sampling, and economic studies are required before any potential
conversion to Ore Reserves can be considered._

·     _A site visit to the Mbe Project was completed by Mitko Ligovski, a Competent
Person representing Forge International, who verified the geological and sampling
data used in this estimate._

·     _Limited preliminary environmental and social baseline work has been undertaken
at the site._

This Inferred MRE represents an approximate 50% uplift to the 870,000oz maiden MRE
for MB01-S, reported on 21 October 2025, and the deposit still remains open laterally
and at depth.

![Picture 1](https://dw6uz0omxro53.cloudfront.net/3773581/dec69d03-5b1b-4087-bb51-
71c0cc1c0929.gif "Oriole Resources Mbe project reaches 1.66Moz gold resource milestone(
ORR)")

**Figure 2. Plan view of the pit constrained MRE model for MB01-S, showing the block
model and US$3,200/oz pit shells.  The black line denotes cross section line presented
in Figure 3 below; note that is it orientated slightly oblique to the east-west 
orientated drill fence lines.**

![Picture 1](https://dw6uz0omxro53.cloudfront.net/3773581/a8c5e8c4-e710-47d8-acc6-
4abf7801af2b.gif "Oriole Resources Mbe project reaches 1.66Moz gold resource milestone(
ORR)")

**Figure 3. Cross section approximately along N872530 at MB01-S (viewing approximately
north) showing the assay results from both trenching and drilling, the US$3,200/
oz pit shell, and mineralised wireframe model.**

The grade-tonnage sensitivity analysis in Table 2 demonstrates that the deposit 
is not particularly sensitive to cut-off grade.

**Table 2.  Grade tonnage sensitivity for MB01-S zone MRE**

| **Cut-off Au (g/t)** | **Tonnes** | **Grade Au (g/t)** | **Contained Gold oz.t** | 
| 0.25 | 42,800,000 | 0.97 | 1,330,000 | 
| 0.3 | 42,400,000 | 0.98 | 1,330,000 | 
| 0.35 | 41,500,000 | 0.99 | 1,320,000 | 
| **0.4** | **40,100,000** | **1.01** | **1,300,000** | 
| 0.45 | 38,200,000 | 1.04 | 1,280,000 | 
| 0.5 | 35,300,000 | 1.09 | 1,240,000 | 
| 0.55 | 31,900,000 | 1.15 | 1,180,000 |

_Note:_

·    _All figures are rounded to reflect the relative accuracy of the estimate. 
Differences may occur due to rounding._

·    _The grade-tonnage sensitivity information is presented for illustrative purposes
only and does not constitute a separate Mineral Resource estimate._

The Inferred MRE for MB01-S is in addition to the 360,000oz contained Inferred MRE
published for the MB01-N deposit on 13 April 2026, which is restated below and takes
into account Oriole’s net attributable interest.  For full disclosure notes related
to the MB01-N MRE, please refer to the Company’s original announcement dated 13 
April 2026.

**Table 3. JORC MRE for MB01-N**

| **JORC Classification** | ** ****Oxidation Level** | **Gross** | **Net Attributable (50%)** | 
| **Tonnage (t)** | **Grade (g/t)** | **Total Contained Gold (oz)** | **Tonnage (t)** | **Grade (g/t)** | **Total Contained Gold (oz)** | 
| **Inferred** | Oxide | 800,000 | 0.75 | 20,000 | 400,000 | 0.75 | 10,000 | 
| Fresh | 9,700,000 | 1.07 | 340,000 | 4,850,000 | 1.07 | 170,000 | 
| **Total** | **10,500,000** | **1.05** | **360,000** | **5,250,000** | **1.05** | **180,000** |

Mbe now has a total JORC Inferred MRE of 1.66 million oz contained Au with a mean
grade of 1.02g/t, with both deposits remaining open laterally and at depth and with
further potential satellite targets within the wider licence area.  The Company 
maintains its belief that the Project has multi-million-ounce potential.

The Company and BCM are currently planning work programmes for the 2026/27 field
season and an update on this will be provided in due course.

In addition, work is still underway to formalise BCM’s 50% beneficial interest in
Mbe, with the drafting of a joint venture partnership agreement in progress. 

Further information can be found in the Mbe JORC Table 1 disclosure on the following
page of the Company’s website: https://orioleresources.com/projects/mbe/