# Oriole Resources advances Bibemi project with 23% reduction in capital costs

- Link: https://www.directorstalkinterviews.com/oriole-resources-advances-bibemi-project-with-23-reduction-in-capital-costs/4121269962
- Published: 2026-11-18T07:02:00+00:00
- Author: Amilia Stone

**[Oriole Resources](https://www.directorstalkinterviews.com/company/oriole-resources-plc/orr.l)
plc** (LON:ORR), the AIM quoted exploration and development company focused on Central
and West Africa, has announced an update on its 50% owned Bibemi gold project in
north-eastern Cameroon. The Company’s third-party consultant, Stirling Process Engineering
Limited has now completed a Scoping Study, based on low-level technical and economic
assessments, on the recently reported ultra-fine grinding mineral processing flowsheet
for sulphide material only (see announcement dated 2 November 2026), to enable a
comparison with the previously reported pressure oxidation mineral processing flowsheet(
see announcement dated 15 May 2025).

**Highlights**

 * The UFG flowsheet shows a substantial 38% reduction in the sulphide only processing
   plant capital cost (CAPEX) of US$13.7m compared to the POX flowsheet, reducing
   the total initial Project CAPEX by 23% to US$46.7m.

 * The simpler UFG flowsheet will reduce operational complexity compared to POX,
   which should assist with project financing, and remove the requirement for several
   highly skilled autoclave technicians.  The estimated operating expenditure (OPEX)
   for the UFG flow sheet is slightly higher per ounce of gold recovered compared
   to the prior POX method study as a result of an increased throughput, lower recovery
   and an increase in power costs.  

 * According to Stirling, there is scope for further optimisation of the UFG flowsheet
   to improve efficiency in overall gold recoveries during the flotation and leaching
   stages and to reduce the reagent costs, which represent a significant portion
   of the total processing costs.

 * The Company will now update the Project’s Preliminary Economic Assessment (“PEA”)
   to incorporate the findings of the UFG Scoping Study and the implications for
   a revised mine planning schedule.  The updated PEA is expected in the coming 
   months.

**Table 1. Overview of key parameters between the POX and UFG processing methods**

| **Parameter** | ** ** | **Units** | **POX** | **UFG** | **Variance** | 
| **Units** | **%** | 
| Plant | Throughput | tpa | 190,800 | 207,956 | 17,156 | +9.0 | 
| Gold recovery | % | 85.0 | 78.7 | -6.3 | -7.4 | 
| Gold production | Oz pa | 10,000 | 10,000 | – | – | 
| CAPEX | Plant | US$m | 35.8 | 22.1 | -13.7 | -38.3 | 
| Project total | US$m | 60.4 | 46.7 | -13.7 | -22.7 | 
| OPEX | Plant | US$m | 30.1 | 29.7 | -0.46 | -1.5 | 
| Project Total | US$/oz | 574.7 | 616.9 | 42.4 | +7.3 | 
| Notes:All costs to scoping study levels of confidence, ±30%POX study used power cost of US$100/MWh; UFG used US$200/MWh |

> **Commenting Chief Executive Officer of Oriole Resources, Martin Rosser, said:**
> “_The key economic findings of the UFG Scoping Study for Bibemi are highly encouraging.__
> __Not only are there notable operational and potential financing benefits, but
> there is a large capital cost saving on the processing plant of US$13.7m, with
> only a slightly increased processing operating cost per ounce of gold produced._
> _“Although the new findings mean that updating the PEA will take slightly longer
> than earlier forecast, once completed it could show a significant improvement 
> in Project economics by adopting the UFG processing method.__ _ _Importantly, 
> we have been awaiting this new information and material development to bolster
> and support the current Bibemi exploitation licence application negotiation effort
> whilst we finalise the PEA in parallel, which we look forward to reporting on 
> in due course.”_

**Further Details**

At the 177km^(2) Bibemi orogenic gold project in the North region of Cameroon, the
Company’s exploration to date has identified shear-hosted gold mineralisation at
four main prospects – Bakassi Zone 1, Bakassi Zone 2, Lawa West and Lawa East – 
within an approximately 12km long mineralised hydrothermal system at surface.

The Project has a Mineral Resource Estimate (“MRE”) of 6.96Mt at 2.06g/t Au for 
460,000oz contained Au, 100,000oz Au of which is classified as Indicated, and the
remaining classified as Inferred under the JORC Code.  The MRE, which is located
entirely within the BZ1-MRE zone, is calculated using a 0.40g/t Au cut-off grade
and is constrained by a US$2,750/oz gold price pit shell (see announcement dated
15 May 2025).  In addition to the MRE, the Company has also reported an Exploration
Target across the Bibemi project of between 3.0 and 5.0Mt with an average grade 
of between 1.50 and 2.50g/t Au, for between 145,000 and 400,000oz contained gold.
The potential quantity and grade of the Exploration Target are conceptual in nature.
There has been insufficient exploration in the areas covered by the Exploration 
Target to estimate a Mineral Resource, and it is uncertain whether further exploration
will result in the estimation of a Mineral Resource.

The Company has submitted an Exploitation Licence Application (“ELA”) for the Project,
which is envisaged to be a small-scale, open pit mine that would target an optimised
open-pit scenario of 89,000oz Au, largely centred on the 100,000oz Au Indicated 
Resource.  As part of the ELA an initial PEA of this optimised scenario, assuming
a 7-year mine life, at ~10,000oz pa Au average annual production, was included within
the ELA (see announcement dated 16 December 2025), and is considered to be at Scoping
Study level.

The initial PEA assumed an 85% gold recovery which reflected results from prior 
metallurgical testwork on sulphide material, at SGS South Africa between 2022 and
2024, that outlined a provisional mineral processing flowsheet to treat the gold-
telluride mineralogy, comprising flotation, POX of the float concentrate, and leaching
of the pressure oxidation residue (see announcement dated 15 May 2025).

Further metallurgical testwork completed this year enabled the development of an
alternative processing flowsheet which comprised flotation, UFG of the float concentrate(
to 80% of material passing at 10μm size or less) and then leaching of the UFG material(
announcement dated 2 November 2026).  The UFG flowsheet targets the sulphide material
only, which contains ~97% of the gold within the ~89,000oz targeted by the optimised
pit scenario at Bibemi (see announcement dated 16 December 2025).  The modest amount
of oxide material would be stockpiled for potential processing later.

The Company today reports that Stirling has completed a Scoping Study for the UFG
flowsheet which has enabled a direct comparison between the UFG and POX flowsheets.
Both flowsheets were designed based on an anticipated gold production rate of 10,000oz
pa and used certain assumptions such as labour, power, and administration costs 
relevant at the date of each study.  The information in this announcement that relates
to mining, processing, metallurgical recovery, infrastructure, capital and operating
cost estimates is based on data and assumptions developed for the purposes of a 
Scoping Study and does not constitute Ore Reserves or JORC‑reportable estimates.

A comparison of key statistics from the two estimates is presented in Table 1.  
The costs are presented to Scoping Study level, with ±30% accuracy.  The UFG flowsheet
represents a lower overall gold recovery (approximately 79%) compared to POX (approximately
85%) although this likely reflects a lower sample head grade from the most recent
metallurgical testwork.

The UFG flowsheet presents a significant 38% reduction in plant CAPEX of US$13.7m,
being estimated at US$22.1m compared to US$35.8m for the POX processing method, 
reducing total expected Project CAPEX to US$46.7m.  The OPEX costs for both methods
are broadly similar, with the UFG scenario being slightly cheaper per tonne compared
to POX (US$29.7/t vs US$30.1/t), albeit 7% more expensive on a per oz of gold basis(
~US$617/oz vs ~US$575/oz).

The Company also recognises that gold recoveries may be improved in the UFG flowsheet
through further investigation and optimisation of the flotation design and leaching
conditions. Optimisation studies into reducing the pre-aeration time and reducing
the free cyanide level in the leach are being considered.  These studies may enable
a reduction in the consumption of cyanide and lime reagents, which represent a significant
portion of the total processing costs.

ALS Ltd. Australia is also completing final testwork to assess whether further recovery
of gold from the flotation tailings might be possible and this testwork will conclude
shortly.

Considering the significant CAPEX cost savings, the potential for further gold recovery
improvement and cost savings with optimisation of the flowsheet, and the logistical
and technical benefits of the UFG flowsheet (see announcement dated 2 November 2026),
UFG is considered to represent a more viable processing option at Bibemi than POX.

The Company is now in the process of updating the PEA based on the UFG flowsheet,
refreshed earthmoving costs due to the oxide material pre-strip, increased plant
throughput and slightly lower overall gold processing plant recovery.  The Company
aims to publish this as soon as possible