# Metal Tiger plc Potential Major Strike Extension Botswana Copper/Silver Project

- Link: https://www.directorstalkinterviews.com/metal-tiger-plc-potential-major-strike-extension-botswana-coppersilver-project/412737325
- Published: 2017-10-03T07:19:52+01:00
- Author: Giles Arbor

**Metal Tiger plc** (LON:MTR), the London Stock Exchange AIM listed investor in 
strategic natural resource opportunities, has today provided an update regarding
the Company’s Joint Venture (“JV”) project with partners MOD Resources (ASX:MOD)
in the Kalahari Copper Belt in Botswana (70% MOD Resources/30% Metal Tiger). Metal
Tiger also holds 95,543,934 MOD shares, equivalent to 5.049% of MOD’s issued share
capital and 1,541,667 MOD warrants at an exercise price of 6 cents (Australian).
Activities in Botswana are conducted under the JV’s local operating company Tshukudu
Metals Botswana (Pty) Ltd. (“Tshukudu”).

**Highlights:**

Drilling has intersected new zones of visible copper mineralisation 300m west and
northeast of planned pit.
 Copper mineralisation now extends over a strike length
of 1.5km and remains open. Seven drill rigs now operating at T3, diamond core drilling
progressing well. Prefeasibility Study now modelling a 2.5Mtpa processing rate, 
up 25% compared to the Scoping Study. Excellent metallurgical testwork results received.

> **Michael McNeilly Chief Executive Officer of Metal Tiger plc commented:** “We
> are delighted to provide an update on activities in Botswana. Since drilling recommenced
> in August, the Tshukudu team have completed over 6,100 metres of drilling with
> a total of 19 diamond holes completed or in progress.
> Very excitingly, 50m wide zones of visible copper mineralisation have been logged
> in core from four holes drilled along strike from the current T3 Mineral Resource.
> We eagerly await the assay results from these holes, and other holes, which point
> to the potential for major strike and down-dip extensions to the current Resource.
> Work on the Prefeasibility Study is also progressing well and remains on schedule
> with the decision taken to increase the modelled ore processing rate to a level
> 25% above that used in the Scoping Study to reflect the increase in the Mineral
> Resource, the expected mineable inventory increase and the strong copper price.
> We look forward to assessing the positive effect these factors have on the Project’s
> baseline economics.”

For images that may assist readers in the visualisation of the T3 Project area and
drill collars mentioned in this announcement, we would refer to the announcement
released today by MOD Resources. This announcement can be viewed through the following
link:

http://search.asx.com.au/s/search.html?query=mod&collection=asx-meta&profile=web

Shareholders should note that the timing of MOD announcements are outside the control
of MTR, however, MTR does its utmost to announce the drill results and important
updates as soon as practicable after MOD makes its announcement to the ASX. MTR 
are only made aware of drill results and important updates immediately prior to 
the MOD release.

**T3 Drilling Programme Update**

The current phase of drilling at the T3 Copper/Silver Deposit commenced on 7th August
2017, with approval granted for the recommencement of both diamond core (DC) and
reverse circulation (RC) drilling at the T3 Project and its vicinity, through to
December 2018.

Visible copper mineralisation consisting multiple intervals of disseminated and 
vein hosted sulphides have been logged within wide zones estimated to be greater
than 50m true thickness, in diamond drill holes, MO-G-74D, MO-G-76D, MO-G-79D and
MO-G-80D, located along strike at the eastern and western limits of drilling at 
T3.

New zones of mineralisation are well outside the current Mineral Resource area. 
Assay results are required to confirm the copper intervals, though geological logging
has determined that mineralisation is dominated by finely disseminated chalcocite
with localised veins showing chalcocite and bornite. The mineralisation is hosted
by both sandstone and mudstone.
 New zones are located down-dip from narrow intersections
of copper and lead/zinc mineralisation intersected at shallow depth by previous 
drilling. For example, the wide intersection of visible sulphides in MO-G-80D, located
300m west of the planned open pit occurs circa 200m down dip from a 1m intersection
of chalcopyrite intersected in water bore hole MO-G-WB06. Copper mineralisation 
now extends over an open strike length of over 1.5km.

Several other holes in the current programme have intersected encouraging vein hosted
mineralisation down-dip from the planed T3 open-pit. Assay results from these holes
will be announced soon and once infill drilling is complete drilling will focus 
on this area.

Drilling has also targeted the Induced Polarisation (IP) geophysics anomaly located
to the north of T3. Hole MO-3R-08D has been completed to a depth of 643.9m intersecting
minor vein hosted chalcopyrite between 590m and 595m down hole, but not determining
the source of the IP anomaly. The possibility that the target sequence may be off-
set, to the north of MO-3R-08D, by a major structural feature interpreted from the
drill core, is planned to be investigated by future drilling. This major structure
may also be related to the 10km long Electromagnetic (EM) geophysics anomaly (T3
Deposit EM anomaly) which extends to the east and west of T3 (see announcement of
21 July 2017).

Currently, there are 7 drill rigs now operating at T3; two DC rigs testing east 
and west strike extensions to T3 Deposit; three DC rigs infill drilling the current
Resource; and two RC rigs drilling diamond hole pre-collars and drilling water boreholes
to test the potential for a sustainable source of plant processing water.
 Since
drilling recommenced, a total of 11 new DC drill holes have been completed (totalling
4,405m), 4 depth extensions (totalling 1,695m) have been drilled to previous holes
and 4 new DC holes are in progress.

**T3 Prefeasibility Study (PFS) Progress**

The T3 open-pit prefeasibility works are progressing to schedule with the completion
of the overall PFS Study expected in December 2017. Updates on the specific study
elements are outlined below.

**Mining & Process Engineering Studies**

Annual ore production targets have been revised to an ore processing rate of 2.5
Mtpa, a 25% increase on the Scoping Study production target.
 Upgrade is in response
to the growth in the T3 Mineral Resource Estimate (announced 24 August 2017), the
expected increase in the mineable inventory and the strength in the copper price
since the Scoping Study was announced.

Planned process plant design will allow for a possible future expansion of up to
4.0 Mtpa. This expansion capacity gives optionality if there are further upgrades
to the T3 Resource and possible supplementary ore supply from nearby deposits.

**Metallurgical Studies**

Results of locked cycle testwork on composite samples for the three main T3 ore 
domains (Chalcocite, Bornite and Chalcopyrite) have been received (Table 1).
 Table
1: Locked Cycle testwork results from composite samples of three T3 ore types.

  |  Domain |  Copper |  Silver |  Mass Recovery % |  
 |  Recovery % |  Grade % |  Recovery % |  Grade g/t |  
 |  Chalcocite |  93.43 |  48.59 |  88.97 |  850 |  2.31 |  
 |  Bornite |  96.25 |  43.57 |  92.16 |  668 |  3.15 |  
 |  Chalcopyrite |  93.34 |  33.15 |  82.56 |  199 |  3.15 |

Locked cycle testwork is more indicative of a production scale metallurgical response
relative to the batch testwork which was used in the Scoping Study. Ore intervals
from a total of 22 drill holes were used to prepare representative composites for
this PFS testwork programme.

Copper recoveries are excellent, ranging from 93.3% to 96.3% into concentrate grades
containing 33.1% to 48.6% Cu.
 Silver recoveries and concentrate grades were also
very good notably in chalcocite and bornite ores which host most of the high-grade
silver mineralisation. Penalty elements were at acceptable levels e.g. arsenic ranged
from 254ppm to 1,905ppm.

**Hydrological Studies**

A series of large bore vertical wells are being drilled across the T3 site to allow
comprehensive testing and modelling of the groundwater quality and quantity.
 These
hydrological test wells, and associated modelling, will be used to both develop 
a water supply solution for the project and refine the open pit design currently
underway. All six water bore test holes drilled so far have struck water and results
are being evaluated. Applications for water extraction will be prepared once sustainable
yields are calculated and T3 water requirements are finalised.

**Environmental Approvals & Stakeholder Engagement**

Baseline flora, fauna and biodiversity studies are ongoing during the dry season
and are expected to be completed in the current quarter.
 Preparation is underway
to commence the formal Environmental Impact Assessment (EIA) process soon after 
completion of the Pre-feasibility Study. Exploration access agreement for the farm
associated with the T3 Project has been extended to 30 April 2018.

Exploration access agreements have been executed for farms associated with the AEM
geophysics targets surrounding T3. These farm access agreements are a precursor 
to gaining approval from the Department of Environmental Affairs (DEA) for drilling
other high priority targets along the T3 Dome.

Tshukudu is developing stakeholder engagement policies and commencing baseline social
studies to enable consistent and fair treatment of all stakeholders associated with
exploration and development activities in Botswana.

**Background**

The T3 Project is located on the Kalahari Copper Belt in northern Botswana and is
part of the MOD/MTR joint venture Botswana Copper/Silver Project. T3 is located 
within the central part of the T3 Dome (approximately 1000km2), which is the focus
of rapidly increasing exploration activity undertaken by Tshukudu. Two significant
resources have been discovered to date within the T3 Dome: T1 (Mahumo deposit 100%
MOD) and T3 (70% MOD / 30% MTR).

The T3 deposit was discovered in March 2016 when a reverse circulation (“RC”) drill
hole intersected 52m @ 2.0% Cu and 32g/t Ag from shallow depth. The maiden T3 JORC(
2012) compliant Mineral Resource was announced on 26 September 2016 with the first
Resource upgrade announced on 24 August 2017. The results of a Scoping Study for
an open pit mine at T3 with a 2Mtpa processing plant, an indicative mine life of
10 years and an average production rate of 21,800tpa of copper and 665,000oz pa 
of silver was released on 6 December 2016. Work on a Pre-Feasibility Study (PFS)
commenced in January 2017 and additional deeper copper mineralisation was discovered
below the T3 Resource in February 2017.

The T3 Prospect geological data and exploration results have been reviewed and approved
by Jacques Janse van Rensburg, BSc (Hons), Business Development Manager and Competent
Person for MOD Resources Ltd. Mineral Resource estimation and classification of 
the T3 Copper/Silver Project was conducted and approved by Mr A.I. Pretorius, MSc.
Pri.Sci.Nat. an independent consultant to MOD Resources Ltd.

 