# Metal Tiger Plc Botswana Copper/Silver Project – T3 Feasibility Study Update

- Link: https://www.directorstalkinterviews.com/metal-tiger-plc-botswana-copper-silver-project-t3-feasibility-study-update/412759952
- Published: 2018-10-16T07:25:00+01:00
- Author: Giles Arbor

**Metal Tiger plc** (LON:MTR), the London Stock Exchange AIM listed investor in 
strategic natural resource opportunities, has today provided an update regarding
the Company’s Joint Venture project with partner MOD Resources Limited (ASX:MOD)
in the Kalahari Copper Belt in Botswana (70% MOD Resources/30% Metal Tiger).

**Highlights:**

· T3 Mine Feasibility Study progressing well within budget, due for completion March
2019.

· Metallurgical test work results identify capital and operational cost savings 
versus Pre-Feasibility Study.

· Botswana Power Corporation has commenced regional electricity grid infrastructure
building including a power line which is due to pass within 12km of planned T3 Mine
site.

· First stage of T3 accommodation village complete with further expansion planned.

· Scope and Terms of Reference for T3 Environmental Social Impact Assessment approved
by Botswana Department of Environment Affairs, report due Q4 2018.

· Completion of the Feasibility Study and approval of the Environmental Social Impact
Assessment are required ahead of applying for the T3 mining license, which is anticipated
in H1 2019.

> **Michael McNeilly Chief Executive Officer of Metal Tiger plc commented:**
> “We are delighted to report that the T3 Mine Feasibility Study remains on track
> to complete in March 2019, with the engineering and design works both on schedule
> and within budget.
> T3 continues to surprise to the upside and, at each juncture, capitalises our 
> belief that this is a highly economic and significant copper project. The findings
> of the Feasibility level metallurgical test work are particularly encouraging 
> with the coarser grind metal recoveries supporting a reduction in anticipated 
> capital, operational and power costs versus the Pre-Feasibility Study stage model.”

**Feasibility Study (FS) Work Stream Detail**

**Metallurgical Test work**

 

·      FS level metallurgical test work has confirmed reduction in expected capital
and operating costs through lower comminution power requirements and neutral pH 
floatation recoveries:

o  Rougher floatation recoveries exceed 97% for Cu and 95% for Ag.

o  Target grind size increased to P_(80) = 212µm (P_(80) = 106µm target used in 
Pre-Feasibility Study)

o  Rougher floatation at neutral pH without lime addition allows for operating cost
savings.

o  Coarser grind beneficial for tailings dewatering.

·      Cleaner optimisation test work to commence soon with plant concentrate grades
expected to average 30-35% Cu over the life of mine.

 

**Process Engineering**

· Comminution study completed by Orway Mineral Consultants confirms that a standard
crush/SAG/Ball circuit is appropriate for all lithological domains within the proposed
T3 pit.

· Preliminary design work on the primary crushing station and grinding circuit has
commenced. Process plant design throughput is 3Mtpa with expansion capacity to 3.5Mtpa
for modest incremental capital. Plant layout will consider future expansion options
beyond 3.5Mtpa. Work being undertaken by process engineering consultants Sedgman.

**Mining Engineering**

· T3 Mine pit design and pit optimisation study underway with mine scheduling study
expected to follow. Work being undertaken by mining consultants SRK Consulting.

· Additional geotechnical drilling is underway to provide detailed information for
the final pit design.

**Mine Dewatering & Process Water**

· Pit dewatering study drilling programme and pump testing have been completed in
the area around the planned pit.

· Groundwater modelling will be used to estimate yields from pit dewatering with
production water bores planned to be used for ore processing and related infrastructure
requirements.

**Mine Infrastructure**

· Botswana Power Corporation has commenced installation of infrastructure that will
be used as part of the grid power line adjacent to the A3 Highway between Maun and
Ghanzi, 12km from the T3 Project.

· T3 Project area 25km2 land acquisition agreement with farm finalised during Q2
2018. Acquired land is sufficient for, and will allow expansion capacity for, the
open pit, process plant and associated mine infrastructure.

· Long term lease agreement executed with a farmer for a 100m wide strip of farmland
to be used as an access road between the A3 highway and the T3 Project. This will
be used to service the mine with enough space to accommodate the planned grid power
spur line.

**T3 Accommodation Village**

· The first stage of a 40-person accommodation village, located on the A3 Highway
near Ghanzi, has been completed, subject to final signoff.

· Project Brief has been submitted to the Botswana Department of Environment Affairs(
DEA) to increase the size of the accommodation village from the current size up 
to 400 personnel and allow for an additional 300 personnel during construction.

**Environmental and Social Impact Assessment (ESIA)**

· DEA approved the Environmental Scope and Terms of Reference for the ESIA in August
2018.

· Approval confirms the work programme being undertaking will satisfy the DEA expectations
if it is carried out and reported to a satisfactory standard and meets regulatory
requirements.

· Preliminary ESIA work programme commenced in December 2017 involving stakeholder
meetings. ESIA includes a range of specialist work, an environmental and social 
management plan and regular stakeholder engagement, all of which is well advanced.

· ESIA Report on track for submission to the DEA during Q4 2018. This work compilation
is being prepared by consultants Loci Environmental.

**Current FS Resource**

· Feasibility Study is based upon the revised Mineral Resource Estimate 60Mt @ 0.98%
Cu and 14g/t Ag at a cut-off of 0.4% Cu, including approximately 36Mt @ 1.14% Cu
and 16g/t Ag in the Indicated Resource category (announced 16 July 2018). Resource
prepared by independent consultants CSA Global.

**Funding for T3 Project**

· MOD report that they are working with debt finance advisers having received significant
interest from several global financial institutions in providing finance to develop
the T3 Project.