** Meridian Mining plc **(LON:MNO) (TSX: MNO) has reported on the advancement towards
the Final Investment Decision of the Cabaçal gold, copper and silver project in 
Mato Grosso, Brazil. AFRY, an international leader in engineering, project management,
and advisory services, has been awarded Cabaçal’s Engineering, Procurement, and 
Construction Management contract. Meridian is also advancing the selection of Cabaçal’s
project finance partner(s) after receiving numerous indicative financing proposals
which include several fully funded proposals. The Company is also reporting that
orders for long-lead items are placed, and off-site access upgrades are on track
for 2026.

> **Mr. Gilbert Clark, CEO, comments**: “We are advancing towards Cabaçal’s FID 
> and welcome AFRY as our EPCM contractor. AFRY’s Brazilian team have built and 
> expanded many Brazilian mines over the last 50 years, and we look forward to their
> input as we bring into production one of South America’s most watched mine developments.
> To build Cabaçal, we need to arrange project finance, and this has been in planning
> since 2024. I am not surprised by the strength of the project finance indicative
> proposals received from the various financial, trading, and industrial groups 
> involved in the process. The project’s economics and the exceptional quality of
> its Cu+Au-Ag concentrates have created serious interest. Having a strong treasury
> of ~USD 90 million puts Meridian in a healthy position to move Cabaçal forward
> and select the right partners as we move from developer to producer while expanding
> our copper and gold exploration programmes.”

**Appointment of EPCM Contractor**

The Company has appointed AFRY as the EPCM contractor for Cabaçal, after a thorough
assessment process, including extensive technical due diligence. AFRY’s project 
construction management strength was a key factor in its selection. It continues
to be Meridian’s priority to maximise Brazilian content in Cabaçal’s build and AFRY
has been operating in Brazil since 1969 and today has approximately 1,450 professionals
in-country, supported by a global organisation of around 18,000 professionals with
a combined history dating back to 1895.

AFRY’s recent Brazilian clients, for which it has provided various engineering and
construction services, include Aura Minerals, Nexa Resources (in Mato Grosso), Hochschild
Mining and Ero Copper. AFRY’s active portfolio covers a broad range of industries,
including mining and metals, pulp and paper, pharmaceuticals, biofuels, and consumer
goods. Brazilian assignments include Arauco, Novo Nordisk, Acelen, Grupo Boticário,
CBMM, AngloGold Ashanti, and Vale.

AFRY’s current operations in Brazil are the result of various acquisitions over 
the years and from the combination of its and Poyry’s global business in 2019. The
most recent acquisition by AFRY in Brazil was Reta Engenharia, in July 2025. With
Reta Engenharia, a Brazilian company specialized in project construction management
founded in 1995 in Belo Horizonte, the combined AFRY-Reta business is a major player
in the Brazilian mining and metals engineering market. For the EPCM process, Meridian’s
build team will be operating out of AFRY’s Belo Horizonte office.

**Project Development Update**

The Company has committed to contracts totalling USD 30.9 million for pre-construction
investments on multiple fronts including the EPCM contract, power transformers, 
off-site civil infrastructure (bridges and road upgrades), a SAG mill, Jameson Cells,
and an IsaMill. To manage these activities, Meridian has expanded its “owner’s team”
to thirteen professionals, and additional management, engineering and technical 
personnel will be recruited in due course.

As outlined in the feasibility study, a 138 kV power line, spanning 24.3 km, will
be constructed, originating from the Araputanga substation – the designated connection
point to the national grid – to the Cabaçal site. The Declaration of Public Utility,
which authorises the installation of structures along the line’s route, has been
secured, as has the Installation Licence for these structures. The Company is currently
managing a competitive bidding process to select an EPC (Engineering, Procurement,
and Construction) contractor for the construction of the power line. The scope of
work includes upgrading the connection substation, constructing the power line, 
and building the receiving substation at the Cabaçal plant.

A key part of Meridian’s ramp-up towards FID, construction and then operation is
sourcing future employees from Cabaçal’s local communities. With our partner FIEMT(
Federação das Indústrias no Estado de Mato Grosso), through SENAI (Serviços Nacional
de Aprendizagem Industrial), a technical college, is being established in São José
dos Quatro Marcos that will be used to train future employees. During peak construction,
it is projected that over one thousand three hundred people will be required, and
during mining operations, more than six hundred people will be needed.

**Project Finance Update**

The Company has completed an initial outreach programme to various debt providers,
banks, funds, commodity traders and export credit agencies. The Company has received
over twenty indicative proposals with multiple proposals over USD 300 million in
debt financing. Several parties have provided fully financed indicative proposals
of USD 400 million, covering project debt, cost overrun funding, and any required
equity contribution and off-take and marketing services.

Based on Cabaçal’s DFS Technical Report (as defined below), the indicative proposals
received from these groups provide Cabaçal with a strong selection of financing 
options. The Company is currently assessing the proposals to generate a short list
of preferred bidders for detailed negotiations.