# Kenmare Resources Q2 record quarter of production for ilmenite

- Link: https://www.directorstalkinterviews.com/kenmare-resources-q2-record-quarter-of-production-for-ilmenite/4121009956
- Published: 2021-07-14T07:54:48+01:00
- Author: Giles

**Kenmare Resources plc **([LON:KMR](https://www.directorstalkinterviews.com/company/kenmare-resources-plc/kmr.l)),
one of the leading global producers of titanium minerals and zircon, which operates
the Moma Titanium Minerals Mine in northern Mozambique, has provided a trading update
for the quarter and half year ending 30 June 2021.

> **Statement from Michael Carvill, Managing Director:**
> “Kenmare’s capital investment over the last three years continues to deliver as
> Q2 saw a record quarter of production for ilmenite, improving on the record set
> in Q1 2021. WCP B continues to perform well in Pilivili, supporting higher volumes
> of ore mined and final product output. We remain confident in the outlook for 
> annual production and re-iterate our guidance of 1.1-1.2 million tonnes of ilmenite
> in 2021.
> We are concerned by the rise in delta variant COVID-19 cases in Southern Africa.
> Therefore I’m particularly pleased that we expect to offer COVID-19 vaccinations
> to all Mine employees and contractors, as well as local communities, later this
> month.
> Market conditions for ilmenite, and titanium feedstocks in general, remained strong
> in Q2 2021 with pricing strengthening quarter on quarter. The outlook for zircon
> has also continued to improve, with price increases during the quarter and continuing
> to date.”

**Q2 202****1**** o****verview**

 * Improved Lost Time Injury Frequency Rate (“LTIFR”) of 0.14 per 200,000 man-hours
   worked for the 12 months to 30 June 2021 (30 June 2020: 0.32), zero lost time
   injuries recorded during the quarter
 * COVID-19 vaccinations of the Mine workforce and local communities are expected
   to start later this month
 * Heavy Mineral Concentrate (“HMC”) production of 436,600 tonnes in Q2 2021, representing
   a 41% increase compared to Q2 2020 (310,300 tonnes), benefitting from higher 
   grade and excavated ore volumes
 * Record ilmenite production of 283,900 tonnes in Q2 2021, representing a 35% increase
   compared to Q2 2020 (209,900 tonnes), benefitting from increased HMC production
 * Primary zircon production of 14,900 tonnes, representing a 28% increase compared
   to Q2 2020 (11,600 tonnes), also benefitting from increased HMC production
 * Total shipments of finished products of 249,600 tonnes, representing a 14% increase
   compared to Q2 2020 (219,100 tonnes)
 * Kenmare expects production of all products to be within 2021 guidance
 * Strong ilmenite market conditions continued in Q2 2021 and this is expected to
   continue in Q3 2021, with higher prices agreed and a strong order book in place
 * The positive outlook for the zircon market has continued to strengthen, with 
   received prices rising in Q2 2021
 * At the end of H1 2021, net debt was US$76.1 million (31 December 2020: US$64.0
   million net debt), as a result of higher prices and sales being offset by the
   timing of capital expenditure and a reduction in the use of invoice factoring

**Production**

Production from the Moma Mine in Q2 and H1 2021 was as follows:

|   | **Q2 20****2****1** | **Q2 20****20** | **Q1 20****2****1** | **H1 20****21** | **H1 20****20** | 
|  | **tonnes** | **% variance** | **% variance** | **tonnes** | **% variance** | 
| **Excavated ore**^(1) | 10,938,000 | 6% | 22% | 19,893,000 | 8% | 
| **Grade**^(1) | 4.70% | 43% | 1% | 4.67% | 40% | 
| **Production** |   |   |   |   |   | 
| HMC production | 436,600 | 41% | 21% | 798,500 | 43% | 
| HMC consumption | 423,200 | 36% | 8% | 814,400 | 46% | 
| Ilmenite | 283,900 | 35% | 3% | 559,000 | 52% | 
| Primary zircon | 14,900 | 28% | 12% | 28,200 | 33% | 
| Rutile | 2,200 | 47% | 16% | 4,200 | 45% | 
| Concentrates^(2) | 11,800 | 31% | 33% | 20,700 | 18% | 
| **Shipments** | 249,600 | 14% | -28% | 594,100 | 44% |

 1. _Excavated ore and grade prior to any floor losses._
 2. _Concentrates include secondary zircon and mineral sands concentrate._

In Q2 2021 Kenmare’s rolling 12-month LTIFR was 0.14 per 200,000 man-hours worked(
Q2 2020: 0.32), with zero lost time injuries recorded during the quarter.

HMC production was 436,600 tonnes in Q2 2021, representing a 41% increase compared
to Q2 2020 (310,300 tonnes). This was a result of a 43% increase in ore grades (
to 4.7%) and a 6% increase in excavated ore volumes (to 10.9 million tonnes), setting
a new quarterly record of HMC production. Excavated ore volumes also increased by
22% when compared to Q1 2021, benefitting from higher mining rates from all plants.
As previously announced, grades are expected to be maintained between 4.5-5.0% Total
Heavy Mineral until Q4 2021 (when grades are anticipated to drop to ~3.7%), before
normalising at around 4.3% in 2022.

Ilmenite production rose broadly in line with increased HMC production to 283,900
tonnes, representing a 35% increase compared to Q2 2020 (209,900 tonnes). Despite
ilmenite recoveries being slightly lower than expected in Q2 2021, production set
a new quarterly record and recoveries have now returned to expected levels.

Primary zircon production increased by 28% to 14,900 tonnes in Q2 2021 (Q2 2020:
11,600 tonnes) benefitting from increased HMC consumption. Rutile production was
2,200 tonnes, up 47% (Q2 2020: 1,500 tonnes) due to increased feed and improved 
circuit recoveries. Concentrates production was 11,800 tonnes, up 31% (Q2 2020: 
9,000 tonnes) also due to increased HMC consumption.

Full year guidance, as published on the 13^(th) January 2021, is maintained for 
all products.

Total shipments in Q2 2021 increased by 14% compared to Q2 2020 and H1 2021 shipments
were up 44% on H1 2020. Kenmare shipped 249,600 tonnes of finished products during
the period (Q2 2020: 219,100 tonnes), which was comprised of 235,400 tonnes of ilmenite,
10,000 tonnes of primary zircon and 4,300 tonnes of concentrates.

Closing stock of HMC at the end of Q2 2021 was 34,300 tonnes, compared with 20,900
tonnes at the end of Q1 2021. Closing stock of finished products at the end of Q2
2021 was 164,100 tonnes, compared to 101,000 tonnes at the end of Q1 2021 (Q2 2020:
156,700 tonnes).

**COVID-19 update**

COVID-19 cases at Moma steadily decreased through Q2 2021, with 41 people in isolation
on 13 April 2021 and continued to fall to zero by late May. However, Southern Africa
has recently been experiencing a third wave of cases, which has also led to a small
increase at site, with 15 people currently in isolation.

Protecting our people and the communities in which we operate has always been Kenmare’s
highest priority. In addition to the various physical distancing and hygiene protocols,
and testing procedures, Kenmare has been working with industry partners and the 
Government of Mozambique to acquire, distribute and administer vaccines. The vaccines
are now on the way to site and vaccinations of the mine workforce and local communities
are expected to start later this month.

**Capital projects update**

The capital project to move WCP B to Pilivili, including associated infrastructure,
is now substantially complete. The final parts of the HMC pumping pipeline for WCP
B operations at Pilivili have been installed and are undergoing ramp up. Heavy mineral
product is being transported via the pipeline and a reduced trucking operation. 
It is expected that the pipeline will be operating at capacity in the coming months.
The total capital cost of the WCP B move is estimated at US$127 million, as outlined
in the Preliminary Results for 2020.

**Market**** update**

Positive market conditions prevailed for mineral sands in Q2 2021 with market prices
for ilmenite, zircon and rutile all increasing.

Ilmenite prices continued to rise through the quarter, benefitting from strong demand.
Pigment plants are operating at high production rates, whilst the titanium metal
and welding sectors are also experiencing a strong recovery. In addition, as a result
of increased production, ilmenite sales volumes increased 52% in H1 2021 (vs H1 
2020).

Despite some disruptions to major titanium feedstock producers in Q2 2021, overall
global supply has increased. This has primarily come from China and Vietnam, in 
addition to ilmenite in the form of concentrates.

The recovery in demand for zircon accelerated in Q2 2021 and price increases were
achieved for Kenmare’s zircon products. The zircon market is tight and further exacerbated
by production disruptions from zircon suppliers. Demand for Kenmare’s zircon products
is currently exceeding its ability to supply.

Due to strong global demand for commodities, the freight market has been exceptionally
tight in Q2, leading to a rapid increase in rates. These conditions are expected
to persist in H2 2021.

Positive market conditions for all Kenmare’s products are expected to continue in
Q3 2021, despite an expected strong freight market having the potential to dampen
received prices. We have a strong order book for our ilmenite products and we expect
to a supportive market for rutile and zircon in H2 2021.

**Finance update**

On 19 May 2021, Kenmare paid its 2020 final dividend of USc7.69 per share. This 
was the balancing payment of a 2020 full year dividend of USc10.00 per share, up
22% from 2019. As previously stated, Kenmare is targeting a 25% Profit After Tax
dividend payment for 2021.

Kenmare drew down in full its US$40.0 million Revolving Credit Facility in early
April 2020, as previously announced, to provide maximum liquidity and flexibility
in an unprecedented period. The Company repaid US$20.0 million of this facility 
in June 2021.

Consequently, at 30 June 2021, cash and cash equivalents were US$56.6 million (31
December 2020: US$81.1 million) and gross bank loans, including accrued interest,
were US$132.7 million (31 December 2020: US$151.3 million). Accordingly, as at 30
June 2021, Kenmare had net debt of US$76.1 million, compared to US$64.0 million 
net debt at 31 December 2020, which is mainly due to the timing of capital expenditure
payments and a reduction in the use of invoice factoring.

Kenmare Resources will announce its results for the six months ended 30 June 2020
on 18 August 2021.