# KEFI Minerals plc US$11.4 Million Commitments Received by ANS

- Link: https://www.directorstalkinterviews.com/kefi-minerals-plc-us11-4-million-commitments-received-by-ans/412771486
- Published: 2019-04-08T07:28:06+01:00
- Author: Giles Arbor

**KEFI Minerals plc** ([LON: KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Federal Democratic
Republic of Ethiopia and the Kingdom of Saudi Arabia, has today provided an update
on the project equity financing plans for the Company’s Tulu Kapi Gold Project.

ANS Mining Share Company S.C has confirmed it has now received its first Project-
equity instalment commitments for US$11.4 million (Ethiopian Birr equivalent) from
its investors. The amount is higher than the previously anticipated US$9 millon (
Ethiopian Birr equivalent). The subscription of this enlarged amount and release
of funds into Tulu Kapi Gold Mines S.C will be in the current quarter upon satisfaction
of conditions summarised below.

The remainder of the US$38 million (Ethiopian Birr equivalent) ANS commitment will
be subscribed at close of full development funding as previously announced. Following
further discussions amongst the stakeholders in the Project it has been mutually
agreed that, of the total commitment of US$38 million (Ethiopian Birr equivalent),
one third will now be invested via KEFI subsidiary KEFI Minerals Ethiopia Limited
so that ANS will be KEFI’s minority partner in KME which controls TKGM and the exploration
areas in the Tulu Kapi district, which are considered prospective for potential 
satellite and stand-alone deposits. The other two thirds of the ANS investment will
be directly into TKGM as previously proposed. Through this revised structure the
overall economics of the Project and the value of KEFI’s interest in the Project
remain unchanged.

The benefits of this optimised approach will include that:

· KEFI will have a strong partner at the KME table to consider potential new projects
alongside KEFI. We expect Ethiopia’s mining sector to become more active on the 
back of our first-mover initiative,

· That, by virtue of the TKGM partners funding the early stages of the development
program before debt-style funding is used, TKGM now targets a longer production 
ramp-up period and cash/gold-in-ore-stock build-up to over $100 million prior to
any commencement of repayments of debt-style finance,

· The implied NPV of KEFI beneficial interest in TKGM’s After Debt and After Tax
NPV (at a gold price of $1,300/oz, on the open pit only, ignoring the underground
deposit and KEFI’s other interests) is £40 million as at today and £66 million at
the start of production. The ownership levels will be that KEFI will own c. 81% 
of KME which in turn will hold c. 59% of TKGM and that KEFI’s beneficial ownership
of TKGM will be c. 45% (both ownership levels in TKGM are net, after adjustment 
for the Government’s 5% free carried interest).

The conditions precedent for the release of funds from the ANS subscription into
TKGM are principally procedural and include:

a) Normal operational and documentary confirmations and undertakings requested by
ANS,

b) National Bank of Ethiopia approval of terms of the full project finance package,
and

c) KEFI’s guarantee to ANS that if the project fails to proceed for whatever reason
and is restructured in whichever manner decided by KEFI, KEFI will ensure that ANS
recovers its 1st Instalment investment before KEFI recovers its own investment.

 

Once these closing requirements are confirmed to ANS, TKGM expects to receive the
initial US$11.4 million (Ethiopian Birr equivalent) subscription. This will place
TKGM in the position that all three of its shareholders (KEFI, Government and ANS)
are contributing to the equity funds being used to kick off the 2-year development
program. KEFI and the Government are already contributing. The local Government 
has approved the community compensation and TKGM is preparing to trigger the development
program in April.

> **Managing Director Mr Harry Anagnostaras-Adams said, **
> “KEFI feels deeply honoured to have the support of pre-eminent Ethiopian partners,
> the Government and ANS, an investment vehicle of leading local financial institutions.
> This complements our focus on ensuring TKGM is aligned with Ethiopian stakeholders
> in every possible sense, from community alignment to equity-partnering.
> The commitments into ANS are a material development and should provide KEFI Minerals
> shareholders comfort that the proposed asset-level equity financing strategy is
> progressing as previously planned. I look forward to updating shareholders upon
> completion of the documentation aspects in the near term.”

**Background**

· KME/TKGM has to date spent approximately US$60 million on the Project over a 14-
year period.

· TKGM now has US$58 million committed by its Ethiopian investors: the Ethiopian
Government and ANS.

· The Ethipoian Government approved its TKGM budget allocations on 1 March 2019 
and has started its spending program.

· The plan is to commence Project development activities with project equity and,
upon trigger of major works in Q4-19 with both project equity and project infrastructure
financing of US$160M, through the bond being arranged ACT Captal, as mandated .

· All relevant levels of the Ethiopian Government have advised they are ready to
trigger the Project development programme.

· Although there has been zero disruption at Tulu Kapi in 14 years of the activities
to date, the Company continues to ensure the highest standards surrounding safety
and security are maintained at the site.

· Another example of recent Project activity has been to reduce the number of households
relocated and to prepare the new homes and farms for the first-phase movers during
April-July 2019, before they are resettled in September-October 2019.