# KEFI Minerals plc Quarterly Operational Update

- Link: https://www.directorstalkinterviews.com/kefi-minerals-plc-quarterly-operational-update/412737734
- Published: 2017-10-09T07:16:57+01:00
- Author: Giles Arbor

**KEFI Minerals plc** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Kingdom of Saudi
Arabia and the Federal Democratic Republic of Ethiopia, has today provided an operational
update for the period from 1 July 2017 to 30 September 2017.

This quarterly operational report encompasses the activities of KEFI Minerals (Ethiopia)
Ltd (“KME”) and Tulu Kapi Gold Mines Share Company Limited (“TKGM”) in Ethiopia 
and Gold & Minerals Ltd (“G&M”) in Saudi Arabia. Some of these matters have been
reported previously.

> **Commenting, KEFI’s Executive Chairman, Harry Anagnostaras-Adams, said:** “It
> has been an exceptionally busy quarter, pulling together our project funding for
> the Tulu Kapi Gold Project in Ethiopia for the closing planned for this year. 
> We are pleased to have now also incorporated plans for extra processing capacity
> and for the drilling work required to add additional resources.
> “In Saudi Arabia, we await the announcement of the new regulations intended to
> overhaul the mining industry with a view to facilitating growth and making it 
> the third pillar of the Saudi economy. In the meantime KEFI has upgraded its portfolio
> and tenure.
> “This is a transformational time for KEFI as the team works hard, together with
> our partners, to build KEFI during the next two years into a +100,000 oz gold 
> producer. At a gold price of $1,250/oz, the first three production years’ projected
> net free cash flow per annum (after debt service and tax) exceeds the Company’s
> current market capitalisation.
> “And our existing project pipeline in Ethiopia and Saudi Arabia provides the opportunity
> to build a production base of 180,000 oz of gold per annum during Tulu Kapi’s 
> first three production years.”

**Tulu Kapi Gold Project, Ethiopia**

· KEFI received all of its VAT refund in accordance with the agreement entered with
the Government of Ethiopia in 2014 upon assuming control of the Tulu Kapi Gold Project(
the “Project”).

· Ethiopia has recently been named by the World Bank as the highest growth country
in the world, improving its ranking within the top 10 growth countries where is 
has been for 15 years running.

· KEFI and the Government of Ethiopia formed TKGM as the project company for developing
the Project. Two of the six Directors of TKGM are representatives of the Government
of Ethiopia – an endorsement of the joint commitment to developing the gold sector,
starting with the Project which ranks as a priority in the Government’s Growth and
Transformation Plan.

· The Ethiopian Government lifted the State of Emergency restrictions imposed in
October 2016. During the State of Emergency, many improvements to governance were
made by the Government, which used its executive powers to create independent review
agencies and transparent procedures. Whilst day to day life in Ethiopia was largely
unaffected and KEFI’s activities specifically were unaffected throughout, its lifting
is positive.

**Project Funding**

· Implementation of the preferred finance plan was triggered on 17 July 2017 upon
signing a detailed Heads of Terms and Mandate with Oryx Management Limited (“Oryx”)
with the goal of closing the funding package this year, which remains on track.

· Drafts of documentation have either been agreed or are advancing as planned. Oryx
has submitted its draft financing agreement to the Ethiopian authorities for approval.

· Oryx has appointed a placing agent for the issue of listed bonds and is forming
its Finance Special Purpose Vehicle which will be the bond issuer.

· The agreements with Oryx, the Government, Ausdrill and Lycopodium are being documented
in detail for approval by the counterparties and the regulators.

· The effect of these arrangements is that KEFI will have reduced the residual capital
requirement for development to proceed to approximately US$20 million, as compared
with approximately US$289 million (adjusted by KEFI from the then-published US$235
million to include assumed working capital and financing costs) when KEFI assumed
Project control in 2014. The key arrangements that have reduced the residual requirement
are:

o Having first expanded the resource base by some 50% and re-designed the open pit,
KEFI then introduced targeted selective mining to down-scale the mining operation
and improve head-grade:

§ total tonnage movement has been reduced from the 2012 DFS 160 million tonnes (
17Mt of ore and 143Mt of waste) to 140 million tonnes (15Mt of ore and 125Mt waste).

§ head grade has been increased from 1.8 grammes per tonne (“g/t”) to 2.1g/t.

o introducing contract mining, whereby Ausdrill will fund the mining fleet, which
transfers some US$50 million of project capital into operating costs which is paid
per tonne delivered.

o arranging project funding with Oryx (debt-style) and the Government of Ethiopia(
project-equity):

§ Oryx proposes to fund all on-site plant and infrastructure (other than that provided
by the Mining Contractor) up to a limit of c. US$100 million as well as transaction
expenses and debt-service costs during the 30-month grace period for construction
and start-up of up to c. US$40 million.

§ The Government proposes to fund all off-site infrastructure up to a limit of US
$20 million.

§ KEFI guarantees that it will meet any shortfall of TKGM funding for the development
of the Project as required. The precise amount of such funding (if any) is expected
to become clear after taking into account actual progress as regards cost and schedule
over the 2018-2019 construction period.

· Having finalised the structuring of the proposed project finance, KEFI can now
move to arrange the residual capital requirement. Key considerations include the
following:

o Whilst the Company has sown the seeds for an institutional equity raising at the
parent company level, KEFI can now bring to a head its discussions with potential
Project level, TKGM, investors.

o Additional project-level equity investment may minimise the dilution of KEFI shareholders’
beneficial interests. A project-equity transaction on the same terms as with the
Government would imply a project valuation of c. US$100 million and KEFI would expect
to retain an equity ownership interest in the order of 55% in the Project.

o KEFI is in discussion with several Project level investors.

o KEFI has deliberately not yet committed to any product offtake arrangements as
that aspect may now form a useful part of arranging the residual funding requirement.

· The financing remains subject to completion of due diligence, regulatory approvals
and execution of binding documentation.

**Project Plans**

· Oryx has agreed to expand its proposed finance facility from US$135 million to
US$140 million as part of the set of arrangements to allow for an increase in ore
processing capacity from 1.5 to 1.7 million tonnes per annum (“Mtpa”) to 1.9 to 
2.1 Mtpa, with the upper and lower limits depending upon the hardness of the ore.

· Oryx’s proposed support is welcome as the increased processing capacity has always
been sought after, but has been a matter of keeping the cost and funding thereof
within manageable levels. Taking the plant capacity back to that proposed in the
2012 DFS will now provide KEFI (through project company TKGM) with the opportunity
to achieve the following:

o Mitigate against the build-up of ore stockpiles to what otherwise would have exceeded
two years of production.

o allow the flexibility to mine at a faster rate as and when warranted in the open
pit as well as from what we expect will come from satellite deposits which have 
been the subject of further positive evaluation recently.

o cater for underground ore from the already reported underground resources.

· The capital required for the capacity increase is being minimised by offsetting
against savings in other aspects of the construction budget. Notably, KEFI, Lycopodium
and Oryx have agreed an organisation plan which allows us to convert the arrangement
with Lycopodium from a (necessarily more expensive) fixed price lump sum arrangement(
EPC) to an open book cost-based arrangement with incentivisation built around target
cost and schedule (incentivised EPCM). One organisational aspect is the installation
of an added layer of management control via the appointment of an independent Client
Representative Engineer to oversee construction under guidance from KEFI’s project
management team, and to independently certify progress claims.

· The community preparations progress to the stage where all data has been tabled
so that the Government can trigger the resettlement this year, synchronised with
the closing of TKGM’s development finance package.

Gold & Minerals Ltd, an incorporated joint venture with 60%-partner ARTAR, Kingdom
of Saudi Arabia

· New Regulatory Regime to be announced by the Saudi Government: The newly created
Energy, Industry and Mineral Resources Ministry is preparing new mining policies
and regulations – intended to overhaul the mining industry with a view to facilitating
growth and making it the third pillar of the Saudi economy.

· Portfolio of Licence Applications: G&M awaits these regulatory clarifications 
and, in the meantime, has upgraded its portfolio.