# KEFI Minerals plc Quarterly Operational Update

- Link: https://www.directorstalkinterviews.com/kefi-minerals-plc-quarterly-operational-update-3/412748846
- Published: 2018-04-05T07:23:58+01:00
- Author: Giles Arbor

**KEFI Minerals Plc** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Kingdom of Saudi
Arabia and the Federal Democratic Republic of Ethiopia, has today provided an operational
update for the period from 1 January 2018 to 31 March 2018.

This quarterly operational update encompasses the activities of KEFI Minerals (Ethiopia)
Ltd (“KME”) and Tulu Kapi Gold Mines Share Company Limited (“TKGM”) in Ethiopia 
and Gold & Minerals Ltd (“G&M”) in Saudi Arabia.

**Ethiopian Government**

· The new Prime Minister Dr. Abiy Ahmed was appointed on 2 April 2018 and is also
Chairman of the ruling federal coalition party and of the party representing Oromia,
in which Tulu Kapi is located. Dr Abiy Ahmed was formerly Vice President Oromia 
Regional Government.

· KEFI expects that the Government will maintain its determination for Ethiopia 
to remain within the world’s top 10 growth countries, where it has been ranked for
a remarkable 15 years in a row. The Company also expects that the strong support
for our project will now be further reinforced.

· Throughout the recent Government transition, KEFI and joint Government-KEFI company
TKGM have been maintaining communications with the Ministries and Government agencies
at federal, regional, zonal and local levels and we can now re-intensify the collaboration.

**Financing**

· Good progress continues with a full consortium having been assembled which is 
focused on raising all development funding at the project-level. We now plan a $
150 million bond issue for the debt side (compared to $140 million previously) to
include some extra cash reserves. This is in addition to c. $40 million of project-
level equity, which includes the Government’s $20 million commitment. These figures
exclude the already-invested project equity of $60 million.

· The planned project consortium now includes the project contractors Lycopodium
and Ausdrill, KEFI partner the Government of Ethiopia and, under Non-Disclosure 
Agreements, the Bond Arranger and one or more of the several potential project equity
investors discussing terms.

· The proposed project financing structure has the following main elements:

o KEFI Minerals plc to remain operating partner in:

— G&M in Saudi Arabia alongside ARTAR, and

— KEFI Ethiopia alongside a new shareholder in KEFI Ethiopia.

o KEFI Ethiopia to remain majority shareholder of TKGM in which the Government is
co-shareholder

o Both KEFI Ethiopia and G&M to trigger exploration programs later this year on 
a recently expanded land package targeting both gold and copper on “Tulu Kapi-style”
gold mineralisation as well as large Volcanic Massive Sulphide systems (“VMS”). 
These exploration programs are to be launched when the new regulations pass in Saudi
Arabia and when Tulu Kapi’s development has been triggered in Ethiopia.

**Timetable for Tulu Kapi financing and development**

· Various project “pre-works” are underway:

o the Ethiopian Roads Authority (“ERA”) has widened and sealed the arterial road
to within 12 km of Tulu Kapi as a prelude to upgrading the side roads to the project
site as part of the Government’s project-equity earn-in. ERA has committed to complete
the upgrade by late 2019 to support the project’s operational requirements. Construction
does not need any new roads;

o the Ethiopian Electric Power Company (“EEPCO”) has confirmed it is planning to
install the power connection from the main transmission line by late 2019, to meet
operational requirements; and

o the Oromia Regional Government and TKGM have agreed the joint preparation of the
new host lands for the community and await clearance to proceed under new Government
teams.

· Various other pre-works have been completed and are planned to serve schedule-
efficiency as from the end of the wet season in Ethiopia in June-September, when
major works can commence.

· Subject to continuing satisfactory progress, project finance drawdown is targeted
to match the commencement of major works. In the meantime, due diligence, documentation
and formalities continue and appropriate updates will be provided.

· Project commissioning is expected to commence by the end of 2019.

**Exploration**

· An aggressive exploration program is scheduled to begin in H2-18 to tackle a recently
expanded exploration land-package now approximating 3,000 sq km. This is the aggregate
of our existing and applied-for position in Ethiopia (100%-owned) and Saudi Arabia(
40%-owned). The commencement of the program relies on the Governments in both country’s
formalising certain licences as scheduled.

· The targets comprise satellite gold deposits under or within trucking distance
of Tulu Kapi along with a set of VMS copper and gold targets in Ethiopia (near Tulu
Kapi) and in the Wadi Bida Mineral Belt (“WBMB”) along strike of Hawiah.

· One area applied for contains significant historic drill intercepts such as 19m
at 9.21 g/t Au and 21.8m at 6.1 g/t Au, trench results of 28.3m at 8.7 g/t Au. Based
on KEFI’s database, Saudi Arabia’s WBMB contains many large gossans with recorded
mineralisation along with evidence of base metals at depth and has a surface expression
twice the size of the Bisha Belt in Eritrea.

· It is notable that, notwithstanding that few international explorer-developers
have yet to enter the Arabian Nubian Shield (“ANS”), the ANS region has more than
doubled its gold production in the last 5 years from c. 50 tonnes of gold in 2013
to more than 100 tonnes in 2017.

· The goals for KEFI’s exploration program are:

o to support and expand Tulu Kapi production from the initial 140,000 oz pa;

o to justify and support the start-up of Jibal Qutman in Saudi Arabia, to generate
cash flow for self-funding a large exploration program; and

o to capitalise on the Company’s pole position in the fast-expanding minerals sector
of the ANS in both gold and copper

**Financial Models and Projections**

· The financial models in the data rooms are consistent with recent Company guidance,
with the Base Case (assuming $1,300/oz) indicating a payback of approximately 3 
years, an EBITDA of over $77M pa and a post-debt NPV of $109M at construction start
and $179M at production start (100% of project at a discount rate of 8% after tax).
The proposed project finance has a tenure of 9 years.

· Projected Production Costs are $712/oz, All-in Sustaining Costs $803/oz and Total
Costs Including Depreciation and Amortisation $984/oz.

· The upside leverage is indicated by 10% increase in gold price from the Base Case
of $1,300/oz increasing NPV by 51%.

**Investor Event & Webinar**

· The Company will host a live webinar at 4pm BST on Wednesday 11 April 2018 which
can be accessed via: www.brrmedia.co.uk

· Listeners are encouraged to submit questions by emailing: questions@brrmedia.co.
uk. The webinar will subsequently be available on the Company’s website at http://
www.kefi-minerals.com/news/webcasts.

Share on:
