# KEFI Minerals plc Q4 2018 Operational Update

- Link: https://www.directorstalkinterviews.com/kefi-minerals-plc-q4-2018-operational-update/412765769
- Published: 2019-01-29T07:17:24+00:00
- Author: Giles Arbor

**KEFI Minerals plc** ([LON: KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Kingdom of Saudi
Arabia and the Federal Democratic Republic of Ethiopia, has today provided its quarterly
operational update.

This update encompasses the activities of KEFI Minerals (Ethiopia) Ltd and Tulu 
Kapi Gold Mines Share Company in Ethiopia, and Gold & Minerals Ltd in Saudi Arabia
for the period from 1 October 2018 to 31 December 2018, together with more recent
developments where appropriate.

Since 1 October 2018, any material events have been reported in separate announcements
which are referred to below, along with explanatory updates on those and other related
matters.

**Tulu Kapi Gold Project in Ethiopia**

_Government Clearance of Community Resettlement_

On 8 October 2018 the Federal Government approved the finalised community resettlement,
livelihood restoration and community development plans. The Regional Government 
asked TKGM to be prepared for community resettlement to start as early as possible
in Q1 2019.

As at the date of this announcement, the Regional Government is not yet ready to
trigger resettlement due to recent changes to its administration and security structure.
However, it has stated that it still wants KEFI/TKGM to be ready to do so later 
in this current quarter.

_3 January 2019 and 25 January 2019: Tulu Kapi Project Updates_

The required Federal Government consents have all been received from all relevant
Federal agencies other than that the project finance structure set out with the 
central bank is awaiting endorsement by the Prime Ministry. KEFI does not anticipate
a problem with this administrative process. The Prime Ministry and Government at
all levels have always been supportive of the Project as a priority for the community,
the Oromia Region and Ethiopia as a whole.

Tulu Kapi Project site activities: a three-month program of land clearing and geotechnical
drilling for the design of infrastructure foundations has been completed. Site preparation
programs continue.

Tulu Kapi Project Development Planning: principal on-site project contractors Lycopodium
and Ausdrill plan for the 24-month development schedule. Principal off-site project
contractors Ethiopian Electrical Power Corporation and Ethiopian Roads Authority
are preparing design and tender documents for off-site infrastructure.

KEFI/TKGM management: continues to be built up for development and operations.

**Saudi Exploration Project**

_30 November 2018: Saudi Exploration Licence Renewed for Hawiah VMS Belt_

This licence was first issued in 2014 and some exciting results were produced from
initial surface and geophysical surveys of a 6km-long surface-exposed mineralised
system (gossan) containing gold and copper. The authorities have recognised that
because we had to stop work for over two years pending their regulatory review and
until the social licence was established on normal terms, the authorities have now
renewed the Hawiah licence and the exploration team is arranging to recommence field
work.

In addition, we have lodged exploration licence applications over the majority of
the 120-kilometre long Wadi Bidah Mineral District, which has twenty-four recorded
VMS (Volcanogenic Massive Sulphide) systems of which Hawiah is one.

**Corporate and Project Finance**

_30 October 2018: Secured Convertible Loan Facility_

A longstanding shareholder agreed to provide the Company an expanded working capital
facility to support preparations for TKGM development.

_17 December: General Meeting of Shareholders_

KEFI Shareholders approved the Secured Convertible Loan Facility.

Tulu Kapi Project Equity:

o the shareholders of Project subsidiary TKGM (KEFI and the Ethiopian Government)
approved the admission of Ethiopian Project equity investor ANS Mining Share Company(“
ANS”) as an additional TKGM shareholder;

o ANS confirmed its equity subscription at the maximum in the previously reported
range, being the Birr-equivalent of US$38 million, upon the relevant Government 
consents being completely finalised and the community resettlement being finally
approved.

o KEFI’s equity in TKGM is expected to be 50.1% with the balance being Ethiopian
Government (via the Ministry of Finance and Economic Cooperation) and financial 
institutions (via ANS).

Tulu Kapi Project Bond/Lease Proposal:

o the Independent Technical Expert signed the Project due technical diligence reports;

o compliance and due diligence procedures remain to be complied with during and 
after drafting of full detailed documentation following all government clarifications
being received

**Project Economics**

The current spot gold price of approximately $1,300/oz, forward market gold prices
and analysts’ long-term forecasts support the Company’s base case projections of
US$1,300/oz.

TKGM projected financial statistics, based only on extracting its one million ounces
of ore reserves within the planned open pit section of the Project, remain in accordance
with previous guidance and as supported by the project feasibility studies and updates:

o shareholders’ invested capital of c. US$120 million

o NPV after debt and after tax, at 8% discount rate of:

§ US$115 million (£87 million) for 100% and US$57 million (£44 million) for 50.1%
at start of construction, and

§ US$192 million (£147 million) for 100% and US$96 million (£73 million) for 50.1%,
at start of production two years later

o Estimated average TKGM EBITDA of US$73 million (£55 million) over 8 years and 
annual debt-service costs during production of US$27 million (£21 million) over 
8 years

**Regulatory and Security Environment**

**Ethiopia**

Ethiopia is Africa’s highest growth country and has, over the past six months, instituted
positive progressive and transformative reforms on many levels throughout the country.

Yesterday the Federal Ministry of Mines, Petroleum and Natural Gas announced that
it had drafted a new Proclamation for regulation of the mining industry, particularly
with an eye to stimulating growth. The Ministry’s statement referred to the introduction
of investment incentives and the removal of obstacles.

The security situation for our Project in Ethiopia is considered better than most
mining sites on the continent and KEFI/TKGM has strong government, business and 
community support, having earned and maintained strong social licence at Tulu Kapi.

**Saudi Arabia**

Saudi Arabia has announced new industry policies and has yet to release the details
of the associated regulations. These changes aim to spur development of the minerals
sector.

Yesterday the Saudi authorities released from a year-long detention the head of 
the group of companies which owns the only other major gold development-ready deposit
in Ethiopia.

The security situation for our projects in Saudi Arabia, as with our sites in Ethiopia,
is considered fine and also derives largely from G&M (the Project company of KEFI
and partner ARTAR) ensuring and maintaining strong social licence with its local
communities.

**Investor Webinar**

The Company will host a live webinar at 3.30pm GMT on Thursday 31 January 2019 which
can be accessed via:

http://webcasting.brrmedia.co.uk/broadcast/5c4f149ea0c50933d2710da5/5c4f1a46a7461f9c6500025b
and also through www.brrmedia.co.uk

Listeners are encouraged to submit questions by emailing: questions@brrmedia.co.
uk

The webinar will subsequently be available on the Company’s website at http://www.
kefi-minerals.com/news/webcasts.