# KEFI Minerals plc Q1 2019 Operational Update

- Link: https://www.directorstalkinterviews.com/kefi-minerals-plc-q1-2019-operational-update/412772177
- Published: 2019-04-16T07:28:00+01:00
- Author: Giles Arbor

**KEFI Minerals plc** ([LON: KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Federal Democratic
Republic of Ethiopia and the Kingdom of Saudi Arabia, is pleased to provide its 
quarterly operational update.

This update encompasses the activities of KEFI Minerals (Ethiopia) Ltd and Tulu 
Kapi Gold Mines Share Company in Ethiopia, and Gold & Minerals Ltd in Saudi Arabia
for the period from 1 January 2019 to 31 March 2019, together with more recent developments
where appropriate.

Since 1 January 2019, any material events have been reported in separate announcements
which are referred to below, along with explanatory updates on those and other related
matters. It has been a very important quarter for the Company.

**Tulu Kapi Gold Project in Ethiopia**

**Government:**

· Prime Ministerial go-ahead for the Project: Dr Abiy Ahmed, Prime Minister of Ethiopia,
issued the remaining instructions for the Project go-ahead as announced on 5 March
2019.

· Clearance of Community Resettlement: The Ethiopian Federal Government has approved
the resettlement plan and the Local Government has now approved the compensation
calculations. The Regional Government has begun triggering the consecutive steps
of the resettlement programme in consultation with the community and TKGM. The current
focus is on the selection of individual land-parcels, house locations and training.
This is expected to lead to compensation payments in July 2019 for the phase one
move of some 60 households, with the preparations being completed in the meantime.

· Clearance of other administrative matters: The Federal Government consents have
all been received from relevant Federal agencies other than some final aspects of
the Project finance structure which has now been endorsed by the Prime Ministry.
Details are being documented with the central bank which has issued approvals for
capital ratios, hedging and bank accounts and we expect residual matters to be resolved
shortly.

**Project Financing Activities:**

· TKGM project development funding:

o Project equity of US$58 million (Ethiopian Birr equivalent) has been committed
from:

* Ethiopian Government project equity of US$20 million (Ethiopian Birr equivalent),
as detailed in the announcement of 25 January 2019; and

* Ethiopian private sector partner ANS Mining Share Company Limited equity of US
$38 million (Ethiopian Birr equivalent): injection of the first equity instalment
of US$11.4 million will be upon satisfaction of certain conditions, as detailed 
in the announcement of 8 April 2019.

* The plan will result in KEFI holding 81% of KME which will hold 59% of KGM. KEFI
beneficial interest in TKGM thus being 45%.

o These project equity figures ignore past investment of c. US$60 million.

o The mandated US$160 million bond issue preparations continue.

**Tulu Kapi Project development preparations:**

· Project development planning:

o Principal on-site Project contractors Lycopodium and Ausdrill have re-affirmed
the 24-month development schedule and the 18-months thereof that commences in Q4
2019, after the wet season and phase one community resettlement. In the meantime,
various engineering and contractual tasks are in process including detailed scheduling
and updating of front end engineering and design.

o Principal off-site Project contractors Ethiopian Electrical Power Corporation 
and Ethiopian Roads Authority have had budget approvals for their works and are 
preparing their sub-contractor tender documents for off-site infrastructure. Their
work has started because their deadlines are of a critical path nature to allow 
plant commissioning to commence in Q4 2021.

o The preferred transport contractor is finalising route surveys for deliveries.

**KEFI Corporate**

**Funding**

* £969,000 equity placing completed, as announced on 21 February 2019.

* Initial £2 million working capital loan facility (convertible at no less than 
2p), as announced on 30 October 2018, not yet utilised.

* Project management and Project finance costs:

· continue to be paid by KEFI as part of its Project equity investment into TKGM.
Some of this will be paid to service providers in KEFI shares convertible at no 
less than 2p (see announcement 28 November 2018); and

· will be paid by TKGM directly (instead of by KEFI) once its equity subscription
funds become available in US$;

* Once TKGM becomes financially self-sufficient, KEFI-borne direct costs will contract
back to c.£1 million p.a. (plus any commitments to exploration as it is started-
up in parallel with construction at Tulu Kapi).

* Capital inflows to KEFI are available under the working capital facility (maximum
of up to £4 million, convertible at no less than 2p) and some cost-recoupments (
estimated at £2 million) at full finance closing for TKGM.

o Tulu Kapi Project economics:

**Financing refinements:**

· The latest Project finance plans provide for equity-funding of the first six of
a twenty-four-month program. The important consequence of this is that cash can 
build up before first lease-payment i.e. cash can build to a projected c. US$80 
million from a projected c. US$40 million.

· Likewise, gold in ore stockpiles is also projected to increase, providing further“
margin of safety”.

* TKGM projected financial statistics (as announced on 8 April 2019):

· Based only on extracting its one million ounces of ore reserves within the planned
open pit section of the Project, projections at US$1,300/oz gold price remain in
accordance with previous guidance, as supported by project feasibility studies and
updates:

o shareholders’ aggregate invested capital of c.US$120-130 million including past
and additional investment;

o NPV after debt and after tax, at 8% discount rate of:

* US$117 million (£90 million) for 100% and US$53 million (£40 million) for KEFI
beneficial interest of 45% at start of construction, and

* US$193 million (£148 million) for 100% and US$87 million (£66 million) for KEFI
beneficial interest 45% at start of production two years later; and

* Estimated average TKGM EBITDA of US$72 million (£55 million) over 8 years and 
annual debt-service costs during production of US$28 million (£22 million) over 
8 years.

**Ethiopian Exploration:**

· Ethiopia Regulatory Improvements:

o During 2018 Ethiopia emerged from two years of states of emergency and is undergoing
a rapid and progressive transformation. The Ethiopian Government continues to push
through an overhaul of regulations for various prioritised sectors including mining,
to expedite development.

o TKGM is the first major development for decades and has been honoured to be invited
to be the industry representative for the Ethiopian Extractive Industries Transparency
Initiative.

· Mobilisation into field for exploration at Tulu Kapi and for district exploration:

o TKGM will start examining development scenarios for the 5-6 g/t underground deposit
once construction of the open pit is underway.

o KME’s exploration programs over its 1,900 sq km Tulu Kapi district areas will 
also trigger when major works start at Tulu Kapi. In the meantime, reconnaissance
has commenced of the various already-drilled mineralised zones for follow-up.

**Saudi Exploration Project**

· Saudi Regulatory Improvements:

o The new Saudi Government continues to overhaul of regulations for the extractive
industries, to expedite development of what it targets to be the third pillar of
its economy.

o G&M has, over the past few years, positioned itself as the only long-standing 
explorer with a large exploration portfolio and non-Government-controlled.

· Mobilisation into field at Hawiah:

o Hawiah is part of the 120 km long Wadi Bidah Mineralised District (“WBMD”) that
is under licence or application for G&M. It contains 24 mapped Volcanic Massive 
Sulphide (“VMS”) systems for exploration, which will start in Hawiah.

o The exploration team is in the field conducting trenching and geophysical surveys
to follow up high-resolution multi-spectral satellite imagery analysis, in preparation
for initial drilling in Q3 2019 of high priority copper-gold targets.

· The Jibal Qutman Project: this gold discovery of G&M sits within the regulatory
authorities as an application for a mining licence and has been relegated in short
term importance for G&M vis a vis WBMD.

· An announcement will be made providing details covering this and related programmes
in due course.