**KEFI Gold and Copper plc **([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold and copper exploration and development company focussed on the Arabian-
Nubian Shield, with projects in the Federal Democratic Republic of Ethiopia and 
the Kingdom of Saudi Arabia, has announced that, having launched the development
of the Tulu Kapi Open Pit Mine and Processing Facility, it will now commence detailed
planning for the development of its second mine, the Tulu Kapi Underground Mine 
following the results of a positive standalone Preliminary Economic Assessment. 
The addition of the Tulu Kapi Underground Mine is expected to raise combined steady-
state production at Tulu Kapi to c.180,000 oz of gold per annum.

This decision follows the recent updating of the Tulu Kapi Preliminary Economic 
Assessment based on already-established JORC compliant Mineral Resources beneath
the open-pittable Ore Reserves.  The Underground Mine development schedule will 
target decline development to start as the Open Pit mine is commissioned and starts
production in mid-2028.  The activities in its first development year would include
the establishment of drilling platforms for both infill drilling and extensional
drilling plus trial production. 

At Tulu Kapi, a potentially high-grade, high-value, large system remains open at
depth and, as indicated in the Company’s announcement on 19 March 2026, will be 
tested through the reinitiation of exploration activities. The last drill hole at
the northern limit of the presently delineated underground mining domain returned
90m at 2.8g/t gold (TKBH_293, from 364m to 454m, downhole width, announced 4 March
2017), highlighting the prospectivity of the region.

The PEA supersedes the indicative underground assessment referred to in the Company’s
announcement of 18 March 2025, which contemplated recovery of approximately 200,000
oz from c.1.5 Mt.  The increase to 2.38 Mt and c.253,000 oz of contained gold reflects
a revision of the cut-off grade.

**Highlights of the 2026 Preliminary Economic Assessment of Tulu Kapi Underground
Mine are:**

·    Application of a cut-off grade of 1.45 g/t based on an assumed gold price of
US$2,350/oz;

·    Post-tax NPV 5% of c.US$274.1 million and IRR of 220%, with payback of 9 months,
on a standalone incremental basis at a gold price of US$2,350/oz;

·    Preliminary underground mining inventory of 2.38 Mt at 3.30 g/t Au, comprising
Indicated Mineral Resources, containing approximately 253,000 oz of gold;

·    The updated schedule reflects a steady-state stoping production target of approximately
500,000 tpa, with the objective of maintaining two developed levels ahead of active
stoping; underground ore is incremental and blended with open pit feed based on 
a 20% increase in plant throughput above nameplate capacity of c.2.0 Mtpa. Associated
capital expenditure is factored in;

·    Recovered gold is expected to be c.237,000 oz, at an assumed metallurgical 
recovery of c.94%, to complement open pit production of c.985,000 oz, for a combined
1.2M oz of gold recovered over 8 years;

·    Pre-production development capital is estimated at US$8.09 million with the
maximum cash drawdown required for the Underground Mine estimated to be c.US$10.5
million, the timing of which would be optimised in 2028 as the Company approaches
production start-up at Tulu Kapi, and is expected to be funded from Open Pit Mine
operating cash flow with no new equity assumed;

·    At assumed gold prices of US$3,000-5,000/oz Au, combined open-pit-plus-underground
estimated AISC has been updated to c.US$1,100-1,300/oz, which reflects the impact
of Government royalties at higher gold prices.

·    Material depth extension potential beyond the current mining inventory, to 
be tested by the extensional drilling programme scheduled to commence in 2029.

> **Harry Anagnostaras-Adams, Executive Chairman of KEFI, commented:**
> “_At Tulu Kapi we are in month six of the development schedule to start production
> in mid-2028.  We have procured the fabrication of plant at international specialty
> workshops, and at site we remain focused on community resettlement and mobilisation
> for construction, which is scheduled to accelerate in the imminent dry season._
> _“The PEA confirms that we can now add this second mine at Tulu Kapi using existing
> mineral resources and the existing plant with minor, already considered modifications.
> It is therefore timely to commence a parallel stream of preparatory work for the
> second mine at Tulu Kapi, the Tulu Kapi Underground Mine._
> _“Based on existing mineral resources, this would underpin combined production
> for 7 to 8 years of 180,000 oz of gold per annum. However, the ore body is open
> and there is potential for large high-grade zones at depth.”_

**Next Steps and Milestones**

·    Engineering Works for the Underground Mine – commencing immediately, targeted
for completion in Q4 2027;

·    Infill and extensional drilling from underground platforms – 2029, with an 
updated Mineral Resource estimate targeted for 2029;

·    Decline development – commencing as the Open Pit Mine is commissioned in mid-
2028, with trial production in the first development year; and

·    First stope ore and ramp-up to steady state – 2029.

**Cautionary Statement Regarding the Preliminary Economic Assessment**

The PEA is preliminary in nature. The preliminary underground mining inventory of
2.38 Mt at 3.30 g/t Au is not an Ore Reserve and has not been demonstrated to be
economically viable in accordance with the JORC Code. It includes Mineral Resources
classified as Inferred, which are considered too speculative geologically to have
the economic considerations applied to them that would enable them to be categorised
as Ore Reserves. There is no certainty that the results of the PEA will be realised,
that the mining inventory will be converted to Ore Reserves, or that the production,
cost or cash flow outcomes described in this announcement will be achieved.