# KEFI Gold and Copper Reports Positive Developments at Tulu Kapi

- Link: https://www.directorstalkinterviews.com/kefi-gold-and-copper-reports-positive-developments-at-tulu-kapi/4121149017
- Published: 2024-03-25T07:06:42+00:00
- Author: Ethan Davis

**KEFI Gold and Copper** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
has reported further positive developments at the Company’s high-grade Tulu Kapi
Gold Project in Ethiopia, as it prepares for full launch in H1 2024.

As previously reported, all of the required development budget of US$320 million(
exclusive of the historical equity investment of c. US$100 million) has been sourced
at the subsidiary level. We are pleased that, following the final approvals from
the lead-bank, all other parties triggered their formal approval processes which
are now all advancing, notably including progress with both the co-lending bank 
and the local equity-capital investors.

A positive development is that recent regulatory changes have facilitated the improvement
to the equity funding structure which has lowered overall finance costs. The regulatory
changes of note were the foreign exchange exemptions, the increase in the maximum
permissible ratio of debt to equity from 70:30 to 80:20 and the deeming as foreign
direct investment the re-investment of the local currency (Ethiopian BIRR) retained
earnings of multi-national corporations (“MNC”) into new business sectors.

Within the development capital budget of US$320 million, US$100 million was to be
provided through the issuance of two types of Equity Risk Notes (“ERN”), one type
for MNC’s with no operations in Ethiopia and another lower-cost ERN for those with
accumulated retained earnings in Ethiopian operations. The Company is pleased to
report that it can now focus on the lower-cost ERN – fixed at 12% per annum. These
notes remain repayable in cash from operations or, as a fall-back, in KEFI equity(
at KEFI’s election), convertible in year 4 (being year 2 of full production) at 
the then prevailing KEFI share price.

The Company can confirm a longstanding and large MNC investor in the ERN has now
received initial board approvals. All syndicate members have agreed a schedule for
all remaining pre-launch tasks including their respective formal approvals ahead
of full financial close mid-2024.

**Comment by Harry Anagnostaras-Adams, KEFI Gold and Copper Executive Chairman:**

“_I am delighted to report the initial board approval of a major local equity-capital
provider. And it is especially pleasing that the instrument designed for this transaction,
the Equity Risk Note, has been streamlined under the lower-cost approach. Our modelling
and production profile for this high-grade open pit gold mine, based on a gold price
of US$1,864/oz (versus current spot of US$2,170/oz), shows sufficient cash will 
have been generated at the proposed time of repayment to repay these ERN in cash
at the time they fall due._

_“When combined with the credit committee approved US$95 million debt from lead 
bank Eastern and Southern Trade and Development Bank (“TDB”) and the Ethiopian Federal
and Regional Governments’ US$20 million commitment, with the potential to increase
to US$40 million, this accounts for US$215 million to US$235 million._

_“I can also advise the Company has received confirmation from the co-lender Africa
Finance Corporation (“AFC”) that its approval processes are underway and progressing
well for its-intended US$95 million investment, which would provide the balance 
of the required funding for Project launch._

_“All syndicate members are supportive and are working to ensure final documentation
is entered into by mid-2024 to enable full Project launch and drawdown of funds.
I look forward to providing further updates as appropriate.”_

**Additional Project Updates**

Preparing for resettling the local community:

·    The planned extra security protection is being implemented as the field activities
increase; and

·    The lenders’ independent security adviser will monitor safety of implementation
over the next few months as we prepare to trigger Project launch mid-2024.

Preparing to trigger procurement and construction:

·    We have completed the detailed work packages for tendering local sub-contractor
work;

·    These are based on the FEED (Front-End Engineering and Design) also completed
by principal contractor Lycopodium; and

·    The mining contractor PW Mining is now seeking its Ethiopian regulatory clearances
for its arrangements with its own financiers and OEM’s (Original Equipment Suppliers).

Establishment and deepening of operational banking support and working capital sources:

·    Ethiopia’s largest bank, the Government-owned Commercial Bank of Ethiopia, 
has established onshore Ethiopian BIRR and US Dollar Project operating accounts 
and is engaging on providing various working capital facilities as we advance;

·    Ethiopia’s largest non-Government bank, Awash Bank, has done likewise and has
also approved a working capital facility for TKGM. It will initially be drawn to
Ethiopian BIRR 35 million (approximately £480,000) and can expand as the launch 
proceeds; and

·    A major international bank, Citibank, is in discussions about opening the offshore
operating accounts in London, in accordance with the foreign exchange exemptions
granted by the central bank, the National Bank of Ethiopia.

Conditions Precedent to Signing Definitive Detailed Formal Agreements (“Detailed
Documentation”):

·    The aforementioned processes are designed to be progressed by the end of May
2024 to the stage that warrants signing of Detailed Documentation between all syndicate
members; and

·    All conditions precedent to signing are typical for a transaction of this nature.