# KEFI Gold and Copper on track to launch Tulu Kapi development in October 2025

- Link: https://www.directorstalkinterviews.com/kefi-gold-and-copper-on-track-to-launch-tulu-kapi-development-in-october-2025/4121218385
- Published: 2025-09-30T07:22:00+01:00
- Author: Amilia Stone

**KEFI Gold and Copper plc** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Democratic Republic
of Ethiopia and the Kingdom of Saudi Arabia, has announced its unaudited interim
results for the six months ended 30 June 2025.

**Highlights**

·    Significant progress made in the period with the Company’s Tulu Kapi Gold Project
and KEFI is on schedule to begin the full development programme in October 2025.

·    The final Tulu Kapi budget of US$340 million and its finance plan remain as
recently announced, with project debt of US$240 million and equity risk capital 
planned to be issued almost entirely by KEFI subsidiaries for US$100 million.

·    The Boards of both co-lending banks and of the Group companies have approved
and are expected to sign the formal commitment of the project loan facilities within
the coming week.

·    The construction contracts have been finalised for signing upon drawdown of
equity.

·    KEFI will now focus on providing details to, and entering into formal arrangements
with, the equity risk capital investors. Non-binding proposals received for the 
equity risk capital currently exceed the US$100 million required.

·    The detailed financing documentation contains standard conditions such as change
of control and conditions precedent for a transaction of this nature, including 
Government confirmations and approvals, and signing will continue in the appropriate
sequence leading up to issuing the notice to proceed to principal contractor Lycopodium.

·    In the meantime, works will continue to escalate at site, in particular with
the community resettlement, funded by working capital facilities pending the project
finance drawdowns of equity and then debt.

·    Saudi projects continue to progress with:

o  Substantial increases and upgrading of the Mineral Resource Estimates for both
the Hawiah deposit and the nearby Al Godeyer deposit.

o  Material upgrade to Jibal Qutman Gold Project Mineral Resources.

o  GMCO/ARTAR-Hancock winning tender for Al Hajar North Exploration Licence, with
licence areas increased from 1,300 km^(2) to >2,200 km^(2) for GMCO-led exploration
programmes.

The interim results for the Group cover the activities of KEFI Minerals (Ethiopia)
Ltd, Tulu Kapi Gold Mines Share Company in Ethiopia, and Gold & Minerals Ltd in 
Saudi Arabia.

The Tulu Kapi Gold Projectis currently 95% beneficially owned by KEFI through KEFI’s
wholly-owned UK subsidiary KME. The Hawiah Copper-Gold Project, the Jibal Qutman
Gold Project and other Saudi projects are held by GMCO in which KEFI currently has
a 15% interest.

Both TKGM and GMCO are being developed by KEFI and its partners as separate operating
companies so that each can build a local organisation capable of developing and 
managing long-term production and exploration activities, as well as exploit future
development opportunities.

**Tulu Kapi**

Significant progress was made in the period and KEFI is on schedule to begin the
full development program of Tulu Kapi in October 2025. We have approved and expect
to sign shortly the formal commitment of the project loan facilities. And the construction
contracts have been finalised for signing upon drawdown of equity which can now 
be finalised amongst the assembled local and regional investors.

_Project financing status_

As previously announced, the Tulu Kapi project has an updated capital budget of 
US$340 million, a small increase from the previous 2023 estimate of US$320 million.
This capital is being raised through a US$240 million debt facility and equity-risk
capital issues of US$100 million, which are proposed almost entirely at the subsidiary
level.

·      Debt facility: The expanded facility of US$240 million, which has been formally
offered by the co-lenders and accepted by KEFI and its local subsidiaries, is expected
to be signed within the coming week. Detailed facility and account opening documentation
will then be executed as we complete arrangements with the proposed investors of
equity-risk capital.

·      Equity-risk capital: The US$100 million is being assembled primarily at the
subsidiary company level. A significant portion has already been secured, with US
$20 million from the Government of Ethiopia, US$10 million already invested by KEFI
and c.US$10 million of KEFI share participation post-closing in respect of closing
fees and costs. The remaining US$60 million is currently being finalised and KEFI
has received conditional proposals that exceed this amount. This will be raised 
through a combination of non-convertible preference shares for Ethiopian investors(“
KEFI Ethio Prefs”) issued by one of KEFI’s Ethiopian subsidiaries, an equity risk
note structured as a “Gold Prepayment” or “Stream” from a mining specialist fund,
and the issue of ordinary shares in either of the Ethiopian subsidiaries, priced
on the basis of a TKGM valuation reflecting its status as a funded project. The 
breakdown and details of the finalised equity-risk capital instruments will be published
by KEFI upon commitment and the signing of definitive documentation.

_Project economics_

The life-of-mine projected operating metrics remain consistent with recent guidance,
including all-in sustaining costs (AISC) of c.US$1,100/oz and first full year production
of 160koz from the open pit. Annual production is planned to then increase with 
the introduction of initial underground production. Year 1 net operating cash flow
is projected at c.US$200 million at a US$2,500/oz gold price and c.US$300 million
at a US$3,500/oz gold price, from the open pit with processing at nameplate capacity.

_Preparations and future plans_

Site preparations are progressing on schedule, with a focus on both infrastructure
and community relations.

·      Infrastructure: A new all-weather road is nearing completion, and another
access road for heavy loads is scheduled to begin construction within the next two
months. Procurement for the electricity connection is complete, with construction
mobilisation having started.

·      Community and social: The local government, with support from TKGM, is already
implementing the “Resettlement Action Plan”, including the community compensation
programme. The phased approach eases the process for the community and ensures compliance
with international standards.

·      Mining operations: The main mining fleet will be procured in early 2026 and
initial open-pit mining is targeted to begin in mid-2027. While the project will
initially focus on the open pit gold reserve, future plans include underground development
to extend the mine’s life and expand production to a targeted 200,000 ounces per
year.

The project has been designed taking into account both local and international ESG(
environmental, social, and governance) standards and alignment with local stakeholders,
including the community, government, and private sectors. The project is seen as
a showcase for international project finance in Ethiopia, contributing to the country’s
growing gold sector.

**GMCO**

In Saudi Arabia, the Company’s GMCO joint venture continued to make good progress
during the period. In the Wadi Bidah Mineral Belt (“WBMB”), following the start 
of drilling in 2019 three VMS discoveries have subsequently been announced – Hawiah
plus its discoveries at Al Godeyer and Abu Salal.

On 15 February 2025, KEFI announced substantial increases and upgrading of the Mineral
Resource Estimates for both the Hawiah deposit and the nearby Al Godeyer deposit.
The Hawiah Mineral Resource Estimate increased by 25% or 7.3 million tonnes (“Mt”)
to 36.2 Mt at 0.82% copper, 0.85% zinc, 0.64g/t gold and 10.0g/t silver.

In addition, the granting to GMCO of the Umm Hijlan Exploration Licence (“EL”) in
the period has almost doubled the targeted strike length of the Hawiah mineralised
system. Drilling is currently taking place.

Over the coming year, Hawiah development studies will be progressed in conjunction
with drilling programmes to upgrade and expand GMCO’s copper-gold zinc-silver Mineral
Resources in this major VMS district. In addition, the new joint venture between
GMCO/ARTAR and Hancock Prospecting will focus on the recently granted 910km^(2) 
EL over the adjacent Wadi Shwas Mineral Belt parallel to and geologically analogous
with the WBMB.

Separately, GMCO’s Jibal Qutman Gold Project saw a material upgrade in its Mineral
Resources in the period with an increased Mineral Resource Estimate of 37.0Mt at
0.76g/t gold, containing 902,000 ounces of gold, 30.5Mt at 0.76g/t of gold (including
748,000 ounces in the Indicated category). Initial development is expected to be
approved at Jibal Qutman during 2025 focusing on open pit mining the oxide ore and
Carbon-In-Leach (“CIL”) processing. In addition, systematic exploration is ongoing
across the expanded Jibal Qutman tenure to identify further resource potential and
confirm structural controls on recently identified higher-grade gold mineralisation.
Drilling to date has focused only on an 8km long section of the original Jibal Qutman
EL. The full 35km mineralised strike length remains to be tested.

**Board and Management Team**

_KEFI Leadership_

·      Board of Directors: KEFI’s board is led by Executive Chairman Harry Anagnostaras-
Adams and Finance Director John Leach, both of whom have extensive experience in
launching, restructuring and operating natural resource-based companies. The board
also includes three independent non-executive directors with deep industry and Ethiopian
knowledge: Richard Robinson (mining operations), Alastair Clark (environmental and
[sustainability](https://www.directorstalkinterviews.com/sustainability-green-stocks-news)),
and Addis Alemayehou (Ethiopian business and investment).

·      Executive Committee: This committee, which includes Mr Anagnostaras-Adams
and Mr Leach, is responsible for operational policy, organisational development 
and oversight of day-to-day operations and features specialists in key areas: Chief
Operating Officer Eddy Solbrandt (systems and organisational optimisation), Rob 
Williams and Simon Cleghorn (technical due diligence), Norman Green (construction),
and Geoff Davidson (mining engineering).

_Tulu Kapi project-level governance_

The governance and leadership structure for Tulu Kapi is composed of a diverse team
drawn from KEFI and its project-level subsidiaries, with significant participation
from Ethiopian stakeholders.

·      KME Ethiopia Holdings: This entity, which has recently been incorporated 
to own the Group’s shareholding in TKGM, will in due course seek listing on the 
Ethiopian Stock Exchange (ESX), will have a board where KEFI holds the majority,
but which also includes non-executive directors nominated by local investors.

·      TKGM: The board of this main operating company is also majority-appointed
by KEFI, including its Executive Chair, COO, and an operations-focused non-executive
director. Crucially, the Ethiopian government appoints non-executive directors representing
its Federal Sovereign Fund, Ministry of Finance, and the Oromia Sovereign Fund, 
ensuring direct government oversight.

_Tulu Kapi operational and advisory team_

The on-the-ground TKGM operational team is led by Managing Director Simon Cleghorn
and features a mix of international and local expertise, with key roles including
Head of Finance Theron Brand and Head of Government Relations Abera Mamo. The project
also relies on a wide array of specialist advisers for various technical, financial,
and social aspects, including Snowdens (mineral resources), Lycopodium (processing),
and Constellis (security).

_GMCO_

KEFI and its majority partner ARTAR (Al Rashid & Sons LLC) have, over the past 17
years, developed a stand-alone management structure for GMCO in which both shareholders
are represented at the Board level (via the Executive Chairmen of each).

Both shareholders also provide additional support in respective areas of expertise.

**Financial Review**

As at 30 June 2025 the Company had not drawn any working capital facilities other
than small overdraft facilities in Ethiopia. Net assets increased to £41 million
as at 30 June 2025 (30 June 2024: £32,6 million) which reflects the Group’s conservative
accounting policy of writing off all exploration. For instance, GMCO is carried 
at nil book value and TKGM at book value of £40.5 million.

The Company’s comprehensive loss for the period reduced to £3.8 million (H1 2024:
loss of £6.1 million).  This primarily reflected a reduction in the Group’s administration
expenses from £3.3 million in H1 2024 to £2.4 million, a reduction in finance costs
from £1.5 million in H1 2024 to £0.7 million and differences in the amounts accounted
for in relation to jointly controlled entities.

**Shareholder Meeting**

The Company expects to convene a general meeting of shareholders in November 2025
to approve certain elements of the Tulu Kapi project finance package requiring shareholder
approval, such as the debt package requiring approval under KEFI Gold and Copper’s
Articles of Association.  Further details will be announced in due course.