**KEFI Gold and Copper plc** ([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold exploration and development company with projects in the Federal Democratic
Republic of Ethiopia and the Kingdom of Saudi Arabia, has provided its latest quarterly
operational update.

This update encompasses the activities of KEFI Minerals (Ethiopia) Ltd and Tulu 
Kapi Gold Mines Share Company in Ethiopia, and Gold & Minerals Ltd in Saudi Arabia,
for the period from 1 January 2022 to 31 March 2022 (“Q1 2022”).  The Tulu Kapi 
Gold Project is under TKGM (planned to be c. 70% owned by KEFI).  The Hawiah Copper-
Gold Project and the Jibal Qutman Gold Project (“Jibal Qutman”) are under G&M (planned
to be c. 30% owned by KEFI).  Both TKGM and G&M are operated by KEFI.

**Ethiopia**

The security situation has improved enormously in Ethiopia over the past few months,
with the end of the civil war in the country’s northern regions during December 
2021, the lifting of the national state of emergency in February 2022, the agreed
ceasefire in March 2022, and the focus of the security forces having now switched
to the policing of priority areas like the Tulu Kapi district.

Until a few years ago, Ethiopia was one of the world’s top 10 growth countries for
nearly 20 years running and now, having overcome its recent security issues, is 
demonstrating a clear determination to expedite the economic recovery and the pursuit
of its economic objectives.  Tulu Kapi will be the country’s first large scale mining
project for some 30 years and is designed to the highest international standards.
It therefore is imposing many demands on a regulatory system which the Ethiopian
Government is upgrading, under strong Ministerial leadership, determined to build
a modern minerals sector.

During Q1 2022 TKGM reactivated Tulu Kapi project launch preparations and has recently
formally advised the Ministry of Mines of its progress being on schedule and that
it can close project finance by mid-year if the security situation is satisfactory
and if the few remaining regulatory administrative tasks are also completed punctually.

In collaboration with the regulatory agencies at all four levels of the Ethiopian
Government, TKGM is implementing a staged Tulu Kapi project launch, with progress
to date as follows:

·    essentially completed technical and legal due diligence, as directed by senior
lenders’ independent advisers – to satisfy conditions precedent to finance closing;

·    triggered detailed engineering – minimising procurement and construction time;

·    recommenced widespread community engagement, which had been suspended for some
months due to previously reported security incidents;

·    restarted district works which have a quick local impact, such as upgrading
the exploration camp for the construction workforce and re-establishing the nursery
for environmental management programmes.  Some of these programmes were scheduled
for post-launch, but have been brought forward to rebuild stakeholder “safety confidence”
over several months of undisturbed progress in the lead-up to financial close, along
with the requisite independent security assessments;

·    commenced regular independent security monitoring;

·    facilitated the completion of the few remaining regulatory administrative tasks:

o  the Ministry of Mines has now endorsed historical costs up to 2020 of c.US$60
million and is now addressing the remainder, incurred after that date or by other
companies on behalf of TKGM;

o  the Ministry of Mines formally requested to allow re-commencement of exploration
at satellite deposit prospects in the Tulu Kapi district;

o  the central bank now addressing permission for both development banks to be allowed
to lend on the same terms. It has already revised, at TKGM’s request, local restrictions
which effectively blocked modern mining project finance until now – such as the 
working rules for the London clearing account to avoid restrictions of capital controls,
the capital ratio for project debt up to 70/30 debt/equity, the use of gold price
hedging if desired, the use of offshore leasing and the application of market-based
interest rates

·    maintained the project syndicate, triggered final pricing by the principal 
contractors and distributed for review an updated term sheet in respect of the offtake-
linked mezzanine facility, now to involve the senior lenders as well as the metals
trader.

**Saudi Arabia**

On 6 January 2022, KEFI announced an updated Mineral Resource Estimate (“MRE”) for
the Hawiah volcanic massive sulphide (“VMS”) deposit of 24.9 million tonnes at 0.90%
copper, 0.85% zinc, 0.62 g/t gold and 9.81 g/t silver.  This represents a c.30% 
increase in resource tonnage and c.5% increase in grade over the previous MRE.  
As a scale-comparison with the Company’s Tulu Kapi Gold Project, Hawiah’s recoverable
metal is now estimated to be in the order of 2.2 million gold-equivalent ounces 
versus Tulu Kapi’s 1.2 million ounces.

Work at the Hawiah Copper-Gold Project during Q1 2022 has focussed on providing 
data for the Hawiah Preliminary Feasibility Study (“PFS”) and included:

·    a 3,700m reverse-circulation (“RC”) drilling programme aimed at upgrading and
expanding the oxide portion of the Hawiah MRE to an Indicated Resource category 
for open-pit mine planning;

·    trenching across the Camp and Crossroad Lodes to collect bulk samples of the
oxide mineralisation;

·    further metallurgical test work on the sulphide mineralisation to determine
the preferred flowsheets to recover the copper concentrates and zinc concentrates,
as well as the gold and silver;

·    a 1,800 metre geotechnical diamond drilling programme; and

·    a 1,350 metre hydrogeological drilling and pump testing programme.

Two Exploration Licences (“ELs”) located immediately west of the Hawiah EL were 
granted in December 2021.  Initial exploration of these Al Godeyer ELs has confirmed
similar copper-gold mineralisation to the Hawiah VMS deposit and indicated good 
continuity of the mineralised horizon. Exploration during the quarter included:

·    a Self-Potential (“SP”) geophysical survey that defined a continuous anomaly
1.3km in strike and a second, shorter anomaly which correlate well with outcropping
gossans;

·    the presence of gold and copper gossans in all trenches over the main SP anomaly
and the majority of trenches over the second SP anomaly. Rock chips taken during
mapping these trenches confirmed copper-gold mineralisation with grades of up to
1.8% copper and 7.2g/t gold; and

·    RC drilling intersected oxide and transition sulphides down to a vertical depth
of 35 metres in the first six holes – assay results are pending for all drillholes.

The Al Godeyer’s exploration focus is to deliver an initial JORC Mineral Resource
during 2022, with a diamond drilling programme set to commence in early April.

At the Jibal Qutman Project, development planning was re-activated following indications
from the Saudi Arabian Ministry of Mineral Resources that the Mining Licence would
progress in 2022.  Jibal Qutman was KEFI’s first discovery in Saudi Arabia with 
a maiden MRE in excess of 700,000 oz of gold.

**KEFI Group**

The improvement in the local working environment in both Ethiopia (security) and
Saudi Arabia (regulatory) since late 2021 has allowed KEFI to achieve rapid progress
in both jurisdictions during Q1 2022.  Combined with the recently reported excellent
exploration results at Hawiah in Saudi Arabia, KEFI now has a much-improved position
as an early-mover in both countries and with a more balanced portfolio of advancing
projects.

Now having three (not one) advanced projects in two countries places the Company
into a much better risk position than was hitherto the case.

Based on metal prices current at 31 December (note 1 below), the following high-
level statistics illustrate the importance of KEFI’s newly-established position 
across the advanced projects and the two countries:

·    KEFI’s beneficial interest in gold-equivalent mineral resources has grown from
1.2 million ounces in mid-2020 to 2.1 million ounces at the end of 2021 with growth
anticipated for 2022 and subsequent years; 

·    KEFI’s market capitalisation at 0.8 pence per share represents the following:

•     US$18/oz-equivalent on JORC resources;

•     7% of NPV (8%) at current metal prices, 13% on Ethiopia alone and 16% on Saudi
alone;

•     Estimated potential Net Operating Cash Flow (see note 2 below) is £137 million(
c. US$185 million) per annum from the combination of all three development projects
at their targeted start-up production rates.

·    NPV (see note 3 below) for KEFI of its projects has tripled since mid-2020,
at 31 December 2021 metal prices and represents 12p per share in issue (6.5 pence
per share Ethiopia and 5.3 pence per share Saudi Arabia). All KEFI’s projects have
resources which remain open and there is a pipeline of nearby additional exploration
projects with walk-up drill targets.

> **Harry Anagnostaras-Adams, Executive Chairman of KEFI, commented:**
> “During the first quarter of 2022 KEFI has made excellent progress on three now-
> advanced projects in two now-pro-development countries.  This is in stark contrast
> to our situation only months ago when our priority was simply to preserve the 
> Ethiopian project finance syndicate against security challenges and to prove up
> sufficient resources in Saudi Arabia to warrant development.
> “I believe this recent pivot means that the first quarter of 2022 represents KEFI’s
> watershed quarter and the most important since the IPO in 2006.”

**Investor Webinar**

The Company will provide a Quarterly Update presentation via the Investor Meet Company
platform on Friday 8 April 2022 at 3pm London time.

The presentation is open to all existing and potential shareholders. Questions can
be submitted pre-event via your Investor Meet Company dashboard up until 9am the
day before the meeting or at any time during the live presentation.

Investors can sign up to Investor Meet Company for free and add to meet KEFI via:

https://www.investormeetcompany.com/kefi-gold-and-copper-plc/register-investor

Investors who already follow KEFI Gold and Copper on the Investor Meet Company platform
will automatically be invited.

The webinar will subsequently be available on the Company’s website at:

http://www.kefi-minerals.com/news/webcasts.