# KEFI Gold and Copper lifting exploration ambitions in Saudi Arabia and Ethiopia

- Link: https://www.directorstalkinterviews.com/kefi-gold-and-copper-lifting-exploration-ambitions-in-saudi-arabia-and-ethiopia/4121131304
- Published: 2023-10-31T07:14:20+00:00
- Author: Amilia Stone

**KEFI Gold and Copper plc **([LON:KEFI](https://www.directorstalkinterviews.com/company/kefi-gold-and-copper/kefi.l)),
the gold and copper exploration and development company, has focused on the Arabian-
Nubian Shield since 2008, assembling a pipeline of projects in the Kingdom of Saudi
Arabia and in the Federal Democratic Republic of Ethiopia, with the most advanced
being the shovel-ready, high-grade Tulu Kapi Gold Project in Ethiopia which is being
prepared for its launch.

We are pleased to provide this Q3 2023 operational update covering the three months
to 30 September 2023 and more recent developments. This update encompasses the activities
of the Company, as well as wholly owned KEFI Minerals (Ethiopia) Ltd, majority-owned
Tulu Kapi Gold Mines Share Company in Ethiopia, and minority-owned Gold & Minerals
Ltd in Saudi Arabia.

> **Executive Chairman, Harry Anagnostaras-Adams commented:** “KEFI’s third quarter
> was one of our having our heads down clearing many conditions precedent for the
> launch of Tulu Kapi Gold Project in Ethiopia and, likewise in Saudi Arabia, our
> team has continued clearing the checklist for shaping the development plans for
> the Jibal Qutman Gold Project and the Hawiah Gold-Copper Project.
> “Conditions in both of our host countries continue to improve for our industry
> and, whilst one should never discount the challenges in frontier markets, our 
> teams are doing an excellent job, our partners, contractors and financiers are
> working with us closely and supportively and we are driving hard to hit our next
> big milestone which is to trigger before the end of this year the first stage 
> of the  Tulu Kapi Gold Project launch.
> “A sign of our confidence is that we are lifting our exploration ambitions in 
> both Saudi Arabia and Ethiopia, where similar geology presents similar opportunity
> which we have come to understand since entering the Arabian Nubian Shield fifteen
> years ago. Our proprietary database has already helped yield our discoveries and
> we will continue to tackle our exploration pipeline during development of our 
> production projects.
> “We have successfully assembled strong alliances with partners, banks and contractors
> in both countries which, in due course, will demonstrate their importance for 
> KEFI’s growth in terms of both local standing and local financial capacity.”

**ETHIOPIA**

**_Tulu Kapi Gold Project_**

Progress on all fronts maintains the plan to launch the high-grade Tulu Kapi Gold
Project (2.1g/t gold open-pit Ore Reserve plus 5.6g/t gold underground Mineral Resource)
before the end of 2023, and to scale up activities to full construction over the
following months in line with the continued upgrade of security protections and 
preparations of the community. We will go as fast as the conditions on the ground
warrant, to ensure rapid ongoing progress.

The planned US$320 million project financing and launch sequence is being executed
as follows:

o Final credit committee approvals by the mandated development banks are now being
processed after the finalised details of exemptions from exchange and capital controls
were received from the Ethiopia Central Bank earlier this month.

o Upon receipt of final lender approvals, the relevant field, legal, plant and mining
teams will mobilise to concurrently complete:

§ Community resettlement agreements with households, all of which has been planned
in detail with the authorities and international specialist experts;

§ Final procurement agreements for the fixed price process plant and the mining 
fleet, for which the contractors and fabricators are on standby;

§ Detailed definitive documentation between all syndicate members, all of which 
has been drafted; and then

§ Final Board approvals by the equity-capital providers, including the development
banks themselves, regional investors subscribing to equity risk notes and the Federal
and Regional Governments subscribing to share capital at the Ethiopian subsidiary-
level.

The finance plan is summarised as follows:

o   US$320 million: development capital excluding the mining fleet provided by the
mining contractor including:

§ US$190 million: secured debt (senior and mezzanine) from project lenders;

§ US130 million: equity-risk capital (in US$ and Ethiopian Birr as required by the
project), comprising:

·    US$40 million: from the Ethiopian Federal and Regional Government;

·    US$90 million: from KEFI subsidiaries, in turn sourced from Equity-Risk Notes(“
ERN’s”) subscribed by the project lenders and large regional investors, with up 
to half of the ERN’s being convertible into shares of KEFI (at KEFI’s election) 
to be prohibited until Year 4 onwards at then prevailing market share prices.

§ We are also arranging our subsidiary-level funding capacity to cover potential
last-minute capital budgeting refinements such as pricing adjustments for the fixed-
price lump-sum plant components last priced at end 2022.

**SAUDI ARABIA**

**_Jibal Qutman DFS_**

The Jibal Qutman Definitive Feasibility Study (“DFS”) is evaluating the economic
and technical feasibility for building a set of adjacent open-pit mines and a centrally
sited Carbon-in-Leach (“CIL”) processing plant, to recover more than 500,000 ounces
of gold, rather than the 169,000 ounces of gold originally envisaged in the 2015
Preliminary Economic Assessment (“PEA”). The 2015 PEA focused on a small heap-leach
approach as a starter-project when, at that time, planning was based on a gold price
of c.US$1,200/ounce. GMCO also continues to explore for additional resources on 
the same and similar structural belts at this project area.

Key DFS workstreams which have now been completed include:

·    metallurgical and geotechnical drilling;

·    infill drilling to upgrade the resource classification; and

·    metallurgical tests, indicating gold recoveries of c.90% for oxidised ore and
69-74% for fresh ore.

Workstreams progressed during Q3 2023 included:

·    finalisation of geological models to update the Mineral Resource Estimate (“
MRE”);

·    mine planning in more detail;

·    finalisation of processing plant design;

·    analysis of data from a ground magnetics survey and 23 trenches completed during
the quarter, to better define drill targets and also to finalise the location for
site infrastructure; and

·    completion of the initial accommodation and works compound at site.

Whilst the results of in-fill drilling and detailed mine planning are assembled 
for an update to the current MRE, exploration results build our expectation of significant
further growth.

**_Jibal Qutman MRE and Exploration_**

_Resource Consolidation_

Since January 2021, the JQ GMCO team has been working on Resource consolidation 
ahead of the DFS, completing 23,500 metres of diamond drilling which has been predominantly
used on infill, metallurgical and geotechnical programmes.

The 2023 MRE is nearing completion and will be finalised this quarter. The work 
surrounding this MRE has focused predominantly on resource classification upgrade
and firming up grade distributions rather than resource expansion. Once finalised
it will be used to drive the mine design and the subsequent Ore Reserve definition.

_Resource Expansion_

Following the completion of the resource upgrade and support works, drilling is 
now focused on the more then 12 other known mineralised targets within the previously
defined mining licence area as well as the now much larger cumulative 270Km^(2) 
exploration licence area. This larger exploration area hosts the north and south
extensions of the known mineralised structures.

Generative programmes have commenced this quarter to develop targets away from these
defined JQ Resource areas. This exploration has included a ground magnetic survey,
airborne magnetic survey, geological mapping and trenching. The generative work,
whilst still in its infancy, has already allowed for numerous targets to be defined
across the 270Km^(2) area.

Two of the near mine targets are currently undergoing drill testing with encouraging
preliminary results.

1)   The Red Hill 2 prospect.  Located 1 kilometre along strike to the north of 
the main Red Hill resource this target has intersected the continuation of the main
Red Hill thrust package, and identified gold zones extending for more than 185m 
along strike.

This structurally complex area is still being evaluated so true widths cannot be
estimated at this time however, the best trenches within this zone include:

–     JQT_403 intersected 39m at 1.74 g/t Au

–     JQT_404 intersected 27.3m at 2.1g/t Au

Drilling to follow up on these results is underway with early holes JQD161 intersecting
10.23m at 1.0g/t Au and JQD222 intersecting 8.46m at 2.7g/t Au.

2)    At the Asfinga target, which is located around 1km north of the 3K Hill Resource,
four trenches have been opened to evaluate a shear hosted quartz vein. Early assays
from trenching indicate mineralisation over a 150m strike length.

The best trenches within this zone include:

–     JQT_414 intersected 16m at 2.31 g/t Au and 7.5m at 1.8g/t au,

–     JQT_417 intersected 25.7m at 0.71g/t Au and 18.5m at 1.35g/t Au and,

–     JQT_418 intersected 7.95m at 3.8g/t Au

Four diamond drill holes have been completed to follow up on these results with 
assays pending.

**_Jibal Qutman Development Planning_**

The above work is designed to consider the alternatives for scaling the annual production
capacity and then finalise the DFS, to optimise the project development plan, for
approval by GMCO and our project finance lenders in Saudi Arabia. Based on encouragement
from regulators and development financiers, we would then expect that upon GMCO 
resolving its commitment to develop, there will be minimal delay in obtaining a 
mining licence, closing project finance within Saudi Arabia and starting development
in 2024, with the exact timing depending upon these reviews and regulatory processes.

**Hawiah Copper-Gold Project**

**_Hawiah DFS_**

Hawiah sits at the northern end of the 120Km^(2) long Wadi Bidah Metallogenic Belt(
WBMB), in which GMCO has five additional Exploration Licences.

Since the discovery of Hawiah in 2019 GMCO has drilled a total of 80,000 metres 
of diamond core (DD) and 5,500m of Reverse Circulation (RC) drilling and has established
a Mineral Resource Estimate (“MRE”) of 29.0 million tonnes (“Mt”) at 0.89% copper,
0.94% zinc, 0.67g/t gold and 10.1g/t silver (see KEFI announcement dated 9 January
2023). This MRE contains a total of 258,000 tonnes (569 million lbs) of copper, 
272,000 tonnes (600 million lbs) of zinc, 620,000 ounces of gold and 9.4 million
ounces of silver.

Whilst GMCO believes that the current Mineral Resource has further expansion potential,
it already ranks amongst the top three base metal projects in Saudi Arabia and in
the top 15% of VMS (“Volcanogenic Massive Sulphide”) deposits globally by tonnage.

During Q2 2023, KEFI announced the following was achieved by GMCO:

·    a maiden MRE for the nearby (12km from Hawiah) Al Godeyer deposit of 1.35Mt
at 0.6% copper, 0.54% zinc, 1.4g/t gold and 6.6g/t silver (see the Company’s announcement
on 3 April 2023); and

·    Hawiah Pre-Feasibility Study (“PFS”) outcomes on the open-pit and associated
studies on the underground mine (see the Company’s announcement on 28 June 2023).

·    Commencement of the 50,000m drilling programme for resource category upgrade
and expansion.

The full mine development concept is still being finalised, but it is envisaged 
that initial open pit mining will be followed by, and complemented by, an underground
operation. Mining optimisation studies will, in due course, consider a range of 
scenarios including various aggregate production rates and the ideal timing for 
starting-up the underground operation.

Metallurgical test results, based on limited samples to date, indicate that a conventional
processing flowsheet provides good recovery to a c.25% copper concentrate and a 
c.50% zinc concentrate along with gold doré. However, other processing flowsheets
remain under consideration.

Whilst the primary focus of the PFS was limited to the relatively near surface portion
of the MRE within the Indicated Resource category, complementary studies on the 
deeper Inferred portions of the Mineral Resource have allowed a positive internal
preliminary assessment to be made of Hawiah’s economic potential.

**_Hawiah Exploration and resource development_**

In addition to the 50,000m Hawiah infill and expansion programme, GMCO have also
focused on upgrading and expanding the existing Al Godeyer resource (12km west of
Hawiah) through diamond drilling, whilst simultaneously conducting earlier stage
exploration at Abu Salal (50km south of Hawiah) and mapping within the wider WBMB
project area.  

_Al Godeyer_

The first phase of the 2023 Al Godeyer drilling programme, which was completed in
August, aimed at upgrading the maiden MRE and brings the project total meters to
4,230m of DD and 1,700m of RC drilling. A follow up phase of drilling is planned
to commence following receipt and interpretation of pending assays with the target
continuing to be the upgrade and expansion of the 1.35Mt Inferred Mineral Resource
to an c.2Mt Mineral Resource at an Indicated classification. This would allow the
defined Resources to support the planned Hawiah DFS, as a satellite open-pit. 

_Abu Salal_

At Abu Salal, a total of 30 trenches have been excavated across the gossanous horizons
which outcrop discontinuously over a 5km strike. Thicknesses of the logged gossans
have ranged from 12-13 metres down to 0.5 meters, with multiple horizons intersected
in several trenches. Assay results have been received for 17 of the trenches which
indicates consistent gold mineralisation within the gossans. Gold grades reached
up to a maximum of 3.01 g/t over a five-meter interval in AST_002, with an average
of 0.6 g/t across all gossan intervals. Copper and zinc have been noted on the flanks
of the gossan with grades of up to 5% copper noted in AST_017, indicating the presence
of base metals at depth.

The culmination of the geological mapping, self-potential (SP) geophysics and the
logging and these new trench results have clearly demonstrated the potential for
massive sulphide mineralisation within a westward dipping sequence in meta-volcanics,
with a similar presentation to that of Hawiah and Al Godeyer.

An initial 2,000m scout drilling programme at Abu Salal commenced in late September
to test key areas of the outcropping gossans at depth for thickness and grade. The
historic mineral occurrence at Abu Salal has never been subjected to systematic 
exploration or subjected to any form of drilling.

**KEFI GROUP**

**_Group Development Plan_**

·    The planned KEFI Group project development sequencing remains as follows:

o 2023 trigger of staged launch of Tulu Kapi open-pit development in Ethiopia for
build-up to full construction over the following few months, commissioning production
end-2025 based on 2023 reserves and resources;

o 2024 launch Jibal Qutman open-pit development in Saudi Arabia based on 2023/24
reserves and resources and targeting first production 2026;

o 2025-26 launch of the Hawiah open-pit in Saudi Arabia for first production to 
follow that in Tulu Kapi and Jibal Qutman; and

o 2026 and thereafter launch of underground mine development at Tulu Kapi and at
Hawiah for first production two years later.

**_Group Metrics_**

Aggregate Mineral Resources across all three projects are 4.7 million ounces of 
gold-equivalent in-situ, of which KEFI’s beneficial interest is 2.0 million ounces.

Aggregate annual production from the three advanced projects is currently projected
at 326,000 ounces of gold-equivalent, of which 148,000 ounces is KEFI’s beneficial
interest, over an initial seven-year period.

The Tulu Kapi open pit is already bankable with a 1 million ounce Ore Reserve. Combined
with the first preliminary planned 250,000 ounce minable resource contribution from
the underground mine.  Tulu Kapi is planned to produce c.144,000 ounces gold per
annum at start-up throughput rate. By lifting process-plant throughput by 20% to
2.4Mtpa, production would be c. 165,000 gold per annum at an All-In-Sustaining Costs
of c.US$900 per ounce, assuming a gold price of US$1,600-2,000 per ounce. At those
same prices, this provides Net Operating Cash Flow of US$112-156 million per annum(
100% basis) for the first seven full years of production (2026-2032).

**_Group Working Capital_**

KEFI has working capital in place to underpin its planned runway to the intended
launch of the Tulu Kapi Project finance in the coming months.

This follows the Company’s repayment of all debts in June 2023 upon completing an
equity placing that raised gross proceeds of £7.2 million via a £5.5 million Firm
Placing, £0.7 million Conditional Subscription, £0.24 million Retail Offer and £
0.75 million Issue of Remuneration Shares in lieu of cash to senior executives. 
The issue of the Conditional Subscription, Retail Offer and Remuneration Shares 
were approved at the Company’s Annual General Meeting on 30 June 2023 and these 
shares have subsequently been issued.

**Group Exploration Project Pipeline**

**_Ethiopia Project Pipeline_**

We have registered a number of applications for new exploration licences. In addition,
we have commenced administrative proceedings in respect of our long-standing proximal
Exploration Licenses (“ELs”) surrounding the Tulu Kapi Project Mining Licence area,
in order to continue exploration programmes and community development which have
always complemented the Tulu Kapi project. During an overhaul of the title-regulatory
system in 2022, these ELs were over-pegged by a Hong Kong shell company owned by
a British Virgin Islands shell company.  We are confident that this situation can
be resolved satisfactorily.

**_Saudi Project Pipeline_**

Following the expansion of GMCO’s exploration portfolio to 15 ELs covering four 
project areas of more than 1,000km^(2), regional exploration teams have mobilised
to the new ELs. As was the case at Jibal Qutman and Hawiah, many of these ELs have
abundant evidence of historical workings and surface expression of mineralisation.

GMCO has begun comprehensive mapping and sampling campaigns over the newly awarded
licences. The outcomes of this fieldwork will be to ground-truth historical data,
assess the surface mineralisation and describe the structural framework controlling
mineralisation. These programmes are expected to build into progressively advanced
exploration works, including geophysics and trenching.

During the quarter, regional sampling of the Umm Al Khabath EL (located at the southern
end of the Wadi Bidah Mineral Belt) returned anomalous gold and base metals. These
results strongly support the interpretation that the Umm Al Khabath EL contains 
VMS style mineralisation, commonly found in the Wadi Bidah.

**INVESTOR WEBINAR**

The next open-forum investor webinar will be held in early December 2023 to coincide
with the planned Ethiopian Government’s MineExpo and will focus on Tulu Kapi Project
Syndicate activities and announcements. Details of these two events will be announced
in due course.